[Federal Register: January 17, 2003 (Volume 68, Number 12)]
[Notices]
[Page 2532-2533]
From the Federal Register Online via GPO Access [wais.access.gpo.gov]
[DOCID:fr17ja03-50]
-----------------------------------------------------------------------
DEPARTMENT OF DEFENSE
Department of the Army; Corps of Engineers
Intent To Prepare a Draft Environmental Impact Statement for the
Mid-Chesapeake Bay Island, MD, Environmental Restoration Feasibility
Study
AGENCY: Department of the Army, U.S. Army Corps of Engineers, DoD.
ACTION: Notice of intent.
-----------------------------------------------------------------------
SUMMARY: The Baltimore District, U.S. Army Corps of Engineers (Corps)
in partnership with the State of Maryland Department of Transportation,
Maryland Port Administration has initiated an environmental restoration
feasibility study for the restoration of island habitat in the Mid-
Chesapeake Bay region. The study focuses on restoring hundreds of acres
of aquatic and wildlife island habitat in the Mid-Chesapeake Bay region
through the beneficial use of dredged materials from the Port of
Baltimore channel system. As part of this study and in accordance with
the National Environmental Policy Act (NEPA) of 1969, an Environmental
Impact Statement (EIS) will be prepared to document the plan
formulation process and recommendations of this study.
FOR FURTHER INFORMATION CONTACT: Questions or information about the
proposed action and draft EIS can be addressed to Ms. Michele (Mimi)
Bistany, U.S. Army Corps of Engineers, ATTN: CENAB-PL, 10 South Howard
Street, P.O. Box 1715, Baltimore, MD 21203-1715, telephone 410-962-
4934; e-mail address: michele.a.bistany@usace.army.mil.
SUPPLEMENTARY INFORMATION: The Mid-Chesapeake Bay study area is defined
by the confluence of the Chester River south to the confluence of the
Potomac River with the Chesapeake Bay, Maryland.
Land subsidence, rising sea level, and wave action have caused
valuable island habitats to be lost through erosion throughout the
Chesapeake Bay. Through the beneficial use of dredged material, a
restored island can be constructed to replace hundreds of acres of
wetland and upland habitat. Therefore, the goal for this feasibility
study is to restore valuable aquatic and terrestrial resting, foraging,
and nursery habitat that has been lost in the Chesapeake Bay for many
migratory birds, fish, and wildlife species through the beneficial use
of dredged material. This habitat will afford improved productivity to
the surrounding area, while providing an environmentally sound method
for the use of dredged material removed from Bay channels.
Corps feasibility studies are conducted using a six-stage planning
approach that incorporates the NEPA process: (1) Identify problems,
opportunities, goals, and objectives; (2) Inventory baseline
conditions; (3) Formulate alternatives; (4) Evaluate effects of the
alternatives; (5) Compare alternatives; and (6) Select a recommended
plan or set of alternative plans that are environmentally,
economically, and engineering sound.
The project delivery team is actively seeking public opinion,
participation, and advice to be incorporated into the planning process
and the selection of an island for restoration. At this time, the
islands that are under consideration within the Mid-Chesapeake Bay
region include Barren, Bloodsworth, James, Holland, Lower Eastern Neck,
Parson's and Sharp's islands. The team is open to any additional
islands for consideration in the Mid-Bay region. As part of the initial
phase of the study, an objective screening criteria will be developed
based on information obtained for the State of Maryland's Dredged
Material Management Program, public and agency input, available data,
and best professional judgment. Following the Corps and NEPA processes,
once the island is selected for restoration, a detailed analysis of the
current existing conditions will be undertaken; alternative restoration
plans will be developed, analyzed and compared; the impacts of those
plans
[[Page 2533]]
will be analyzed; and a recommended plan will be selected.
To solicit public input into the study and into the island
selection, up to three public scoping meetings are planned for the late
January/early February 2003 timeframe. A newsletter broadcasting the
dates, times, and locations will be sent to agencies, groups and
individuals on the study's mailing list once the meetings have been
scheduled. To verify your inclusion, or to be added in the mailing
list, please contact the study team leader, Ms. Michele Bistany (see
FOR FURTHER INFORMATION CONTACT).
The study will be conducted in compliance with Section 404 and
Section 401 of the Clean Water Act, Section 7 of the Endangered Species
Act, the Clean Air Act, the U.S. Fish and Wildlife Coordination Act,
Section 106 of the National Historic Preservation Act, Prime and Unique
Farmlands, the Magnuson-Stevens Fishery Conservation and Management
Act, and National Pollutant Discharge Elimination System Act. All
appropriate documentation (i.e., Section 7, Section 106 coordination
letters, and public and agency comments) will be obtained and included
as part of the EIS.
As part of the EIS process, recommendations will be based on an
evaluation of the probable impact of the proposed activity on the
public interest. The decision will reflect the national concern for the
protection and utilization of important resources. The benefit, which
may reasonably be expected to accrue from the proposal, will be
balanced against its reasonably foreseeable detriments. All factors
that may be relevant to the proposal will be considered, among these
are wetlands; fish and wildlife resources; cultural resources; land
use; water and air quality; hazardous, toxic, and radioactive
substances; threatened and endangered species; regional geology;
aesthetics; environmental justice; cumulative impacts; and the general
needs and welfare of the public.
The draft EIS for the Mid-Chesapeake Bay Island environmental
restoration study is expected for public release in July 2005.
Robert W. Lindner,
Chief, Planning Division.
[FR Doc. 03-1112 Filed 1-16-03; 8:45 am]
BILLING CODE 3710-41-M