[Federal Register: August 19, 2003 (Volume 68, Number 160)]
[Rules and Regulations]               
[Page 49845-49972]
From the Federal Register Online via GPO Access [wais.access.gpo.gov]
[DOCID:fr19au03-17]                         
 

[[Page 49845]]

-----------------------------------------------------------------------

Part II





Department of Energy





-----------------------------------------------------------------------



Federal Energy Regulatory Commission



-----------------------------------------------------------------------



18 CFR Part 35



Standardization of Generator Interconnection Agreements and Procedures; 
Final Rule


[[Page 49846]]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

18 CFR Part 35

[Docket No. RM02-1-000; Order No. 2003]

 
Standardization of Generator Interconnection Agreements and 
Procedures

July 24, 2003.
AGENCY: Federal Energy Regulatory Commission, DOE.

ACTION: Final rule.

-----------------------------------------------------------------------

SUMMARY: The Federal Energy Regulatory Commission (Commission) is 
amending its regulations under the Federal Power Act to require public 
utilities that own, control, or operate facilities for transmitting 
electric energy in interstate commerce to file revised open access 
transmission tariffs containing standard generator interconnection 
procedures and a standard agreement that the Commission is adopting in 
this order and to provide interconnection service to devices used for 
the production of electricity having a capacity of more than 20 
megawatts, under them. Any non-public utility that seeks voluntary 
compliance with the reciprocity condition of an open access 
transmission tariff may satisfy this condition by adopting these 
procedures and this agreement.

EFFECTIVE DATE: This final rule will become effective October 20, 2003.

FOR FURTHER INFORMATION CONTACT: 
Patrick Rooney (Technical Information), Office of Market, Tariffs 
and Rates, Federal Energy Regulatory Commission, 888 First Street, 
NE., Washington, DC 20426, (202) 502-6205.
Roland Wentworth (Technical Information), Office of Market, Tariffs 
and Rates, Federal Energy Regulatory Commission, 888 First Street, 
NE., Washington, DC 20426, (202) 502-8262.
Bruce Poole (Technical Information), Office of Market, Tariffs and 
Rates, Federal Energy Regulatory Commission, 888 First Street, NE., 
Washington, DC 20426, (202) 502-8468.
Michael G. Henry (Legal Information), Office of the General Counsel, 
Federal Energy Regulatory Commission, 888 First Street, NE., 
Washington, DC 20426, (202) 502-8532.

SUPPLEMENTARY INFORMATION:

Table of Contents

I. Introduction
    A. Background
    1. Need for Standard Generator Interconnection Procedures and 
Agreement
    2. Interconnection ANOPR
    3. Interconnection NOPR
    a. Overview of the NOPR
    b. Severing of Small Generator Issues from the NOPR
    B. Legal Authority
    1. The Federal Power Act and Order No. 888
    2. Commission Interconnection Case Law
    C. Differences Between the Proposed and Final Rules
II. Discussion
    A. Issues Related to the Standard Large Generator Interconnection 
Procedures (LGIP)
    1. Overview
    2. Section-by-Section Discussion of the Proposed LGIP
    Section 1--Definitions
    Section 2--Scope and Application
    Section 3--Interconnection Request
    Section 4--Queue Position
    Section 5--Procedures for Interconnection Requests Submitted Prior 
to Effective Date of Interconnection Procedures
    Section 6--Interconnection Feasibility Study
    Section 7--Interconnection System Impact Study
    Section 8--Interconnection Facilities Study
    Section 10--Optional Interconnection Study
    Section 9--Engineering & Procurement (``E&P'') Agreement
    Section 11--Standard Large Generator Interconnection Agreement
    Section 12--Construction of Transmission Provider's Interconnection 
Facilities and Network Upgrades
    Section 13--Miscellaneous
    Appendices
    B. Issues Related to the Standard Large Generator Interconnection 
Agreement (LGIA)
    1. Overview
    2. Article-by-Article Discussion of the Proposed LGIA
    Article 1--Definitions
    Article 2--Effective Date, Term and Termination
    Article 3--Regulatory Filings
    Article 4--Scope of Service
    Article 5--Interconnection Facilities Engineering, Procurement, and 
Construction
    Article 6--Testing and Inspection
    Article 7--Metering
    Article 8--Communication
    Article 9--Operations
    Article 10--Maintenance
    Article 11--Performance Obligation
    Article 12--Invoice
    Article 13--Emergencies
    Article 14--Regulatory Requirements and Governing Law
    Article 15--Notices
    Article 16--Force Majeure
    Article 17--Default
    Article 18--Indemnity
    Article 19--Assignment
    Article 20--Severability
    Article 21--Comparability
    Article 22--Confidentiality
    Article 23--Environmental Releases
    Article 24--Information Requirements
    Article 25--Information Access and Audit Rights
    Article 26--Subcontractors
    Article 27--Disputes
    Article 28--Representations, Warranties and Covenants
    Article 29--Joint Operating Committee
    Article 30--Miscellaneous
    Appendices
    C. Other Significant Policy Issues
    1. Interconnection Pricing Policy
    Concerns about the Fairness and Efficiency of the Commission's 
Crediting Policy
    Interconnection Pricing and the Transition to Standard Market 
Design
    The Inability of a Transmission Owner To Recover the Costs of 
Network Upgrades
    Responsibility for Line Outage Costs Resulting from Interconnection
    Issues Concerning the Five Year Refund Period and the Payment of 
Interest
    Rules Governing the Payment of Credits
    Responsibility for the Costs Incurred by Affected Systems
    Policies Regarding Previously Approved Cost Allocations and Pricing 
Arrangements
    Miscellaneous Pricing Issues
    2. Interconnection Products and Scope of Service
    Definition of Interconnection Products
    Pricing of Network Resource Interconnection Service
    Study Requirements for Network Resource Interconnection Service
    Identification of Types of Interconnection Services to be Studied
    Revisions to the Final Rule LGIP and Final Rule LGIA
    3. ``Distribution'' Interconnections
    4. Issues Relating to Qualifying Facilities
    5. Variations from the Final Rule
    6. Waiver Availability for Small Entities
    7. OATT Reciprocity Requirements Applied to the Final Rule LGIP and 
Final Rule LGIA
    8. General Comments/Clarifications
    a. Insurance
    b. Liquidated Damages

[[Page 49847]]

    c. Consequential Damages
    d. Two vs. Three Party Agreements
    D. Compliance Issues
    1. Amendments to Transmission Providers' OATTs
    2. Grandfathering of Existing Interconnection Agreements (ISOs and 
non-ISOs)
    3. Order No. 2001 and the Filing of Interconnection Agreements
III. Information Collection Statement
IV. Environmental Impact Statement
V. Regulatory Flexibility Act
VI. Document Availability
VII. Effective Date and Congressional Notification
Regulatory Text
Appendix A--Flow Chart of the Large Generating Facility Interconnection 
Process
Appendix B--Commenter Acronyms
Appendix C--Standard Large Generator Interconnection Procedures (LGIP), 
including Standard Large Generator Interconnection Agreement (LGIA)
    Before Commissioners: Pat Wood, III, Chairman; William L. Massey, 
and Nora Mead Brownell.

I. Introduction

    1. This Final Rule requires all public utilities that own, control 
or operate facilities used for transmitting electric energy in 
interstate commerce to have on file standard procedures and a standard 
agreement for interconnecting generators larger than 20 MW. The 
Commission expects that this Final Rule will prevent undue 
discrimination, preserve reliability, increase energy supply, and lower 
wholesale prices for customers by increasing the number and variety of 
new generation that will compete in the wholesale electricity market.
    2. This Final Rule requires public utilities that own, control, or 
operate facilities for transmitting electric energy in interstate 
commerce to file revised open access transmission tariffs (OATTs) to 
add Standard Large Generator Interconnection Procedures (Final Rule 
LGIP)\1\ and a Standard Large Generator Interconnection Agreement 
(Final Rule LGIA).\2\ Any non-public utility that seeks voluntary 
compliance with the reciprocity condition of an open access 
transmission tariff may satisfy this condition by adopting this 
Agreement and these procedures.
---------------------------------------------------------------------------

    \1\ Readers may note that provisions of the Final Rule LGIP are 
referred to as ``Sections'' whereas provisions of the Final Rule 
LGIA are referred to as ``Articles.''
    \2\ Such filings must be made within 60 days of publication of 
this Final Rule in the Federal Register.
---------------------------------------------------------------------------

    3. The Final Rule LGIP sets forth the procedures that 
Interconnection Customers and Transmission Providers are required to 
follow during the interconnection process.\3\ The Final Rule LGIA sets 
forth the legal rights and obligations of each Party, addresses cost 
responsibility issues, and establishes a process for resolving 
disputes.
---------------------------------------------------------------------------

    \3\ Unless otherwise defined in this Preamble, capitalized terms 
used in this Final Rule have the meanings specified in Section 1 of 
the Final Rule LGIP and Article 1 of the Final Rule LGIA. The term 
Generating Facility means the specific device for which the 
Interconnection Customer has requested interconnection. The owner of 
the Generating Facility is referred to as the Interconnection 
Customer. The entity (or entities) with which the Generating 
Facility is interconnecting is referred to as the Transmission 
Provider. The term Large Generator is intended to refer to any 
energy resource having a capacity of more than 20 megawatts, or the 
owner of such a resource.
---------------------------------------------------------------------------

    4. The Federal Energy Regulatory Commission's (Commission's) 
authority to require the addition of the Final Rule LGIA and Final Rule 
LGIP to the OATT derives from its findings of undue discrimination in 
the interstate electric transmission market that formed the basis for 
Order No. 888.\4\ The Commission here adopts standard procedures and a 
standard agreement to be used by Transmission Providers with 
Interconnection Customers proposing to interconnect a generator of more 
than 20 MW to sell energy at wholesale in interstate commerce. The 
Final Rule LGIP and Final Rule LGIA apply to any new Interconnection 
Request to a Transmission Provider's Transmission System.\5\ The 
Commission is not requiring any retroactive changes to individual 
(versus generic) interconnection agreements filed with the Commission 
prior to the effective date of this Final Rule.
---------------------------------------------------------------------------

    \4\ Promoting Wholesale Competition Through Open Access Non-
Discriminatory Transmission Services by Public Utilities; Recovery 
of Stranded Costs by Public Utilities and Transmitting Utilities, 
Order No. 888, 61 FR 21540 (May 10, 1996), FERC Stats. & Regs. ] 
31,036 (1996), order on reh'g, Order No. 888-A, 62 FR 12274 (Mar. 
14, 1997), FERC Stats. & Regs. ] 31,048 (1997), order on reh'g, 
Order No. 888-B, 81 FERC ] 61,248 (1997), order on reh'g, Order No. 
888-C, 82 FERC ] 61,046 (1998), aff'd in relevant part sub nom. 
Transmission Access Policy Study Group v. FERC, 225 F.3d 667 (DC 
Cir. 2000), aff'd sub nom. New York v. FERC, 535 U.S. 1 (2002).
    \5\ New Interconnection Requests include those submitted after 
the effective date of this Final Rule and include requests to 
increase the capacity of, or modify the operating characteristics 
of, an existing Generating Facility that is interconnected with the 
Transmission Provider's Transmission System.
---------------------------------------------------------------------------

A. Background

    5. The electric power industry continues to be in transition. Where 
the industry once comprised mainly large, vertically integrated 
utilities providing bundled power at cost-based rates, companies 
selling unbundled wholesale power at rates set by competitive markets 
have now become common. Balanced market rules and sufficient 
infrastructure are essential for achieving power markets that will 
provide customers with reasonably priced and reliable service.
    6. The Commission continues to work to encourage fully competitive 
bulk power markets. The effort took its first major step with Order No. 
888, which required public utilities to provide other entities 
comparable access to their facilities for transmitting electricity in 
interstate commerce, and continued with Order No. 2000,\6\ which 
encouraged the development of Regional Transmission Organizations 
(RTOs).
---------------------------------------------------------------------------

    \6\ Regional Transmission Organizations, Order No. 2000, 65 FR 
810 (Jan. 6, 2000), FERC Stats. & Regs. ] 31,089 (1999), order on 
reh'g, Order No. 2000-A, 65 FR 12,088 (Mar. 8, 2000), FERC Stats. & 
Regs. ] 31,092 (2000), aff'd sub nom. Public Util. Dist. No. 1 v. 
FERC, 272 F.3d 607 (DC Cir. 2001).
---------------------------------------------------------------------------

    7. In this proceeding the Commission, pursuant to its 
responsibility under Sections 205 and 206 of the Federal Power Act 
(FPA) to remedy undue discrimination, requires all public utilities 
that own, control, or operate facilities for transmitting electric 
energy in interstate commerce to append to their OATTs a Final Rule 
LGIP and Final Rule LGIA. The Commission believes that these documents 
will provide just and reasonable terms and conditions of transmission 
service while ensuring that reliability is protected and that they will 
provide a reasonable balance between the competing goals of uniformity 
and flexibility.
1. Need for Standard Generator Interconnection Procedures and Agreement
    8. In April 1996, in Order No. 888, the Commission established the 
foundation necessary to develop competitive bulk power markets in the 
United States: non-discriminatory open access transmission services by 
public utilities and stranded cost recovery rules to provide a fair 
transition to competitive markets. Order No. 888 did not directly 
address generator interconnection issues.
    9. In Tennessee Power Company \7\ (Tennessee) the Commission 
clarified that interconnection is a critical component of open access 
transmission service and thus is subject to the requirement that 
utilities offer comparable service under the OATT. In Tennessee the 
Commission encouraged, but did not require, each Transmission Provider 
to revise its OATT to include interconnection procedures, including a

[[Page 49848]]

standard interconnection agreement and specific criteria, procedures, 
milestones, and time lines for evaluating Interconnection Requests.\8\
---------------------------------------------------------------------------

    \7\ Tennessee Power Company, 90 FERC ] 61,238 (2002).
    \8\ See, e.g., Commonwealth Edison Co., 91 FERC ] 61,083 (2000).
---------------------------------------------------------------------------

    10. The Commission to date has addressed interconnection issues on 
a case-by-case basis. Although a number of Transmission Providers have 
filed interconnection procedures as part of their OATTs,\9\ many 
industry participants remain dissatisfied with existing interconnection 
policy and procedures. With the increasing number of interconnection-
related disputes, it has become apparent that the case-by-case approach 
is an inadequate and inefficient means to address interconnection 
issues.
---------------------------------------------------------------------------

    \9\ See, e.g., American Electric Power Service Corp., 91 FERC ] 
61,308 (2000), order denying reh'g and granting clarification, 94 
FERC ] 61,166, order dismissing request for clarification, 95 FERC ] 
61,130 (2001), appeal docketed sub nom. Tenaska, Inc. v. FERC, No. 
01-1194 (DC Cir. Apr. 23, 2001); Southwest Power Pool, Inc., 92 FERC 
] 61,109 (2000); Carolina Power & Light Co., 93 FERC ] 61,032 
(2000), reh'g denied, 94 FERC ] 61,165 (2001), appeal docketed sub 
nom. Tenaska, Inc. v. FERC, No. 01-1195 (DC Cir. Apr. 23, 2001); 
Virginia Electric & Power Co., 93 FERC ] 61,307 (2000), order on 
clarification, 94 FERC ] 61,045, reh'g denied, 94 FERC ] 61,164 
(2001), appeal docketed sub nom. Tenaska, Inc. v. FERC, No. 01-1196 
(DC Cir. Apr. 23, 2001); Consumers Energy Co., 93 FERC ] 61,339 
(2000), order on reh'g and clarification, 94 FERC ] 61,230, order on 
clarification and denying reh'g, 95 FERC ] 61,131 (2001).
---------------------------------------------------------------------------

    11. Interconnection plays a crucial role in bringing much-needed 
generation into the market to meet the growing needs of electricity 
customers. Further, relatively unencumbered entry into the market is 
necessary for competitive markets. However, requests for 
interconnection frequently result in complex, time consuming technical 
disputes about interconnection feasibility, cost, and cost 
responsibility. This delay undermines the ability of generators to 
compete in the market and provides an unfair advantage to utilities 
that own both transmission and generation facilities. The Commission 
concludes that there is a pressing need for a single set of procedures 
for jurisdictional Transmission Providers and a single, uniformly 
applicable interconnection agreement for Large Generators.\10\ A 
standard set of procedures as part of the OATT for all jurisdictional 
transmission facilities will minimize opportunities for undue 
discrimination and expedite the development of new generation, while 
protecting reliability and ensuring that rates are just and reasonable.
---------------------------------------------------------------------------

    \10\ In another rulemaking, the Commission proposes a separate 
set of procedures and an agreement applicable to Small Generators 
(any energy resource having a capacity of no larger than 20 MW, or 
the owner of such a resource) that seek to interconnect to 
jurisdictional Transmission Providers. See Standardization of Small 
Generator Interconnection Agreements and Procedures, Notice of 
Proposed Rulemaking, Docket No. RM02-12-000 (issued concurrently 
with this Final Rule). 104 FERC ] 61,104.
---------------------------------------------------------------------------

    12. Interconnection is a critical component of open access 
transmission service, and standard interconnection procedures and a 
standard agreement applicable to Large Generators will serve several 
important functions: They will (1) Limit opportunities for Transmission 
Providers to favor their own generation, (2) facilitate market entry 
for generation competitors by reducing interconnection costs and time, 
and (3) encourage needed investment in generator and transmission 
infrastructure. The Commission expects that the Final Rule LGIP and 
Final Rule LGIA (as well as the documents that will be developed in the 
Small Generator Interconnection proceeding--see footnote 10, supra) 
will resolve most disputes, minimize opportunities for undue 
discrimination, foster increased development of economic generation, 
and protect system reliability. Therefore, the Commission adopts the 
Final Rule LGIP and Final Rule LGIA, which will be required as an 
amendment to the OATT of each public utility that owns, controls, or 
operates facilities for transmitting electric energy in interstate 
commerce. As discussed below, more flexibility is available to 
independent transmission entities in the procedures and agreement they 
must adopt as compared with the standard provisions adopted herein.
2. Interconnection ANOPR
    13. The Commission issued an Advance Notice of Proposed Rulemaking 
(ANOPR) regarding generator interconnection on October 25, 2001.\11\ As 
a point of departure, the ANOPR presented the Standard Generator 
Interconnection Procedures and Standard Generation Interconnection 
Agreement of the Electric Reliability Council of Texas (ERCOT).\12\ The 
Commission supplemented and modified the ERCOT documents with various 
``best practices'' that were identified in Attachment A to the ANOPR. 
These ``best practices'' were based, in part, on generator 
interconnection procedures and agreements that had been approved by the 
Commission in past cases. The ANOPR instructed the commenters and 
parties to assume that the Commission's current pricing policy, as 
described in ANOPR Attachment B, would remain in effect.
---------------------------------------------------------------------------

    \11\ Standardizing Generator Interconnection Agreements and 
Procedures, Advance Notice of Proposed Rulemaking, 66 FR 55140 (Nov. 
1, 2001), FERC Stats. & Regs. ] 35,540 (2001).
    \12\ The ERCOT agreement and procedure were appended to the 
ANOPR as Appendix A.
---------------------------------------------------------------------------

    14. The ANOPR initiated a consensus-making process in which members 
of various segments of the electric power industry, government, and the 
public had an opportunity to provide input. This effort resulted in two 
documents that largely shaped the Notice of Proposed Rulemaking (Large 
Generator Interconnection NOPR) that followed.\13\ These two documents 
are referred to as the Consensus LGIP and Consensus LGIA (although a 
consensus was not reached on all issues). The Commission received 
numerous comments, primarily from Transmission Providers, Transmission 
Owners, generators (herein called Interconnection Customers), and state 
regulators, on the ANOPR and the Consensus LGIP and Consensus LGIA.
---------------------------------------------------------------------------

    \13\ Standardization of Generator Interconnection Agreements and 
Procedures, Notice of Proposed Rulemaking, 67 FR 22250 (May 2, 
2002), FERC Stats. & Regs. ] 32,560 (2002).
---------------------------------------------------------------------------

3. Interconnection NOPR
a. Overview of the NOPR
    15. Although the negotiators did not reach consensus on every 
issue, the Consensus LGIP and LGIA reflect substantial agreement among 
diverse interests. The Commission used these documents and the comments 
on them to create the proposed standard LGIP and LGIA documents (NOPR 
LGIP and NOPR LGIA). Generally, the NOPR used the Consensus LGIP and 
LGIA provisions where there was agreement. Where the participants could 
not reach consensus on a particular issue and options were presented in 
the Consensus LGIP and LGIA, the Commission chose between those options 
guided by the principle of minimizing barriers to entry of new 
generation without increasing the risk of reliability problems. Where 
an issue remained unresolved and no option was presented, the 
Commission generally proposed the ERCOT provision.
b. Severing of Small Generator Issues From the NOPR
    16. In their comments on the interconnection NOPR, supporters of 
Small Generators (which are defined herein as devices for the 
production of electricity having a capacity no more than 20 MW) 
requested that the Commission adopt separate rules and procedures for 
interconnecting Small Generators. They argued that use of a Final Rule 
LGIP and Final Rule LGIA

[[Page 49849]]

designed for Large Generators would unduly hinder the development of 
Small Generators. They sought streamlined procedures and requirements 
that would allow an Interconnection Customer with a Small Generator to 
avoid delays caused by studying sequentially the effects of 
interconnecting its generator with the Transmission Provider's electric 
system.
    17. Persuaded by this request, the Commission decided to propose 
separate Small Generator interconnection procedures and an agreement 
(SGIP and SGIA) to provide the right incentives for both Transmission 
Providers and Interconnection Customers with Small Generators.\14\ To 
that end, the Commission severed the issues related to interconnecting 
generators no larger than 20 MW from this proceeding and initiated 
another rulemaking docket, RM02-12-000, for the former.\15\
---------------------------------------------------------------------------

    \14\ The Small Generator Interconnection ANOPR proposed adopting 
two Small Generator Interconnection Procedures documents and two 
Small Generator Interconnection Agreements, with the distinction 
between the two sets of documents being the size of the Small 
Generator.
    \15\ See Standardization of Small Generator Interconnection 
Agreements and Procedures, Advance Notice of Proposed Rulemaking, 67 
FR 54749 (Aug. 26, 2002), FERC Stats. & Regs. ] 35,544 (2002).
---------------------------------------------------------------------------

B. Legal Authority

1. The Federal Power Act and Order No. 888
    18. In fulfilling its responsibilities under Sections 205 and 206 
of the Federal Power Act,\16\ the Commission is required to address, 
and has the authority to remedy, undue discrimination. The Commission 
must ensure that the rates, contracts, and practices affecting 
jurisdictional transmission do not reflect an undue preference or 
advantage for non-independent Transmission Providers and are just and 
reasonable. Additionally, as discussed in Order No. 888, the 
Commission's regulatory authority under the Federal Power Act ``clearly 
carries with it the responsibility to consider, in appropriate 
circumstances, the anticompetitive effects of regulated aspects of 
interstate utility operations pursuant to [FPA] Sections 202 and 203, 
and under like directives contained in Sections 205, 206, and 
207.''\17\
---------------------------------------------------------------------------

    \16\ 16 U.S.C. 824d, 824e (2000).
    \17\ Gulf States Utils. Co. v. FPC, 411 U.S. 747, 758-59 (1973); 
see City of Huntingburg v. FPC, 498 F.2d 778, 783-84 (D.C. Cir. 
1974) (noting the Commission's duty to consider the potential 
anticompetitive effects of a proposed interconnection agreement).
---------------------------------------------------------------------------

    19. The record underlying Order No. 888 showed that public 
utilities owning or controlling jurisdictional transmission facilities 
had the incentive to engage in, and had engaged in, unduly 
discriminatory transmission practices.\18\ The Commission in Order No. 
888 also thoroughly discussed the legislative history and case law 
involving Sections 205 and 206, concluded that it had the authority and 
responsibility to remedy the undue discrimination it had found by 
requiring open access, and decided to do so through a rulemaking on a 
generic, industrywide basis.\19\ The Supreme Court affirmed the 
Commission's decision to exercise this authority by requiring non-
discriminatory (comparable) open access as a remedy for undue 
discrimination.\20\
---------------------------------------------------------------------------

    \18\ Order No. 888, FERC Stats. Regs ] 31,036 at 31,679-84; 
Order No. 888-A, FERC Stats. & Regs ] 31,048 at 30,209-10.
    \19\ Order No. 888, FERC Stats. & Regs ] 31,036 at 31,668-73, 
31,676-79; Order No. 888-A, FERC Stats. & Regs ] 31,048 at 30,201-
12; TAPS v. FERC, 225 F.3d 667, 687-88 (DC Cir. 2000).
    \20\ New York v. FERC, 535 U.S. 1 (2002).
---------------------------------------------------------------------------

    20. The Commission has identified interconnection as an element of 
transmission service that is required to be provided under the 
OATT.\21\ Thus, the Commission may order generic interconnection terms 
and procedures pursuant to its authority to remedy undue discrimination 
and preferences under Sections 205 and 206 of the Federal Power Act.
---------------------------------------------------------------------------

    \21\ See Tennessee Power Co., 90 FERC ] 61,238 at 61,761, reh'g 
dismissed, 91 FERC ] 61,271 (2000).
---------------------------------------------------------------------------

2. Commission Interconnection Case Law
    21. Unless expressly changed in this Final Rule, the holdings in 
the Commission's existing interconnection precedents will remain a 
useful guide during the implementation of this Final Rule. The 
Commission's interconnection cases have drawn the distinction between 
Interconnection Facilities and Network Upgrades. Interconnection 
Facilities are found between the Interconnection Customer's Generating 
Facility and the Transmission Provider's Transmission System. The 
Commission has developed a simple test for distinguishing 
Interconnection Facilities from Network Upgrades: Network Upgrades 
include only facilities at or beyond the point where the 
Interconnection Customer's Generating Facility interconnects to the 
Transmission Provider's Transmission System.\22\ The Commission has 
made clear that Interconnection Agreements are evaluated by the 
Commission according to the just and reasonable standard.\23\ Most 
improvements to the Transmission System, including Network Upgrades, 
benefit all transmission customers, but the determination of who 
benefits from such Network Upgrades is often made by a non-independent 
transmission provider, who is an interested party. In such cases, the 
Commission has found that it is just and reasonable for the 
Interconnection Customer to pay for Interconnection Facilities but not 
for Network Upgrades. Agreements between the Parties to classify 
Interconnection Facilities as Network Upgrades, or to otherwise 
directly assign the costs of Network Upgrades to the Interconnection 
Customer, have not been found to be just and reasonable and have been 
rejected by the Commission.\24\
---------------------------------------------------------------------------

    \22\ Entergy Gulf States, Inc., 98 FERC ] 61,014 at 61,023, 
reh'g denied, 99 FERC ] 61,095 (2002); see Public Service Co. of 
Colorado, 59 FERC ] 61,311 (1992), reh'g denied, 62 FERC ] 61,013 at 
61,061 (1993).
    \23\ Pacific Gas & Electric Company, et al., 102 FERC ] 61,070 
(2003).
    \24\ See, e.g. Illinois Power Co., 103 FERC ] 61,032 (2003); 
American Electric Power Service Corp., 101 FERC ] 61,194 (2002).
---------------------------------------------------------------------------

    22. Regarding pricing for a non-independent Transmission Provider, 
the distinction between Interconnection Facilities and Network Upgrades 
is important because Interconnection Facilities will be paid for solely 
by the Interconnection Customer, and while Network Upgrades will be 
funded initially by the Interconnection Customer (unless the 
Transmission Provider elects to fund them), the Interconnection 
Customer would then be entitled to a cash equivalent refund (i.e., 
credit) equal to the total amount paid for the Network Upgrades, 
including any tax gross-up or other tax-related payments. The refund 
would be paid to the Interconnection Customer on a dollar-for-dollar 
basis, as credits against the Interconnection Customer's payments for 
transmission services, with the full amount to be refunded, with 
interest within five years of the Commercial Operation Date. The 
Commission has clarified that transmission credits may be used whether 
or not a Generating Facility is being dispatched and that credits must 
be accepted for all network transmissions by the Interconnection 
Customer, regardless of whether the plant from which the credits 
originated is dispatched.\25\ Credits are not tied to any particular 
Generating Facility.\26\ The Commission has stated that peaking 
facilities, for instance, must be allowed to use credits even when the 
Generating

[[Page 49850]]

Facility is not dispatched.\27\ The Commission has also allowed 
Transmission Providers to require several Interconnection Customers to 
share the costs of Network Upgrades, under certain circumstances.\28\
---------------------------------------------------------------------------

    \25\ Entergy Services, Inc., 101 FERC ] 61,289 (2002).
    \26\ Id.
    \27\ Colton Power, LP, 101 FERC ] 61,150 (2002).
    \28\ Id.
---------------------------------------------------------------------------

    23. The Commission has also clarified that an Interconnection 
Customer need not enter into an agreement for the delivery component of 
transmission service to interconnect with a Transmission Providers' 
Transmission System.\29\ At the same time, Interconnection Service or 
an interconnection by itself does not confer any delivery rights from 
the Generating facility to any points of delivery.\30\
---------------------------------------------------------------------------

    \29\ Entergy Services, Inc., 101 FERC ] 61,016 (2002); Southern 
Company Services, Inc., 95 FERC ] 61,307 at 62,049, order dismissing 
reh'g, 96 FERC ] 61,168 (2001); Tennessee Power Co., 90 FERC ] 
61,238 at 61,761 (2000).
    \30\ See Arizona Public Service Co., 94 FERC ] 61,027 at 61,076, 
order on reh'g, 94 FERC ] 61,267 (2001).
---------------------------------------------------------------------------

    24. The Commission has clarified that ownership of the 
Interconnection Facilities does not have a direct effect on reliability 
of the system. Therefore, as long as the Transmission Provider operates 
the Interconnection Facilities, the Commission will allow an 
Interconnection Customer to own part, or all, of those facilities.\31\
---------------------------------------------------------------------------

    \31\ Arizona Public Service Company, 102 FERC ] 61,303 (2003).
---------------------------------------------------------------------------

C. Differences Between the Proposed and Final Rules

    25. The Final Rule LGIP and Final Rule LGIA largely track the 
proposed documents. Changes made in the Final Rule tend to be specific 
to an individual LGIP section or LGIA article, and do not require 
fundamental changes to the documents. That being said, there are a few 
significant issues, some substantive and others organizational, that 
the Commission summarizes here.
    26. Most importantly, we note that the Final Rule applies to 
independent and non-independent Transmission Providers alike, but non-
independent Transmission Providers are required to adopt the Final Rule 
LGIP and Final Rule LGIA into their OATTs, with deviations from the 
Final Rule justified using either the ``regional differences'' or 
``consistent with or superior to'' standard. We also allow Regional 
Transmission Organizations (RTOs) and ISOs more flexibility to 
customize an LGIP and LGIA to meet their regional needs. This applies 
to terms and conditions as well as pricing. While RTOs and ISOs are 
required to submit compliance filings, they may submit LGIP and LGIA 
terms and conditions that meet an ``independent entity variation'' 
standard that is more flexible than the ``consistent with or superior 
to'' standard and the regional differences standard.
    27. We are also including in the Final Rule LGIA an article 
addressing insurance requirements and limiting liability for 
consequential damages, both of which were absent from the NOPR. 
Provision for liquidated damages had been removed from the Final Rule 
LGIP but remains an option in the Final Rule LGIA. Also, in the Final 
Rule LGIP, when a Transmission Provider elects to study Interconnection 
Requests in Clusters, it would simultaneously study all 
Interconnections Requests received within a 180 day window, rather than 
a 90 day window as proposed.
    28. On pricing, we clarify the approach set forth in the NOPR. We 
continue our current policy of requiring a Transmission Provider that 
is not an independent entity to provide transmission credits for the 
cost of Network Upgrades needed for a Generating Facility 
interconnection. For a Transmission Provider that is an independent 
entity, such as an RTO or ISO, we allow flexibility as to the specifics 
of the interconnection pricing policy. Also, an RTO or ISO may propose 
participant funding for Network Upgrades for a generator 
interconnection, and, for a transitional period not to exceed a year, a 
region may use participant funding as soon as an independent 
administrator has been approved by the Commission and the affected 
states.
    29. Where the policy of transmission credits for upgrades required 
as a result of the interconnection applies, the Commission provides 
several clarifications in this Final Rule. For example, the 
Interconnection Customer should receive transmission credits only if 
its Generating Facility has achieved commercial operation. Transmission 
credits are to be paid to the Interconnection Customer when upgrades to 
an Affected System \32\ are constructed and the Interconnection 
Customer has paid for them. Finally, the Transmission Provider may 
decline to award credits for only those transmission charges that are 
designed to recover out-of-pocket costs, such as the cost of line 
losses, associated with the delivery of the output of the Generating 
Facility.
---------------------------------------------------------------------------

    \32\ An Affected System is an electric system other than the 
Transmission Provider's Transmission System that may be affected by 
the proposed interconnection.
---------------------------------------------------------------------------

II. Discussion

    30. In part A of this discussion we address the Standard Large 
Generator Interconnection Procedures (Final Rule LGIP) that specify the 
details of the uniform process a prospective Interconnection Customer 
and its Transmission Provider shall use to initiate, evaluate, and 
implement an Interconnection Request pursuant to the Final Rule.
    31. In part B we discuss the details of the Standard Large 
Generator Interconnection Agreement (Final Rule LGIA) to be executed by 
the prospective Interconnection Customer, the Transmission Provider 
and, where appropriate, the Transmission Owner. This document is 
incorporated as Appendix 6 to the Standard Large Generator 
Interconnection Procedures and covers the related rights and 
obligations of the Parties.\33\
---------------------------------------------------------------------------

    \33\ The Final Rule LGIP and Final Rule LGIA define Party or 
Parties as ``Transmission Provider, Transmission Owner, 
Interconnection Customer, or any combination of the above.''
---------------------------------------------------------------------------

    32. In part C, we discuss a number of other significant policy 
issues in connection with this rulemaking, including pricing policies; 
the required Interconnection Services; the treatment of 
``Distribution'' level interconnections; Qualifying Facility matters; 
variations from the Final Rule and accommodation of regional 
differences; the availability of waivers for small entities; OATT 
reciprocity implications for interconnection requests; assorted 
clarifications to the NOPR's proposals; insurance and liquidated 
damages matters; two- versus three-party interconnection agreements; 
and consequential damage issues.
    33. In part D, we address Compliance Issues pertaining to the 
requirement for a Transmission Provider to file conforming amendments 
to its existing OATT; the treatment to be accorded existing 
interconnection agreements (grandfathering); and the method a 
Transmission Provider is to use to file executed and unexecuted 
interconnection agreements in accord with this Final Rule.

A. Issues Related to the Standard Large Generator Interconnection 
Procedures (LGIP)

1. Overview \34\
---------------------------------------------------------------------------

    \34\ For the convenience of the reader, a flow chart depicting 
the interconnection process is appended to this preamble as Appendix 
A.
---------------------------------------------------------------------------

    34. The Final Rule Standard Large Generator Interconnection 
Procedures (LGIP) document specifies the steps that must be followed 
and deadlines that must be met when an Interconnection

[[Page 49851]]

Customer requests interconnection of either a new Generating Facility 
or the expansion of an existing Generating Facility with the 
Transmission Provider's Transmission System.\35\ The Commission directs 
each public utility to amend its OATT with a single compliance filing 
to incorporate the Final Rule LGIP and the Standard Large Generator 
Interconnection Agreement (LGIA) documents. RTOs and ISOs must also 
make compliance filings, but as discussed above, will have more 
flexibility to propose different procedures and a different agreement.
---------------------------------------------------------------------------

    \35\ Any Transmission Provider with an Interconnection Request 
outstanding at the time this Final Rule becomes effective shall 
transition to the Final Rule LGIP within a reasonable period of 
time. This is further described in Final Rule LGIP Section 5.1.
---------------------------------------------------------------------------

    35. The Final Rule LGIP sets forth the following steps to secure an 
interconnection. First, the prospective Interconnection Customer will 
submit an Interconnection Request to the Transmission Provider along 
with a $10,000 deposit, preliminary site documentation, and the 
expected In-Service Date.\36\ The Transmission Provider will 
acknowledge receipt of the request and promptly notify the 
Interconnection Customer if its request is deficient. When the 
Interconnection Request is complete, the Transmission Provider will 
place it in its interconnection queue with other pending requests. The 
Transmission Provider will assign a Queue Position to each completed 
Interconnection Request based on the date and time of its receipt.\37\ 
Queue Position is used to determine the order of performing the various 
Interconnection Studies and the assignment of cost responsibility for 
the construction of facilities necessary to accommodate the 
Interconnection Request.\38\ The Transmission Provider will also 
maintain a list of all Interconnection Requests \39\ on its OASIS.\40\
---------------------------------------------------------------------------

    \36\ The standard form of Interconnection Request is Appendix 1 
of the LGIP document.
    \37\ For example, the first complete Interconnection Request, 
assigned an earlier Queue Position, is ``higher-queued'' relative to 
the second complete Interconnection Request that is assigned a later 
Queue Position and is ``lower queued.'' The withdrawal of a complete 
Interconnection Request causes it to lose its Queue Position and all 
succeeding complete Interconnection Requests to advance, 
accordingly.
    \38\ Any Interconnection Customer assigned a Queue Position 
before the effective date of this Final Rule would retain that Queue 
Position.
    \39\ We emphasize that the Final Rule LGIP requires the 
Transmission Provider, the Transmission Owner, and such entities' 
officers, employees, and contractors to maintain proper procedures 
for Confidential Information provided by an Interconnection Customer 
related to the Interconnection Request, the disclosure of which 
could harm or prejudice the Interconnection Customer or its 
business.
    \40\ Open Access Same-Time Information System and Standards of 
Conduct, Order No. 889, 61 FR 21737 (May 10, 1996), FERC Stats. & 
Regs. ] 31,035 at 31,590 (1996), order on reh'g, Order No. 889-A, 62 
FR 12484 (Mar. 14, 1997), FERC Stats. & Regs. ] 31,049 (1997), reh'g 
denied, Order No. 889-B, 81 FERC ] 61,253 (1997), aff'd in relevant 
part sub nom. Transmission Access Policy Study Group v. FERC, 225 
F.3d 667 (DC Cir. 2000), aff'd sub nom. New York v. FERC, 535 U.S. 1 
(2002).
---------------------------------------------------------------------------

    36. The Parties will then schedule a Scoping Meeting to discuss 
possible Points of Interconnection and exchange technical information, 
including data that would reasonably be expected to affect such 
interconnection options.\41\ The Scoping Meeting is followed by a 
series of Interconnection Studies to be performed by, or at the 
direction of, the Transmission Provider to evaluate the proposed 
interconnection in detail, identify any Adverse System Impacts on the 
Transmission Provider's Transmission System or Affected Systems, and 
specify the facility modifications that are needed to safely and 
reliably complete the interconnection.\42\ These studies include:
---------------------------------------------------------------------------

    \41\ The Scoping Meeting will address technical matters such as 
facility loadings, general instability issues, general short-circuit 
issues, general voltage issues, and general reliability issues that 
would affect the Interconnection Customer's designation of its Point 
of Interconnection.
    \42\ The standard forms of agreement for the Interconnection 
Feasibility Study, the Interconnection System Impact Study, the 
Interconnection Facilities Study, and the Optional Interconnection 
Study, are included at Appendices 2-4 to the Final Rule LGIP, 
respectively.

    (1) Interconnection Feasibility Study to evaluate on a 
preliminary basis the feasibility of the proposed interconnection, 
using power flow and short-circuit analyses (to be completed within 
45 Calendar Days from the date of signing of an Interconnection 
Feasibility Study Agreement) (study requires a $10,000 deposit);
    (2) Interconnection System Impact Study to evaluate on a 
comprehensive basis the impact of the proposed interconnection on 
the reliability of Transmission Provider's Transmission System and 
Affected Systems, using a stability analysis, power flow, and short-
circuit analyses (to be completed within 60 Calendar Days from the 
date of signing of an Interconnection System Impact Study Agreement) 
(study requires a $50,000 deposit);\43\
---------------------------------------------------------------------------

    \43\ At the Transmission Provider's option, Interconnection 
System Impact Studies for multiple Generating Facilities may be 
conducted serially or in clusters.
---------------------------------------------------------------------------

    (3) Interconnection Facilities Study to determine a list of 
facilities (including Transmission Provider's Interconnection 
Facilities and Network Upgrades as identified in the Interconnection 
System Impact Study), the cost of those facilities, and the time 
required to interconnect the Generating Facility with the 
Transmission Provider's Transmission System (to be completed within 
90-180 Calendar Days from the date of signing of an Interconnection 
Facilities Study Agreement) (study requires a $100,000 deposit or an 
estimated monthly cost developed by the Transmission Provider for 
conducting the Interconnection Facilities Study); and
    (4) Optional Interconnection Study or sensitivity analysis of 
various assumptions specified by the Interconnection Customer to 
identify any Network Upgrades that may be required to provide 
transmission delivery service over alternative transmission paths 
for the electricity produced by the Generating Facility and (study 
requires a $10,000 deposit).

    37. The Interconnection Feasibility Study, the Interconnection 
System Impact Study, and the Interconnection Facilities Study must be 
performed in the above order, with completion of each study before the 
next begins.\44\ An Interconnection Customer may also request a restudy 
of any of the above if a higher-queued project either drops out of the 
queue, is subjected to Material Modifications, or changes its Point of 
Interconnection.\45\ The Interconnection Customer will pay the actual 
costs for performing each of the Interconnection Studies and restudies.
---------------------------------------------------------------------------

    \44\ These Interconnection Studies are typical of the kinds of 
studies undertaken by Transmission Providers to evaluate 
Interconnection Requests. The Interconnection Facilities Studies and 
Interconnection System Impact Studies also correspond to 
transmission service studies described in the pro forma open access 
tariff. See Order No. 888-A (Tariff Part II, 19 Additional Study 
Procedures for Firm Point-To-Point Transmission Service Requests; 
and Tariff Part III, 32 Additional Study Procedures for Network 
Integration Transmission Service Requests), FERC Stats. & Regs., 
Regulations Preambles (July 1996-December 2000), ] 31,048 at 30,524-
26 and 30,535-36.
    \45\ An Interconnection Feasibility Restudy must be completed 
within 45 Calendar Days of such request. Similarly, the Transmission 
Provider has 60 Calendar Days to complete either an Interconnection 
System Impact Restudy or an Interconnection Facilities Restudy.
---------------------------------------------------------------------------

    38. The Transmission Provider's Interconnection Facilities Study 
report \46\ will include a best estimate of the costs to effect the 
requested interconnection which are to be funded up-front by the 
Interconnection Customer. At the same time as the report is issued, the 
Transmission Provider shall also give the Interconnection Customer a 
draft interconnection agreement completed to

[[Page 49852]]

the extent practicable.\47\ The Transmission Provider and the 
Interconnection Customer will then negotiate the schedule for 
constructing and completing any necessary Transmission Provider 
Interconnection Facilities and Network Upgrades, and incorporate this 
schedule into the interconnection agreement that is signed by the 
Parties.\48\
---------------------------------------------------------------------------

    \46\ Upon the completion of each of the Interconnection Studies, 
a report is prepared which presents the results of the analyses.
    \47\ The draft interconnection agreement shall include: Appendix 
A, Interconnection Facilities, Network Upgrades and Distribution 
Upgrades; Appendix B, Milestones; Appendix C, Interconnection 
Details; Appendix D, Security Arrangements Details; Appendix E, 
Commercial Operation Date; and Appendix F, Addresses for Delivery of 
Notices and Billings.
    \48\ In general, the In-Service Date of an Interconnection 
Customer's Generating Facility or Generating Facility expansion will 
determine the sequence of construction of Network Upgrades. An 
Interconnection Customer, in order to achieve its expected In-
Service Date, may request that the Transmission Provider advance the 
completion of Network Upgrades necessary to support such In-Service 
Date that would otherwise not be completed pursuant to a contractual 
obligation of an entity other than the Interconnection Customer. The 
Transmission Provider will use Reasonable Efforts to advance the 
construction if the Interconnection Customer reimburses it for any 
associated expediting costs and the cost of such Network Upgrades. 
The Interconnection Customer is entitled to transmission credits for 
the expediting costs that it pays.
---------------------------------------------------------------------------

2. Section-by-Section Discussion of the Proposed LGIP
    39. What follows is a discussion of the standard interconnection 
procedures the Commission proposed, the comments received, and the 
Commission's conclusion. The order of discussion follows the 
organization of the proposed LGIP, covering Sections 1-13. Only 
subsections for which issues are raised are presented. For example, we 
discuss Section 2.3, but not Sections 2.1 or 2.2 because no significant 
issues were raised regarding Sections 2.1 or 2.2. Readers should note 
that section numbers referred to in the following discussion are the 
numbers contained in the proposed LGIP. Some proposed sections are 
renumbered in the Final Rule; mention of that fact will be made in the 
Commission Conclusions discussion, where appropriate. Also, note that 
Proposed LGIP Section 14 is eliminated from the Final Rule in its 
entirety because provisions for interconnection procedures and an 
interconnection agreement for Small Generators have been severed from 
this proceeding, as discussed, supra.
    40. Section 1--Definitions--Section 1 of the NOPR LGIP and Article 
1 of the NOPR LGIA contained defined terms that appeared in the 
respective documents. For the sake of consistency, the Final Rule LGIP 
and Final Rule LGIA contain one common set of terms. Included in the 
list of defined terms are a number of new terms which were not included 
in the NOPR LGIP and NOPR LGIA. Comments relating to the definition of 
terms in both documents are discussed below.
    41. Ancillary Services (In the NOPR: Ancillary and Other 
Services)--The NOPR proposed that Ancillary and Other Services would 
have the same meaning as defined in the Transmission Provider's OATT 
and include some other services such as generator balancing, black 
start, and automatic generation control.
Comments
    42. Cinergy and Entergy claim that this term is not used in the 
LGIA and that its definition should be deleted.
Commission Conclusion
    43. The Commission disagrees that the definition should be deleted. 
The term is used in Article 9 of the NOPR LGIA and elsewhere. However, 
to be consistent with the OATT, the Commission here adopts the 
definition of Ancillary Services in Order No. 888: ``Those services 
that are necessary to support the transmission of capacity and energy 
from resources to loads while maintaining reliable operation of the 
Transmission Provider's Transmission System in accordance with Good 
Utility Practice.''
    44. Commercial Operation Date--The NOPR proposed to define 
Commercial Operation Date as the date on which the Generating Facility 
commences commercial operation of a unit at the Generating Facility 
after Trial Operation of the unit is completed, as confirmed in 
writing, in accordance with proposed Appendix F to the NOPR LGIA.
Comments
    45. Central Maine points out that when a Generating Facility 
consists of more than one generating unit, under the NOPR, the 
Commercial Operation Date depends on the operability of a generating 
unit after its testing. Central Maine requests that the Commission 
define the term Commercial Operation Date as the date on which the 
Generating Facility as a whole commences commercial operation, not the 
individual generating units.
Commission Conclusion
    46. The Commission is not adopting Central Maine's proposal. The 
Generating Facility (referred to as the Facility in the NOPR LGIP and 
NOPR LGIA) could consist of multiple generating units with 
substantially different Commercial Operation Dates. Under Central 
Maine's proposal, all of the Generating Facilities at the complex would 
be required to undergo a pre-commercial Trial Operation each time a new 
generating unit at the Generating Facility is ready to commence 
commercial operation. Central Maine gives no reason why this should be 
required. Furthermore, revising the NOPR LGIP is unnecessary because 
Article 6.1 of the NOPR LGIA (Pre-Commercial Operation Date, Testing 
and Modifications) addresses testing of the Generating Facility and the 
Interconnection Customer's Interconnection Facilities to ensure their 
safe and reliable operation.
    47. Generating Facility (In the NOPR: Facility)--The NOPR proposed 
to define the term Facility as the Interconnection Customer's 
generator, as identified in the Interconnection Request, but excluding 
the Interconnection Customer's Interconnection Facilities. In this 
Final Rule, the Commission has renamed Facility to Generating Facility 
to avoid confusion between other facilities and equipment.
Comments
    48. Central Maine states that a full description of the Generating 
Facility should be attached to the interconnection agreement as an 
appendix.
Commission Conclusion
    49. The Commission concludes that it is unnecessary to append a 
description of the Generating Facility to the interconnection agreement 
because Appendix 1 of the Final Rule LGIP (Interconnection Request) 
already provides detailed information about the Generating Facility. 
Accordingly, the Commission adopts the proposed definition but changes 
the defined term from Facility to Generating Facility.
    50. Generator--In the NOPR, the Commission proposed to define the 
term Generator to mean any Generating Facility, regardless of 
ownership.
Comments
    51. Dairyland Power points out that the term Generator is used in 
the NOPR LGIP to refer to the entity that owns the Generating Facility, 
as well as the facility itself. It asks for clarification.
Commission Conclusion
    52. To clarify, we use the term Interconnection Customer in this 
preamble and the Final Rule to refer to the owner of the Generating 
Facility. The terms Small Generator and Large Generator refer to the 
class of energy producing devices no larger than 20 MW and larger than 
20 MW, respectively.

[[Page 49853]]

    53. Good Utility Practice--In the NOPR, the Commission defined Good 
Utility Practice to mean any of the practices, methods and acts 
generally accepted in the region, including Applicable Reliability 
Standards and the National Electrical Code.
Comments
    54. NERC states that although the terms Good Utility Practice and 
Applicable Reliability Standards have separate definitions, they have 
often been used interchangeably. It notes that the Commission has 
defined Applicable Reliability Standards to include NERC and regional 
reliability council requirements while Good Utility Practice is a 
broader term that includes Applicable Reliability Standards. NERC 
comments that it is important that these terms be used consistently.
    55. Cinergy notes that Good Utility Practice is defined to include 
compliance with the National Electrical Code. It states that because it 
is not subject to the National Electrical Code, it would be improper to 
attempt to bind it to such compliance.
Commission Conclusion
    56. The Commission agrees with NERC that there is some overlap in 
the proposed definitions of Good Utility Practice and Applicable 
Reliability Standards. To remove any misunderstanding in the definition 
of Good Utility Practice, the Commission is adopting in the Final Rule 
the Order No. 888 definition, which contains no references to 
Applicable Reliability Standards and National Electrical Code. This 
also addresses Cinergy's concern.
    57. Interconnection Guidelines--The NOPR stated that the technical 
requirements to be followed by the Parties are set forth in the 
proposed Appendix G (Interconnection Guidelines).
Comments
    58. Southern observes that proposed Appendix G is blank, inferring 
that the Interconnection Customer and Transmission Provider negotiate 
the technical and operational requirements. Southern believes that this 
is inappropriate because interconnection guidelines should be 
established by the Transmission Provider, not by negotiation. Southern 
contends that requiring a Transmission Provider to negotiate the 
technical and operational requirements with each Interconnection 
Customer is inconsistent with the goal of uniform interconnection 
procedures.
Commission Conclusion
    59. Proposed Appendix G was intended to set forth uniform technical 
and operational requirements applicable to all Interconnection 
Customers established by the Transmission Provider, not to be a vehicle 
for the Parties to negotiate technical and operational requirements on 
a case-by-case basis. The Commission concludes, however, that most, if 
not all, of the generic technical and operational requirements are 
already set forth in the Final Rule LGIA. We are therefore not defining 
the term Interconnection Guidelines as well as not including proposed 
Appendix G in the Final Rule LGIA.\49\
---------------------------------------------------------------------------

    \49\ See, e.g., Article 7 (Metering), Article 8 (Communications) 
and Article 9 (Operations).
---------------------------------------------------------------------------

    60. Joint Operating Committee--The NOPR proposed to define Joint 
Operating Committee to mean a committee comprised of members of 
individual operating committees that addresses issues arising out of 
the duties, roles, and responsibilities of individual operating 
committees described in Article 29 of the NOPR LGIA.
Comments
    61. FirstEnergy and PSNM state that the Joint Operating Committee 
would impose additional administrative costs on the Transmission 
Provider and is also unnecessary.
Commission Conclusion
    62. The Commission is not deleting the term. As discussed later, 
the Final Rule does not require the Parties to form individual 
operating committees. Instead, the Final Rule requires a Joint 
Operating Committee comprising the Transmission Provider and all of its 
Interconnection Customers. Among other things, the committee will 
address issues arising out of the duties, roles, and responsibilities 
of the Parties under their interconnection agreements.
    63. Network Upgrades--In the NOPR, Network Upgrades were defined as 
additions, modifications, and upgrades to the Transmission System 
required beyond the Point of Interconnection in order to accommodate 
the interconnection of the Generating Facility. Network Upgrades are 
identified by the Parties in Appendix A to the interconnection 
agreement (including any modifications, additions or upgrades made to 
such facilities). The NOPR also stated that Network Upgrades benefit 
all users of the Transmission System, without distinction or regard as 
to the purpose of the upgrade.
Comments
    64. Several commenters, including Calpine and SoCal Water District, 
request that the definition of Network Upgrades be clarified and made 
as specific as possible. Calpine and Nevada Power propose that Network 
Upgrades should include only facilities shown to be ``integrated'' to 
the Transmission System, that is, likely to be used by entities other 
than the Interconnection Customer. Some commenters \50\ contend that 
circuit breakers are not Network Upgrades, since they benefit only the 
new Interconnection Customer.
---------------------------------------------------------------------------

    \50\ E.g., Edison Mission, Georgia Transmission, MidAmerican, 
and SoCal Water District.
---------------------------------------------------------------------------

Commission Conclusion
    65. The Final Rule revises the definition of Network Upgrade to 
include the phrase ``at or beyond the Point of Interconnection,'' 
instead of ``beyond the Point of Interconnection,'' to make it 
consistent with established Commission precedent. The network begins at 
the point where the Interconnection Customer connects to the 
Transmission System, not somewhere beyond that point.\51\ Facilities 
beyond the Point of Interconnection are part of the Transmission 
Provider's Transmission System and benefit all users. We are also 
removing the concept of beneficiary from the definition so as to avoid 
implying a pricing policy in the definition.
---------------------------------------------------------------------------

    \51\ See Entergy Gulf States, Inc., 99 FERC ] 61,095 (2002).
---------------------------------------------------------------------------

    66. We disagree with the comments stating that the term is not well 
defined. The Commission has defined Network Upgrades as those 
facilities ``at or beyond the Point of Interconnection'' partially in 
order to clarify to all entities exactly what is a Network Upgrade. We 
are removing references to beneficiaries from the definition, because 
our well-established precedent regarding what constitutes Network 
Upgrades does not require a case-specific determination that all users 
benefit from Network Upgrade; instead we look only as whether the 
upgrade is at or beyond the Point of Interconnection.\52\
---------------------------------------------------------------------------

    \52\ E.g., Entergy Services, Inc. v. FERC, 319 F.3d 536 (DC Cir. 
2003); Southern Company Services, Inc., 101 FERC ] 61,309 (2002); 
American Electric Power Service Corp., 101 FERC ] 61,194 (2002); 
Tampa Electric Company, 99 FERC ] 61,192 (2002).
---------------------------------------------------------------------------

    67. Reasonable Efforts--The NOPR proposed to define Reasonable 
Efforts as actions that are timely and consistent with Good Utility 
Practice and are substantially equivalent to those a Party would use to 
protect its own interests.

[[Page 49854]]

Comments
    68. Some commenters including Central Maine found this definition 
to be vague. They also contend that only Good Utility Practice should 
be required.
Commission Conclusion
    69. The Commission adopts the proposed definition. The standard in 
the NOPR is necessary to ensure comparable treatment. If a Party 
normally exceeds Good Utility Practice when it protects its own 
interests, it must do so for others as well.
    70. System Protection Facilities--The NOPR proposed to define 
System Protection Facilities as the equipment required to protect the 
Transmission System from faults and other electrical disturbances 
occurring at the Interconnection Customer's Generating Facility, and 
vice versa.
Comments
    71. NERC proposes that the definition of System Protection 
Facilities should include ``necessary protection signal communications 
equipment'' in addition to the other equipment mentioned in the 
definition. It argues that such communications equipment is needed to 
coordinate and monitor the operation of protective devices.
Commission Conclusion
    72. The Commission agrees with NERC and adopts the recommended 
language.
    73. Transmission Owner and Transmission Provider--In the NOPR, the 
Commission proposed to define Transmission Owner to mean any entity 
that owns, leases or otherwise possesses an interest in the 
Transmission System at the Point of Interconnection. It proposed to 
define Transmission Provider to mean the entity that provides 
transmission service under its OATT.
Comments
    74. EEI proposes that the definition of Transmission Provider be 
revised to include Transmission Owner. National Grid states that the 
proposed LGIA should clearly delineate the rights and responsibilities 
of Transmission Owners that are not Transmission Providers.
Commission Conclusion
    75. We agree with EEI. Accordingly, the definition of Transmission 
Provider in the Final Rule includes the Transmission Owner as well. 
While we recognize that the Transmission Provider and the Transmission 
Owner may be distinct entities in some cases, throughout the Final Rule 
we will refer to both the Transmission Provider and the Transmission 
Owner generically as the Transmission Provider. There are a few 
instances in which the distinction between Transmission Owner and 
Transmission Provider becomes relevant and there we use the appropriate 
terms.
    76. Section 2--Scope and Application--Section 2 of the NOPR LGIP 
provided that the Transmission Provider receive, process, and analyze 
all Interconnection Requests in the same manner as it does for itself, 
its subsidiaries or Affiliates.
    77. Section 2.3--Base Case Data--Section 2.3 of the NOPR LGIP 
required the Transmission Provider to provide base case power flow, 
short-circuit and stability databases to the Interconnection Customer 
upon request so that the Interconnection Customer may independently 
study its Interconnection Request.
Comments
    78. Mirant notes that certain of the language from the Consensus 
LGIP Section 2.3 concerning confidentiality provisions and the makeup 
of the Base Case data appears to have been unintentionally left out of 
the NOPR LGIP Section 2.3.\53\
---------------------------------------------------------------------------

    \53\ Mirant states that the following language was left out of 
Section 2.3 of the NOPR LGIP: ``and contingency lists upon request 
subject to confidentiality provisions. Such databases and lists, 
herein referred to as Base Cases, shall include all (I) generation 
projects and (ii) transmission projects, including merchant 
transmission projects that are proposed for a Transmission System 
for which a transmission expansion plan has been submitted and 
approved by the applicable authority.''
---------------------------------------------------------------------------

    79. Dominion Resources asks that the Commission revise LGIP Section 
2.3 to state that Base Case data is subject to a confidentiality 
provision between the Parties. Sempra comments that the Transmission 
Provider should protect the confidentiality of other Interconnection 
Customers' information that is part of those databases. Entergy states 
that this Section should apply only to information that is not 
commercially sensitive, so as to avoid providing a competitive 
advantage to other Interconnection Customers.
    80. Calpine argues that the Transmission Provider should provide, 
in addition to the stated databases, all underlying assumptions, data 
files and documents used to create the Base Case, because otherwise the 
provision could be interpreted as a narrow set of data files that are 
meaningless.
    81. The Ohio PUC contends that the Commission should ensure that 
rules for handling critical energy infrastructure information (CEII) 
are not abused by utilities that seek to withhold from public 
disclosure commercial information that is not really CEII and that has 
historically been central to public regulatory proceedings. It believes 
that there must be procedures to ensure protection of critical public 
interests. The Ohio PUC recommends that the procedures be carried out 
by an entity, such as the newly formed Department of Homeland Security, 
that has specific experience in CEII and is qualified to review the 
Commission's CEII decisions.
Commission Conclusion
    82. As Mirant correctly notes, segments of the Consensus LGIP 
Section 2.3 relating to confidentiality and the makeup of the Base Case 
data were inadvertently omitted from the NOPR; this text is included in 
the Final Rule. Both confidentiality and the Base Case data format were 
significant topics in the Commission Staff Queuing Technical Conference 
held on January 21, 2003. Most conference participants agreed that 
providing this Base Case data was reasonable in that it would help the 
Interconnection Customer and its subcontractor conduct Interconnection 
Studies independently, expedite the evaluation process, and free up the 
Transmission Provider's resources, and reduce the time that would 
otherwise be devoted to performing Interconnection Studies or acting as 
the Interconnection Customer's consultant. The Commission believes that 
adding the missing text addresses other commenters' concerns regarding 
the need for confidential treatment of the Base Case data and other 
commercially sensitive information that may be provided to the 
Interconnection Customer.
    83. In response to Calpine, we clarify that Transmission Providers 
must provide all underlying assumptions and data files so that the 
Interconnection Customer or its subcontractor can independently conduct 
Interconnection Studies.
    84. As to the concerns of the Ohio PUC and others regarding the 
security of critical energy infrastructure information, the security of 
the energy infrastructure is essential. The Commission expects that all 
Transmission Providers, market participants, and Interconnection 
Customers will comply with the recommendations of the President's 
Critical Infrastructure Protection Board, as well as any best practice 
recommendations or requirements that may be issued by NERC or any other 
electric reliability authorities. In particular, all public utilities 
are expected to meet basic standards for system infrastructure and 
operational

[[Page 49855]]

security, including physical, operational, and cyber-security 
practices. However, they are not to abuse security requirements in an 
effort to withhold from public disclosure commercial information that 
lacks legitimate CEII status.
    85. Section 3--Interconnection Request--In NOPR LGIP Section 3, the 
Commission proposed that each Interconnection Request include, among 
other things, a refundable deposit of $10,000 that would be applied 
toward the cost of the Interconnection Feasibility Study.
    86. Section 3.1--General--NOPR LGIP Section 3.1 would have required 
that the Interconnection Customer submit to the Transmission Provider 
an Interconnection Request and a refundable deposit of $10,000 to be 
applied toward the cost of an Interconnection Feasibility Study. The 
Interconnection Customer would submit a separate Interconnection 
Request for each site to be studied and may submit multiple 
Interconnection Requests for a single site. At the Interconnection 
Customer's option, the Parties could identify alternative Points of 
Interconnection and configurations at the Scoping Meeting and attempt 
to eliminate alternatives from further consideration. The 
Interconnection Customer would be required to select the Point of 
Interconnection no later than the execution of the Interconnection 
Feasibility Study Agreement.
Comments
    87. Some commenters, including Entergy and PJM, state that an 
initial evaluation of several alternative interconnection sites is 
inconsistent with regional planning and can be accomplished only at the 
expense of Transmission Providers and lower queued Interconnection 
Customers seeking swift interconnection.
    88. Cal ISO raises several questions related to the possibility of 
multiple Interconnection Requests for a single site: (1) Do multiple 
Interconnection Requests refer only to routing and interconnection 
arrangements? (2) If so, how many alternatives are acceptable under one 
submittal? (3) Is an Interconnection Request for one site that is to be 
evaluated at two different voltage levels, one or two Interconnection 
Requests? and (4) Is the $10,000 deposit required for each 
Interconnection Request, resulting in multiple deposits for multiple 
requests at a single site?
    89. ISO New England recommends revising this section to give an RTO 
or ISO authority to set reasonable interconnection deposit amounts, 
taking into account the requested study's complexity. It also states 
that concerns about discriminatory treatment of Interconnection 
Customers should be alleviated because the RTO or ISO is independent.
Commission Conclusion
    90. Except as noted below, we are adopting Section 3.1 in the Final 
Rule as proposed. Allowing the Interconnection Customer the option to 
have the Parties evaluate alternative interconnection sites and 
configurations at the Scoping Meeting will greatly reduce the need to 
conduct detailed analyses of interconnection options that are found to 
have little merit. Providing the Interconnection Customer with more 
information prior to authorizing an Interconnection Feasibility Study 
should lead to more efficient use of the Transmission Provider's 
planning resources and higher quality Interconnection Studies.
    91. With regard to Cal ISO's first question, multiple 
Interconnection Requests at a single site could involve more than just 
alternative routing and interconnection arrangements. For example, they 
could also involve substantially different Generating Facility designs. 
Regarding Cal ISO's second question, we do not set a generic limit on 
the number of Interconnection Requests that may be included in a single 
submittal, but leave it to the Parties to reach agreement at the 
Scoping Meeting, or, if they fail to agree, pursue dispute resolution. 
As to the third question, a request to evaluate one site at two 
different voltage levels would be two Interconnection Requests. With 
respect to Cal ISO's fourth question, the Interconnection Customer must 
submit a deposit with each Interconnection Request when more than one 
request is submitted for a single site. However, if an Interconnection 
Request is withdrawn before the execution of an Interconnection 
Feasibility Study Agreement, perhaps as a result of discussions at the 
Scoping Meeting, the Transmission Provider must promptly return the 
deposit to the Interconnection Customer. Finally, the Commission is 
clarifying Section 3.1 to eliminate the uncertainty underlying Cal 
ISO's questions 3 and 4.
    92. The Commission is not revising proposed LGIP Section 3.1 to 
provide the flexibility that the New England ISO seeks. The proposed 
study deposit requirements appropriately balance the interests of the 
Transmission Provider and the Interconnection Customer. However, as 
explained elsewhere in this preamble, we will entertain proposals by an 
RTO or ISO to adopt alternative interconnection procedures that reflect 
regional differences.
    93. Section 3.2--Identification of Types of Interconnection 
Services--Section 3.2 of the NOPR LGIP stated that, when the 
Interconnection Customer submits its Interconnection Request, it must 
identify the type of Interconnection Service it desires. The Final Rule 
provides for two service products: (1) Energy Resource Interconnection 
Service, which is a basic or minimal interconnection service, and (2) 
Network Resource Interconnection Service, which is a more flexible and 
comprehensive service. However, any Interconnection Customer requesting 
Network Resource Interconnection Service may request that it also be 
studied for the less comprehensive Energy Resource Interconnection 
Service up to the point when an Interconnection Facility Study 
Agreement is executed. Comments and conclusions relating to Section 3.2 
of the NOPR LGIP are discussed in part II.C.2 (Interconnection Products 
and Scope of Service).
    94. Section 3.3.1--Initiating an Interconnection Request--According 
to NOPR LGIP Section 3.3.1, in order to initiate an Interconnection 
Request, the Interconnection Customer would be required to submit a 
$10,000 deposit, a completed Interconnection Request, and either a 
demonstration of Site Control (e.g., securing land rights, air permit, 
etc.) or an additional deposit of $10,000, with the deposits applied 
toward any required Interconnection Studies. The latter deposit would 
be refundable only if the Interconnection Customer demonstrates Site 
Control within the time period specified in the proposed LGIP Section 
3.3.3.
    95. Proposed LGIP Section 3.3.1 would allow the expected In-Service 
Date of the Generating Facility to be no later than the completion date 
of the relevant region's expansion planning period, not to exceed seven 
years from the date of the Interconnection Request, unless the 
Interconnection Customer can demonstrate that engineering, permitting 
and construction of the Generating Facility will take longer. Under the 
proposal, the In-Service Date may not exceed ten years from the date 
the Interconnection Request is received by the Transmission Provider.
Comments
    96. Some commenters contend that an Interconnection Customer should 
be required to demonstrate Site Control when it submits an 
Interconnection

[[Page 49856]]

Request.\54\ They disagree with the proposed LGIP Section 3.3.1 
provision that allows for the posting of an additional $10,000 deposit 
in lieu of the demonstration of Site Control. For example, PJM states 
that Site Control is a strong indication of a serious project and is 
essential for establishing a queue that will consist of projects that 
are likely to be completed. PJM claims that this is not a burdensome 
requirement, and that every one of the 285 requests for generator 
interconnection that it has received since 1999 has included evidence 
of Site Control at the Interconnection Feasibility Study stage. Edison 
Mission believes that the Interconnection Customer must have 
uninterrupted Site Control throughout the interconnection process. It 
states that a $10,000 deposit is not sufficient to discourage 
Interconnection Customers from filing premature Interconnection 
Requests (in order to secure a favorable Queue Position) and only later 
find themselves to be unable to secure Site Control. Edison Mission 
further contends that such a minimal deposit requirement may encourage 
Interconnection Customers, not acting in good faith, to speculate in 
interconnection rights by placing deposits for Interconnection Requests 
at promising locations. It believes that such speculation will 
frustrate other Interconnection Customers that obtain a site but are 
locked out of interconnection due to the superior Queue Position of a 
Party that merely posted a deposit. Edison Mission predicts that this 
will become an even greater issue as market designs based on locational 
marginal pricing become the norm.
---------------------------------------------------------------------------

    \54\ E.g., BPA, Central Maine, Cleco, Edison Mission, Georgia 
Transmission, NYTO, PJM, PJMTO, and Salt River Project.
---------------------------------------------------------------------------

    97. Cleco believes that the only deposit that should be refundable 
is the $10,000 deposit paid in lieu of demonstrating Site Control, not 
the original deposit initiating an Interconnection Request. Moreover, 
Cleco states that the Commission should make clear that the $10,000 
deposited in lieu of Site Control should be refundable if the 
Interconnection Customer demonstrates Site Control within the time 
period specified in Section 3.3.3.
    98. Central Maine takes exception to allowing an Interconnection 
Customer to remain in the queue for a period not to exceed ten years 
from the date of receipt of the Interconnection Request; it says this 
period is too long. FirstEnergy recommends replacing ``Regional 
Expansion Planning Period'' with ``Transmission Provider Expansion 
Planning Period.'' Salt River Project seeks clarification as to how to 
reconcile a situation where the original In-Service Date is ten years 
out and there is then a three year extension.
    99. Some commenters, including American Wind Energy, Edison 
Mission, NMA, Peabody, and WEPCO, contend that the development time for 
certain large scale coal, wind power, and other types of projects raise 
special issues. For example, they want the ten year restriction 
eliminated because their equipment is not ``off-the-shelf,'' and siting 
and permitting can exceed ten years. Some commenters also want the 
Commission to revise Section 3.3.1 to allow them up to nine months 
after the Interconnection Request is made to submit final design 
specifications. They contend that because large non-gas-fired 
generators are unique and not ``off-the-shelf,'' completion of the 
final design specifications requires nine or more months after the 
Interconnection Request is submitted.
Commission Conclusion
    100. We retain the proposed text that requires a demonstration of 
Site Control or a posting of an additional deposit of $10,000. There 
may be instances when requiring Site Control could unduly delay the 
interconnection process.
    101. We also share Edison Mission's concern that some participants 
may attempt to game the system by filing Interconnection Requests at 
multiple sites knowing that Site Control is unlikely to be obtainable 
at every site. However, under NOPR LGIP Section 11.3, the 
Interconnection Customer must provide reasonable evidence of Site 
Control within 15 Business Days after the receipt of the Final 
Interconnection Agreement or post additional security of $250,000, 
which will be applied toward future construction costs when the 
demonstration of Site Control is made. This is sufficient incentive for 
an Interconnection Customer to refrain from engaging in the speculative 
behavior suggested by Edison Mission.
    102. With respect to the ten-year period for allowing an 
Interconnection Customer to remain in the queue, we believe that ten 
years should be adequate time to complete the siting, permitting and 
construction requirements for all plants unless major permitting delays 
are encountered. Large non-gas-fired projects (e.g., coal or oil 
projects) generally take eight years or less to complete. Thus, a ten-
year period gives large projects at least a two year buffer. Moreover, 
we note that numerous Interconnection Customers and Transmission 
Providers negotiated this time limit during the Consensus process. 
Finally, if an Interconnection Customer believes it needs additional 
time to complete its project, it should seek the approval of the 
Transmission Provider to extend the In-Service Date. Accordingly, the 
Commission clarifies that the term of the Final Rule LGIP Section 3.3.1 
is ten years, or longer if the Parties agree, with such agreement not 
to be unreasonably withheld.
    103. Regarding the need for additional time for some 
Interconnection Customers to complete design specifications, the 
Commission is not convinced that an exception should be made in the 
Final Rule LGIP to allow an Interconnection Customer proposing to 
construct a large non-gas-fired Generating Facility to submit final 
design specifications nine months after the Interconnection Request is 
made. The Interconnection Customer should have its design substantially 
completed prior to submitting its Interconnection Request so that it 
does not block or disrupt the queuing process. The Transmission 
Provider is not able to act on an Interconnection Request unless it 
includes all necessary information, and to give one class of 
Interconnection Customers extra time to submit design specifications 
would be unfair to other Interconnection Customers in the queue.
    104. As to FirstEnergy's recommendation, the Commission clarifies 
that, in the absence of a regional expansion planning period, the 
appropriate expansion planning period would be that of the Transmission 
Provider.
    105. Section 3.3.4--Scoping Meeting (In the NOPR: Initial Scoping 
Meeting)--Proposed LGIP Section 3.3.4 would have required the 
Transmission Provider to hold a Scoping Meeting with the 
Interconnection Customer no later than 30 Calendar Days from receipt of 
the Interconnection Request. The purpose of the Scoping Meeting would 
be to discuss alternative interconnection options, including potential 
feasible Points of Interconnection. The Interconnection Customer would 
designate its Point of Interconnection and one or more alternative 
Points of Interconnection on the basis of information gathered at the 
Scoping Meeting. Section 3.3.4 would also provide that the 
Interconnection Customer may forgo the Interconnection Feasibility 
Study and proceed directly to an Interconnection System Impact Study.
Comments
    106. Several commenters, including El Paso, Entergy, FirstEnergy, 
and

[[Page 49857]]

Georgia Transmission, state that the Parties should be able to agree to 
schedule a Scoping Meeting outside the 30-day window.
    107. El Paso believes that the Interconnection Customer should not 
make the final decision on designation of the Point of Interconnection; 
instead, the Transmission Provider should designate the Point of 
Interconnection with the Interconnection Customer's consent. At a 
minimum, El Paso recommends that Section 3.3.4 be modified to state 
that the Transmission Provider must consent to the designation of Point 
of Interconnection and that such consent will not be unreasonably 
withheld. El Paso explains this is because the designation of Point of 
Interconnection has serious cost consequences for the Transmission 
Provider and its customers.
    108. PJM states that the Interconnection Feasibility Study is an 
important first step in evaluating an Interconnection Request and that 
about one-third of the Interconnection Requests are withdrawn after the 
Interconnection Feasibility Study. PJM adds that the Interconnection 
Customer should not be allowed to skip the Interconnection Feasibility 
Study and go directly to the Interconnection System Impact Study 
because this omission would have serious implications for the 
Clustering of Interconnection of Studies and would create the need for 
a large number of restudies. PJM proposes that this provision be 
deleted from the Final Rule LGIP.
Commission Conclusion
    109. In the Final Rule LGIP, the Commission is revising Section 
3.3.4 to allow the Parties to hold the Scoping Meeting outside the 30 
Calendar Day window upon agreement of the Parties, since either Party 
can object to the postponement. With respect to El Paso's concern 
regarding the designation of the Point of Interconnection, the purpose 
of the Scoping Meeting is to discuss alternative interconnection 
options, including potential Points of Interconnection. The Commission 
notes that the Transmission Provider will have an opportunity to voice 
its concerns at the Scoping Meeting and assess the likely cost 
consequences of interconnecting at various points. It is appropriate 
that the Interconnection Customer decide its Point of Interconnection 
based on input from the Transmission Provider because the former must 
consider its investment in the Generating Facility and its site 
selection criteria, as well as its initial funding of Network Upgrades. 
For these reasons, we adopt Section 3.3.4 as proposed.
    110. Regarding PJM's concern about allowing the Interconnection 
Customer to skip the Interconnection Feasibility Study and proceed 
directly to the Interconnection System Impact Study, the Commission 
agrees with PJM that the Interconnection Feasibility Study is an 
important first step in evaluating an Interconnection Request and 
should not be skipped. The Commission is therefore deleting this text 
from the Final Rule LGIP Section 3.3.4.
    111. Section 3.4--OASIS Posting--Proposed LGIP Section 3.4 required 
that the Transmission Provider post on its OASIS a list of all 
Interconnection Requests. It must post the following information for 
each Interconnection Request: the location by county and state; the 
station or transmission line or lines where the interconnection will be 
made; and the projected In-Service Date. The list will not disclose the 
identity of the Interconnection Customer until the Interconnection 
Customer executes an interconnection agreement or requests that the 
Transmission Provider file an unexecuted Agreement with the Commission. 
The Transmission Provider also must post deviations from the study time 
lines set forth in the interconnection procedures. Interconnection 
Study reports and Optional Interconnection Study reports also must be 
posted after the Parties meet to discuss the applicable study results.
Comments
    112. Avista states that listing the location of a Generating 
Facility by county and state is not sufficient. The location should be 
specified in greater detail, because some counties cover hundreds of 
square miles. Mirant and NYTO state that the identity of the 
Interconnection Customer should be posted on the OASIS when the 
Interconnection Request is made because it will help identify 
Interconnection Customers that are unlikely to see their projects 
through completion and drop out of the queue. Mirant claims that the 
identity of the Interconnection Customer is important for conducting 
meaningful Optional Interconnection Studies.
    113. NSTAR seeks clarification about whether entire studies 
consisting of base case data are to be posted on the OASIS, or just the 
interpretive analysis contained in the study reports. Salt River 
Project seeks clarification as to whether the posting of deviations 
refers to the study time lines in proposed LGIP Section 6.3 
(Interconnection Feasibility Study Procedures) or the study time lines 
that were agreed to by the Parties in advance. MidAmerican recommends 
that changes in the Generating Facility's In-Service Date should also 
be posted on the OASIS.
Commission Conclusion
    114. The Commission is not requiring that the location of a 
Generating Facility be specified in any greater detail than proposed 
because the OASIS posting also includes the substation or transmission 
line where the interconnection is to be made. We are also not requiring 
that the identity of the Interconnection Customer be posted when the 
Interconnection Request is made because disclosing the identity at that 
early stage may put the Interconnection Customer at a competitive 
disadvantage and its project at risk. With regard to Mirant's assertion 
that the identity of the Interconnection Customer is important in 
conducting meaningful Optional Interconnection Studies because it helps 
identify who may drop out of the queue, we note that the Optional 
Interconnection Studies are to be performed after the Interconnection 
System Impact Study, at which point only serious projects are likely to 
remain in the queue.
    115. The Commission clarifies that the study reports are to be 
posted, not the actual studies. Regarding deviations from the study 
time lines, the Commission clarifies that the Transmission Provider is 
to post deviations from the study time lines as projected by the 
Transmission Provider for completing future Interconnection Studies. 
For example, Section 6.3 (Interconnection Feasibility Study Procedures) 
calls for the Interconnection Feasibility Study to be completed within 
45 Calendar Days after the Transmission Provider receives the fully 
executed Interconnection Feasibility Study Agreement. If the 
Transmission Provider anticipates that it will not be able to complete 
the Interconnection Feasibility Study within 45 Calendar Days, it 
should post its deviation along with an explanation for the delay 
(e.g., backlog). Finally, we adopt MidAmerican's recommendation, and 
Final Rule LGIP Section 3.4 requires the posting of any expected 
deviation from a Generating Facility's In-Service Date.
    116. Section 3.5--Coordination with Affected Systems--Proposed LGIP 
Section 3.5 dealt with interconnections that may affect a Transmission 
System other than that of the Transmission Provider. A third party 
Transmission System was proposed to be defined in the NOPR LGIA as an 
Affected System. Section 3.5 also proposed obligations and rights of 
the Affected System, the

[[Page 49858]]

Transmission Provider, and the Interconnection Customer, including a 
requirement to coordinate Interconnection Studies.
Comments
    117. Interconnection Customers including Duke Energy, Independent 
Producers, Norton Energy, and Peabody support requiring the 
Transmission Provider (rather than the Interconnection Customer) to 
coordinate and perform all necessary Interconnection Studies and 
Network Upgrades with an Affected System. Duke Energy agrees that the 
Affected System Operator should be required to cooperate with the 
Transmission Provider in completing necessary studies. Duke Energy also 
wants the Affected System Operator to enter into an agreement with the 
Interconnection Customer. Other commenters, predominately Transmission 
Providers, oppose placing these responsibilities on the Transmission 
Provider.\55\ They contend that (1) a contract cannot bind a third 
party that is not a signatory to it, (2) it is unfair to impose 
liability for liquidated damages for an incomplete study on the 
Transmission Provider where the Transmission Provider has no control 
over the Affected System, (3) the Transmission Provider should be 
required to use only ``reasonable efforts'' to coordinate with an 
Affected System, (4) the Interconnection Customer should pay any costs 
of conducting Interconnection Studies on an Affected System, including 
all costs of delays caused by the studies, (5) the Interconnection 
Customer should be required to pay for the necessary upgrades on the 
Affected System and not be allowed to operate until such upgrades are 
completed, and (6) the Transmission Provider should not be responsible 
for actions (or inactions) of third parties either with regard to 
funding or construction of Network Upgrades.
---------------------------------------------------------------------------

    \55\ E.g., AEP, Ameren, BPA, Cal ISO, Central Maine, Central 
Vermont PSC, Cleco, the Construction Issues Coalition, Dairyland 
Power, Dominion Resources, Entergy, Georgia Transmission, Imperial 
Irrigation, ISO New England, MidAmerican, the Midwest ISO, National 
Grid, Nevada Power, NYTO, PGE, PJM, Salt River Project, SoCal 
Edison, TANC, and TVA.
---------------------------------------------------------------------------

Commission Conclusion
    118. The Commission continues to treat interconnection and delivery 
as separate aspects of transmission service, and an Interconnection 
Customer may request Interconnection Service separately from 
transmission service (delivery of the Generating Facility's power 
output). In the majority of circumstances, interconnection alone is 
unlikely to affect the reliability of any neighboring Transmission 
System. However, in those rare instances in which the interconnection 
alone may cause a reliability problem on an Affected System, the 
Commission adopts the approach of Order No. 888 for Network Upgrades 
required to protect an Affected System from a reliability problem due 
to delivery service.\56\ Under Order No. 888, the Transmission Provider 
is required to assist the Transmission Customer in coordinating with 
the Affected System on any Network Upgrades needed to protect the 
reliability of that system.\57\ We will also allow the Transmission 
Provider to coordinate the timing of construction of Network Upgrades 
to its Transmission System with the construction required on the 
Affected System.\58\ As provided in the OATT, the Commission's Dispute 
Resolution Service is available should the Interconnection Customer 
wish to challenge the Transmission Provider's decision to delay 
construction pending completion of the Affected System's upgrades.\59\
---------------------------------------------------------------------------

    \56\ See Section 21 of the OATT. See also Tampa Electric Co., 
103 FERC ]61,047 (2003), and Nevada Power, 97 FERC ]61,227 (2001), 
reh'g denied, 99 FERC ]61,347 (2002); but see American Electric 
Power Service Corporation, 102 FERC ]61,336 (2003).
    \57\ Section 21.1 of the OATT states that: ``The Transmission 
Provider will undertake reasonable efforts to assist the 
Transmission Customer in obtaining such arrangements, including 
without limitation, provided any information or data required by 
such other Transmission System pursuant to Good Utility Practice.''
    \58\ Section 21.2 of the OATT states that: ``Transmission 
Provider shall have the right to coordinate construction on its own 
system with the construction required by others. The Transmission 
Provider, after consultation with the Transmission Customer and 
representatives of such other systems, may defer construction of its 
new transmission facilities, if the new transmission facilities on 
another system cannot be completed in a timely manner.''
    \59\ See Section 21.2 of the OATT.
---------------------------------------------------------------------------

    119. The Commission reiterates that under Order No. 888, economic 
losses from having to redispatch generation do not justify delaying the 
provision of the delivery component of transmission service.\60\ The 
Commission adopts the same standard here for interconnections.
---------------------------------------------------------------------------

    \60\ See Section 13.2 of the OATT.
---------------------------------------------------------------------------

    120. Thus, unless the interconnection alone will endanger the 
reliability of an Affected System, a Transmission Provider may not 
require an Interconnection Customer, as a condition of interconnection, 
to accept responsibility for Network Upgrades on other systems. To hold 
new Interconnection Customers responsible for upgrades to all 
interconnected systems, including not only the system to which the 
Generating Facility interconnects, but other, more distant systems as 
well would create an unreasonable obstacle to the construction of new 
generation.\61\ We reiterate that requiring a Transmission Provider to 
coordinate intermediate studies and upgrades with other systems is just 
and reasonable.
---------------------------------------------------------------------------

    \61\ Nevada Power, 97 FERC ]61,227 (2001), reh'g denied, 99 FERC 
]61,347 at 62,294 (2002).
---------------------------------------------------------------------------

    121. Although the owner or operator of an Affected System is not 
bound by the provisions of the Final Rule LGIP or LGIA, the 
Transmission Provider must allow any Affected System to participate in 
the process when conducting the Interconnection Studies, and 
incorporate the legitimate safety and reliability needs of the Affected 
System. However, the Affected System is not required to participate in 
the interconnection of the Generating Facility, as proposed by Duke 
Energy. If the Affected System declines to work with the Transmission 
Provider, or fails to provide information in a timely manner, the 
Transmission Provider may proceed in the interconnection process 
without taking into account the information that could have been 
provided by the Affected System. Neither the Final Rule LGIP nor the 
Final Rule LGIA is intended to expose the Transmission Provider to 
liability as a result of delays by the Affected System.
    122. In addition, we note that NERC Planning Standards require 
Transmission Providers to work together to minimize effects on each 
others' systems. When a Transmission Provider adds its own new 
generation to its system, this may have a reliability effect on other 
systems, requiring coordination among systems. Such coordination must 
extend to new generation of any Interconnection Customer because, as 
stated in this provision, a Transmission Provider must offer all 
generators service that is comparable to the service that it provides 
to its own generation or that of its Affiliates.
    123. Section 3.6--Withdrawal--Proposed LGIP Section 3.6 provided 
that the Interconnection Customer would have the option to withdraw its 
Interconnection Request at any time with written notice to the 
Transmission Provider. If the Interconnection Customer fails to adhere 
to the requirements of the interconnection procedures, its request 
would be deemed withdrawn and the Transmission Provider would provide 
written notice of the deemed

[[Page 49859]]

withdrawal along with a written explanation. In either instance, the 
Interconnection Customer would lose its Queue Position and pay all of 
the Transmission Provider's prudently incurred costs up to the 
withdrawal. The Transmission Provider would be required to update its 
OASIS queue posting and to refund the Interconnection Customer any 
portion of the Interconnection Customer's deposits or study costs that 
exceeds the costs that the Transmission Provider has incurred, 
including interest. In the event of a withdrawal, the Interconnection 
Customer would be able to request all information the Transmission 
Provider developed for any completed Interconnection Studies, up to the 
date of withdrawal of the Interconnection Request, subject to the 
confidentiality provisions of Section 13.1.
Comments
    124. FirstEnergy and WEPCO assert that an Interconnection Customer 
should be given a reasonable amount of time to address purported 
deficiencies before a Transmission Provider deems a request withdrawn 
because the purported deficiency may not have been adequately 
communicated to the Interconnection Customer.
    125. Cinergy requests that this section be modified to require that 
a Transmission Provider provide written notice to the Transmission 
Owner of any Interconnection Customer withdrawal notice it receives or, 
alternatively, that the Interconnection Customer provide notice to both 
the Transmission Provider and the Transmission Owner.
    126. When an Interconnection Customer withdraws its application, 
NYTO supports having the Interconnection Customer pay the Transmission 
Provider all monies due to the Transmission Provider before it is 
allowed to obtain any Interconnection Study data or results. Duke 
Energy argues that an Interconnection Customer's responsibility for 
prudently incurred costs terminates either when the Transmission 
Provider receives the Interconnection Customer's notice of withdrawal 
or, in the event the Interconnection Customer is deemed to have 
withdrawn its application for interconnection, when the Transmission 
Provider provides notice of withdrawal.
    127. PJM believes that the proposed language implies that if an 
Interconnection Customer disputes its loss of Queue Position, it would 
remain in the queue pending Dispute Resolution. PJM advocates instead 
the approach the Commission has accepted in the PJM Tariff, that is, 
when an Interconnection Customer is disqualified from the queue, it is 
eliminated from the queue unless and until a Dispute Resolution process 
restores its position.
Commission Conclusion
    128. The Commission agrees with FirstEnergy and WEPCO that 
Interconnection Customers should be given an opportunity to address any 
deficiencies before their requests are deemed withdrawn by the 
Transmission Provider. Proposed LGIP Section 3.6 is revised in the 
Final Rule LGIP accordingly.
    129. The Commission agrees with Duke Energy that an Interconnection 
Customer's responsibility for a Transmission Provider's prudently 
incurred cost terminates at the earlier of either when the Transmission 
Provider receives the Interconnection Customer's notice of withdrawal 
or when the Transmission Provider provides a notice of withdrawal after 
deeming an Interconnection Request to be withdrawn. The Commission also 
agrees with NYTO that when the Interconnection Customer withdraws its 
application, it must pay all monies due to the Transmission Provider 
before it is allowed to obtain any Interconnection Study data or 
results.
    130. We agree with PJM that it is unreasonable for an 
Interconnection Customer to maintain its Queue Position pending Dispute 
Resolution. In most cases, Dispute Resolution and any related 
litigation would create delays, and it would be unfair to delay the 
projects of lower queued Interconnection Customers while a higher-
queued Interconnection Customer's Queue Position is in dispute. The 
Commission clarifies this section in the Final Rule LGIP accordingly.
    131. Section 4--Queue Position--Proposed LGIP Section 4 would 
establish the Interconnection Customer's Queue Position (i.e., the 
chronological priority assigned to an Interconnection Request), which 
would be used to determine both the order in which studies are 
performed and the cost responsibility for the facilities necessary to 
accommodate the Interconnection Request. At the Transmission Provider's 
option, Interconnection System Impact Studies would be performed 
serially as Interconnection Requests are received or in clusters, as 
discussed below. Proposed LGIP Section 4 also described when a Queue 
Position can be transferred to another entity, and when an 
Interconnection Customer could modify its Interconnection Request 
without losing its Queue Position.
    132. Section 4.1--General--Proposed LGIP Section 4.1 required the 
Transmission Provider to assign a Queue Position to the Generating 
Facility based on the date and time of receipt of a valid 
Interconnection Request. However, if the sole reason that an 
Interconnection Request is deemed invalid is lack of information 
required in the Interconnection Request, and if the Interconnection 
Customer provides such information in accordance with Section 3.3.3 of 
the proposed LGIP, the Transmission Provider would then be required to 
assign the Interconnection Customer a Queue Position based on the date 
and time that the Interconnection Request was initially filed. The 
Queue Position of each Interconnection Request would be used to 
determine the order of performing the Interconnection Studies, which 
would determine the cost responsibility for the facilities necessary to 
accommodate the Interconnection Request. This is because the facilities 
needed for one Interconnection Customer are affected by the facilities 
needed for other generators that come before it in the queue.
Comments
    133. TVA observes that the level of commitment by Interconnection 
Customers to complete an interconnection varies. A change in the 
request of a higher queued Generating Facility will affect lower queued 
generators because it may require restudies. It states that the 
``first-come, first-served'' method rewards an Interconnection Customer 
that simply is the first in line, even if it has not done the 
preparation to make a complete and legitimate Interconnection Request. 
According to TVA, this is costly and unfair to other Interconnection 
Customers. It also asserts that if an Interconnection Customer seeks to 
change its Point of Interconnection, it should be placed in a lower 
position in the queue. Ameren has similar concerns and states that it 
has a high withdrawal rate for Interconnection Requests. It claims that 
fewer restudies would be needed if a Transmission Provider could study 
only ``serious'' requests.
    134. American Wind Energy believes that projects in the queue when 
the Final Rule takes effect should receive equal treatment under the 
new rule. It states that since summer 2000 several developers have 
accelerated their projects and have executed interconnection 
agreements. These developers should be able to have their

[[Page 49860]]

interconnection agreements revised to be consistent with the Final Rule 
LGIA.
    135. PJM believes that the proposed procedures do not help 
eliminate projects that are not economically feasible. Accordingly, the 
Interconnection Customer should be required to meet milestones to show 
significant commitment to a project. The fixed schedule approach (which 
fixes a time period for completing an Interconnection Study after the 
receipt of an Interconnection Request) undermines integrated regional 
planning, since it forces planners to study each Interconnection 
Request independently of other Interconnection Requests that are 
located in close electrical proximity. PJM also notes that such 
projects could have related effects on the Transmission System and 
overall expansion alternatives.
    136. PacifiCorp believes that there will be problems in the queuing 
and the Interconnection System Impact Study process if an 
Interconnection Customer is allowed to request an Interconnection Study 
when it does not expect to begin construction or operations for a long 
time. According to PacifiCorp, long lead times substantially increase 
the uncertainty that the project will be completed. An independent 
Transmission Provider should be given more flexibility in addressing 
these issues.
    137. TECO Energy states that the Interconnection Request must 
provide a demonstration of Site Control for the Generating Facility at 
the time of the initial request before it may enter the queue. It 
states that it is inefficient to commit a Transmission Provider's 
resources to the study of a request until the project achieves a level 
of certainty and specificity that justifies the commitment of 
resources, even though the Interconnection Customer pays for the 
Interconnection Studies.
    138. EEI, PSEG, and SoCal Edison all state that they generally 
support establishing a single integrated queue per RTO region.
    139. EEI states that Interconnection Service and delivery service 
are separate and that there is no need to combine them. It believes 
that any combination of the two services requires a single 
Interconnection Feasibility Study for several generators, would likely 
overly complicate the queuing process, and subsequently delay study 
completions. It contends that the separation of interconnection and 
delivery services is critical to designing a queue that is appropriate 
for both non-Standard Market Design and Standard Market Design service.
    140. Xcel observes that the ``first-come, first-served'' queue 
process does not take into account either the transmission planning 
requirements of RTOs or state integrated resource planning statutes and 
rules, which often require the use of a ``portfolio approach'' whereby 
state-regulated load-serving entities select between competing 
generation providers based on the total cost of generation and 
transmission.
    141. Xcel supports a process similar to the periodic ``open 
season'' used for gas pipelines, in which the Transmission Provider or 
RTO would periodically solicit market interest in incremental 
transmission capacity and then develop a transmission plan that serves 
the various market needs at the lowest overall cost.
    142. TXU wants the Final Rule to allow a Transmission Provider, 
RTO, or ISO to create queues that are periodically opened and closed, 
based on a predetermined time period. Proposed projects should be 
placed into a queue according to the date of the Interconnection 
Request.
    143. American Wind Energy, NYISO, and Tenaska believe that Queue 
Position should not be used exclusively to determine the cost 
responsibility for the facilities necessary to accommodate the 
Interconnection Request. American Wind Energy states that the first 
wind project in the queue should not be required fund the Network 
Upgrades for what logically will be a long term large scale build-out 
of an entire wind resource area. NYISO also contends that the 
Commission's proposal is not workable in the NYISO system because its 
interconnection cost allocation rules are not based on Queue Position. 
Instead, Interconnection Facility costs are determined each year and 
allocated on the basis of pro-rata electrical impact among the members 
of a group of projects that have reached a specified point in the New 
York State project permitting process.
Commission Conclusion
    144. The Commission understands Ameren's and PJM's concerns that 
uncertainty about project withdrawal creates difficulties for a 
Transmission Provider in planning for necessary Network Upgrades. 
Having an Interconnection Customer and a Transmission Provider 
establish agreed upon milestones at the Scoping Meeting should help to 
ensure that the Transmission Provider's planning process reflects only 
the interconnection of Generating Facilities that are making 
satisfactory progress toward completion. Also, a Transmission Provider 
facing difficulties of this sort may wish to consider conducting 
Interconnection Studies on a clustered basis (see discussion below). 
Factors other than Queue Position also must be considered in 
determining the cost responsibility of an Interconnection Customer, 
especially when a Transmission Provider conducts Interconnection 
Studies on a clustered basis. However, we believe that Queue Position 
must play a critical role in determining cost responsibility, and 
expect the Transmission Provider to give appropriate recognition to 
Queue Position when it develops its cost allocation rules.
    145. We agree with TVA's comment that moving the proposed Point of 
Interconnection should lead to a lower Queue Position if it is a 
Material Modification under Final Rule LGIP Section 4.4.3. Section 4.1 
is revised accordingly in the Final Rule.
    146. With respect to TECO Energy's comments on the need to 
demonstrate Site Control in the initial application, the Commission 
notes that LGIP Section 3.3.1 and the definition of Site Control in the 
Final Rule already require early demonstration of Site Control or 
posting a deposit of $10,000. Section 7.2 of the Final Rule LGIP 
requires a demonstration of Site Control prior to executing the 
Interconnection System Impact Study Agreement. We conclude that these 
provisions adequately demonstrate Site Control.
    147. There must be a single integrated queue per geographic region. 
We note that it was the method generally agreed upon during the 
Commission staff's Technical Conference on Queuing. However, we will 
afford an RTO or ISO the flexibility to propose queues and queuing 
rules designed to meet its regional needs.
    148. Xcel's and TXU's comments are addressed in the Commission 
Conclusions discussion for Section 4.2 (Clustering), which follows.
    149. Section 4.2--Clustering--For the purpose of the 
Interconnection System Impact Study, Section 4.2 of the NOPR LGIP 
permitted the Transmission Provider to study Interconnection Requests 
serially or in clusters. The Transmission Provider would be allowed to 
simultaneously study all Interconnection Requests received during a 
period not to exceed 90 Calendar Days (``the queue cluster window'') 
except requests for Energy Resource Interconnection Service, which 
would be studied serially. The Transmission Provider would be permitted 
to study an Interconnection Request separately if warranted by Good 
Utility Practice based upon the

[[Page 49861]]

electrical remoteness of the proposed Generating Facility.
Comments
    150. Various Transmission Providers including BPA, NYTO, and PJM 
recommend that the queue cluster window be extended from 90 to 180 days 
so that the study process may be fully integrated into the Transmission 
Provider's planning process, and to ensure that one set of 
Interconnection Studies can be completed before the next round begins. 
PJM states that a 180-day window reasonably balances the competing 
objectives of completing Interconnection Studies as rapidly as possible 
and ensuring that the study process produces meaningful regional 
expansion plans that induce economically efficient decisions by 
generation developers. PSEG sees merit in the clustering approach, but 
states that it should be tied to the planning process and have 
specified start and end dates. PJM opposes the requirement to study 
requests for Energy Resource Interconnection Service serially, arguing 
that most of the tests applied to Energy Resource Interconnection 
Service and Network Resource Interconnection Service are the same.
    151. The Midwest ISO seeks clarification whether a cluster refers 
to a group of Interconnection Requests that were submitted during a 
specified time period, such as 90 Calendar Days, or to a group of 
Generating Facilities that are located in geographic proximity to one 
other, or both. The Midwest ISO seeks further clarification whether 
each Interconnection Request is to be studied serially within the 
cluster in order to determine the cost of Network Upgrades for each, or 
all of the Interconnection Requests are to be studied simultaneously, 
which will determine only the total cost of Network Upgrades. It argues 
that if the latter is the case, the Commission will need to prescribe a 
way to allocate the total cost of Network Upgrades to each 
Interconnection Customer within the cluster.
    152. American Wind Energy states that clustering is the best method 
to interconnect both large and small generators in a balanced regional 
planning process, and also facilitates the coordinated completion of a 
useful Interconnection System Impact Study.
Commission Conclusion
    153. In the Final Rule, we are setting the queue cluster window for 
conducting Interconnection System Impact Studies at 180 Calendar Days. 
As the commenters make clear, the principal benefit of studying 
Interconnection Requests in clusters is that it allows the Transmission 
Provider to better coordinate Interconnection Requests with its overall 
transmission planning process, and, as a result, achieve greater 
efficiency in both the design of needed Network Upgrades and in the use 
of its planning resources. We are persuaded by the arguments of PJM and 
others that the proposed 90-day cluster window is too short to achieve 
this result, and that a 180-day window is more appropriate.
    154. We are also persuaded by PJM that if the Transmission Provider 
elects to study Interconnection Requests in clusters, requests for both 
Energy Resource Interconnection Service and Network Resource 
Interconnection Service should be included in the clustered 
Interconnection Studies. Requiring the Transmission Provider to perform 
System Impact Studies for Energy Resource Interconnection Service 
requests on a serial basis would mean that many of the efficiency 
benefits of clustering would be lost. When a Transmission Provider 
conducts Interconnection Studies on a clustered basis, the 
Interconnection Customer may have to wait longer to obtain study 
results than it would if its request were studied serially. However, 
some of the information that an Interconnection Customer needs is 
provided by the Interconnection Feasibility Study, which is conducted 
serially and early in the study process.
    155. Clustering is strongly encouraged in queue management and the 
Interconnection Study process for all Transmission Providers. We 
vigorously support the use of queue windows to manage the 
Interconnection Study process. In response to the Midwest ISO's 
comments, Final Rule IP Section 4.2 has been modified to better explain 
the clustering process. Queue windows with regular, fixed opening and 
closing dates are essential to an orderly process. Once fixed, any 
changes to these dates should be announced with a posting on the 
Transmission Provider's OASIS at least 180 days in advance of the 
change. Cluster windows enable the Transmission Provider to evaluate 
all pending Interconnection Requests periodically and systematically in 
light of the Transmission Systems's capabilities at the time of each 
clustered Interconnection System Impact Study.
    156. Clustering (by queue position and electrical location) ensures 
that the regional expansion plan considers all uses of the Transmission 
System and enables expansion of the system to be accomplished in the 
most efficient manner reasonably achievable. However, projects that are 
electrically isolated can still be studied independently. Additionally, 
allocation of cost responsibility for system upgrades and jointly used 
facilities is more readily managed by studying requests in clusters. 
Absent the ability to cluster interconnection requests, it is difficult 
to distinguish the Transmission Provider's cost responsibility for 
baseline reliability upgrades from the responsibility of 
Interconnection Customers and other developers for the costs of 
upgrades required to accommodate their Interconnection Requests since 
each request would have to be studied serially. Equally important, 
Interconnection Studies for smaller generators can be more easily 
expedited. These efficiencies are best obtained using clustered queue 
windows, not through the sequential processing of Interconnection 
Requests.
    157. Section 4.3--Transferability of Queue Position--The Commission 
proposed in Section 4.3 of the NOPR LGIP that an Interconnection 
Customer may transfer its Queue Position to another entity if such 
entity acquires the Generating Facility identified in the 
Interconnection Request and the Point of Interconnection does not 
change.
Comments
    158. National Grid states that the Commission should resist 
requests from those that propose to make Queue Position a tradable 
commodity to gain flexibility over the timing of their proposed 
projects. National Grid offers several arguments against allowing this: 
(1) It would create an unnecessary commodity that would encourage 
gaming in competitive markets, (2) it would render the interconnection 
queue process unmanageable because the trading of Queue Positions would 
make it impossible to build sets of assumptions on which to base 
studies, (3) it would add another layer of administrative burdens for 
Transmission Providers; and (4) the disputes over Queue Position that 
are likely to arise would divert the Transmission Provider's attention 
away from facilitating reasonably prompt interconnections. Instead, the 
Commission should adopt a subordinate application process like the one 
implemented in NEPOOL, which allows a project sponsor to accelerate the 
construction and operation of its facilities application ahead of other 
projects in the queue in return for the sponsor's assumption of the 
risks associated with building the facilities in a sequence different 
from the study order of the queue.
    159. The CPUC believes that changes resulting from an 
Interconnection Customer selling its Queue Position

[[Page 49862]]

could harm subsequent Interconnection Customers in the queue, since it 
could affect the portfolio of technologies in the queue and the 
diversity of the Transmission System as a whole. According to the CPUC, 
an Interconnection Customer wishing to sell its position should be 
required to provide assurances that it will pay not only for any 
Interconnection Studies needed as a result of the change, but also for 
the costs to subsequent Interconnection Customers in the queue as a 
result of the change. The seller of the Queue Position should also be 
liable for any obligations that the buyer of the position is unable to 
fulfill in the event of a Default.
Commission Conclusion
    160. While the commenters raise legitimate concerns with Queue 
Position trading in general, we conclude that the restrictions on 
transferability that are already contained in Section 4.3 address these 
concerns. Section 4.3 of the Final Rule LGIP permits an Interconnection 
Customer to transfer its Queue Position to another entity only if such 
entity acquires the specific Generating Facility identified in the 
Interconnection Request and the Point of Interconnection does not 
change. These limitations on transferability greatly reduce the 
potential impact on lower queued Interconnection Customers. The new 
Interconnection Customer would also be required to show, under Section 
4.4.3 of the Final Rule LGIP, that any proposed change is not a 
Material Modification.
    161. Section 4.4--Modifications--Proposed LGIP Section 4.4 would 
have required that the Interconnection Customer submit to the 
Transmission Provider, in writing, modifications to any information 
provided in the Interconnection Request. Either the Interconnection 
Customer or the Transmission Provider would be permitted to identify 
changes to the planned interconnection that may reduce the costs and 
increase the benefits (including reliability) resulting from the 
interconnection. If the changes are acceptable to the Transmission 
Provider and Interconnection Customer (such acceptance not to be 
unreasonably withheld), the Transmission Provider would make the 
necessary changes and proceed with interconnection restudies in 
accordance with Sections 6.4, 7.6 and 8.5 of the LGIP, as applicable. 
Accordingly, the Generating Facility would retain its Queue Position.
    162. Section 4.4.1--Proposed LGIP Section 4.4.1 LGIP would allow an 
Interconnection Customer to make the following modifications to its 
Interconnection Request, provided that it makes them before returning 
the executed Interconnection System Impact Study Agreement to the 
Transmission Provider: (1) A reduction of as much as 60 percent in the 
megawatt output of the proposed project, (2) modification of the 
technical parameters associated with the Generating Facility technology 
or the step-up transformer impedance characteristics, (3) modification 
of the interconnection configuration, or (4) any other type of change 
except to the proposed Point of Interconnection. Any increase in the 
Generating Facility's megawatt output would be placed at the end of the 
queue.
Comments
    163. Dynegy argues that item (4) is confusing, makes the other 
items in the list redundant, and does not belong in this section. 
Several commenters, including Duke Energy and WEPCO, advocate allowing 
an Interconnection Customer to increase the output of its Generating 
Facility by up to ten percent of the voltage level of the line to which 
it is interconnecting without affecting its Queue Position.
Commission Conclusion
    164. We agree with Dynegy that item (4) does not belong in this 
section. The item more appropriately belongs in Section 4.4.3. 
Accordingly, Final Rule LGIP Section 4.4.3 includes the following 
sentence: ``Any change to the Point of Interconnection shall constitute 
a Material Modification.''
    165. We reject the other commenters' proposal to allow an 
Interconnection Customer to increase the output of its Generating 
Facility by up to ten percent. The percentage by which the capacity of 
the proposed Generating Facility could be increased without 
substantially changing the size and configuration of necessary Network 
Upgrades needed to accommodate the change in output would depend on the 
size and location of the Generating Facility and the voltage level at 
the Point of Interconnection, among other things. This could vary 
significantly from case to case, and may well be less than ten percent.
    166. Section 4.4.3--Proposed LGIP Section 4.4.3 would have required 
that, prior to making a modification other than one specifically 
permitted by Sections 4.4.1, 4.4.2, and 4.4.5, the Interconnection 
Customer may first ask the Transmission Provider to evaluate whether 
the modification is actually a Material Modification. A Material 
Modification would be a modification that has a material effect on the 
cost or timing of a lower queued Interconnection Customer. The 
Transmission Provider would be required to evaluate the proposed 
modification and inform the Interconnection Customer in writing whether 
the modification would considered be a Material Modification. The 
Interconnection Customer could then either withdraw the proposed 
modification or submit a new Interconnection Request for such 
modification.
Comments
    167. SoCal Water District and Dynegy ask the Commission to clarify 
the definition of Material Modification to avoid disputes between the 
Parties regarding the Generating Facility's Queue Position. Ameren 
argues that a modification that is proposed as not being ``material'' 
may in fact be a Material Modification. FirstEnergy opposes giving the 
Transmission Provider the discretion to determine whether a request is 
a Material Modification. El Paso observes that reading proposed LGIP 
Sections 4.4.3 and 4.4.5 together implies that the Transmission 
Provider will be forced to judge whether an extension of three years or 
more is material and to determine if a cost effect or other project 
change is material. El Paso supports defining a Material Modification 
as: (1) A change greater than 12 months in Commercial Operation Date, 
(2) an increase of greater than $100,000 or 10 percent in the 
Transmission Provider's cost that a later queued Interconnection 
Customer would bear; or (3) a change greater than five miles in the 
location of, or any change in the voltage level at, the Point of 
Interconnection. Edison Mission believes that the Final Rule LGIP 
should clarify the effect of material improvements and modifications to 
existing Generating Facilities on the interconnection status and the 
rights of such Generating Facilities. The Bureau of Reclamation 
expresses concern that the NOPR does not define how or when an existing 
Interconnection Customer would be affected by Material Modifications. 
The Bureau of Reclamation is concerned because design and approval of 
its generator refurbishment is a federal responsibility and would be 
subject to the federal appropriation process.
Commission Conclusion
    168. It is not necessary to revise proposed LGIP Section 4.4.3 to 
define precisely what constitutes a Material Modification. The impact 
of a modification depends in large part on the size, location, type of 
project and the

[[Page 49863]]

configuration of the Transmission Provider's Transmission System. The 
various Interconnection Studies will identify the modification's impact 
on other Interconnection Customers. This impact determines if the 
change is indeed a Material Modification. We leave it to the 
Transmission Provider to make that determination; however, it must do 
so on a reasonable basis.
    169. Section 4.4.4--Proposed LGIP Section 4.4.4 in the NOPR LGIP 
provided that, upon receipt of an Interconnection Customer's request 
for modification permitted under Section 4.4, the Transmission Provider 
would perform any necessary additional Interconnection Studies as soon 
as practicable, but in no event later than 30 Calendar Days after 
receiving notice of the Interconnection Customer's request. Any 
additional Interconnection Studies resulting from such modification 
would be done at the Interconnection Customer's expense.
Comments
    170. Exelon asserts that this section is not practical and is 
punitive to all lower queued Interconnection Customers. It contends 
that each time a modification is requested, a Transmission Provider or 
Transmission Owner must begin studying the modification within 30 Days 
and all work on the Interconnection Studies of all lower queued 
Interconnection Customers must be halted.
Commission Conclusion
    171. We adopt Section 4.4.4 as proposed. While any modification 
that requires additional study can pose a challenge to the Transmission 
Provider's schedules and resources, the modifications that are 
permitted under Section 4.4 occur early enough in the study process 
that their effect on Interconnection Customers lower in the queue 
should be limited. Furthermore, since all Interconnection Requests are 
evaluated in the same restudy, this provision appropriately balances 
the Interconnection Customer's need for flexibility to change the 
project with the Transmission Provider's need for certainty in resource 
costs and schedules.
    172. Section 4.4.5--Section 4.4.5 of the NOPR LGIP provided that an 
extension of less than three cumulative years in the Commercial 
Operation Date of the Generating Facility should not be considered a 
Material Modification and should be treated in the same manner as in 
Section 12.3 (Construction Sequencing).
Comments
    173. Salt River Project seeks clarification on what to do when the 
original In-Service Date is at the maximum allowable ten years (under 
Proposed LGIP Section 3.3.1) and there is a request for a three year 
extension. Duke Energy supports allowing an Interconnection Customer to 
request an extension of all dates, including the In-Service Date, for 
periods of less than three cumulative years. Sempra believes that the 
Transmission Provider needs greater flexibility to manage and evaluate 
its Transmission System for delays of more than one year.
    174. Westconnect RTO finds that two provisions in this Section 
contradict Western Electricity Coordinating Council (WECC) procedures. 
They are allowing the Interconnection Customer to decide to extend its 
Generating Facility's Commercial Operation Date for up to a total of 
three cumulative years and providing that such extensions are not 
material and should be handled through construction sequencing. 
Westconnect RTO asserts that regional practices concerning transmission 
planning and reliability should be honored.
    175. SoCal PPA and El Paso believe that a three year period is an 
unreasonably long time to permit suspension of interconnection because 
it interferes with the Transmission Provider's ability to manage the 
queue and plan its system.
Commission Conclusion
    176. With respect to Salt River Project's request, we clarify that 
the term contained in Final Rule LGIP Section 3.3.1 is ten years, or 
longer if the Transmission Provider agrees. Furthermore, such agreement 
shall not be unreasonably withheld. This clarification also addresses 
Duke Energy's and Sempra's concerns.
    177. With respect to Westconnect RTO's assertion that this section 
contravenes WECC procedures, as stated above, we would permit 
modifications to the Final Rule LGIA and Final Rule LGIP where the 
Transmission Provider shows that there are legitimate regional 
differences, such as the WECC procedures, that would support such 
modifications. As to other arguments that three years is an 
unreasonably long time to permit extensions of the Commercial Operation 
Date, the Commission recognizes that such flexibility places a burden 
on the Transmission Provider's expansion planning process, but these 
extensions in most cases are well within the scope of other unforeseen 
changes that affect the planning process. The Final Rule therefore 
adopts Section 4.4.5 as proposed.
    178. Section 5--Procedures for Interconnection Requests Submitted 
Prior to Effective Date of Interconnection Procedures--Section 5 of the 
proposed LGIP described the procedures for assigning a Queue Position 
prior to the effective date of the Final Rule LGIP. It also proposed a 
transition process for a Transmission Provider with an Interconnection 
Request that is outstanding when the Final Rule takes effect.
    179. Section 5.1--Queue Position for Pending Requests--Proposed 
LGIP Section 5.1 provided that any Interconnection Customer assigned a 
Queue Position prior to the effective date of the Final Rule LGIP would 
retain that Queue Position. Also, if an Interconnection Study Agreement 
has not been executed as of the Final Rule effective date, then that 
Interconnection Study and subsequent Interconnection Studies would be 
processed in accordance with the Final Rule. However, an executed 
Interconnection Study Agreement would be completed in accordance with 
the terms in place at the time of execution of that agreement. The 
proposed section also provided that if an interconnection agreement has 
been tendered as of the Final Rule effective date, the Transmission 
Provider and Interconnection Customer would finalize its terms. To the 
extent necessary, outstanding requests would transition to the Final 
Rule procedures within a reasonable period of time, not to exceed 60 
Calendar Days. Reasonable extensions would be granted.
Comments
    180. The Midwest ISO recommends adding a subsection to the LGIP 
that permits Interconnection Requests in existing queues of non-RTO 
Transmission Providers to be merged into the queue of the RTO or ISO 
based on the original request dates at the time the Transmission 
Provider joins the RTO.
    181. Central Maine supports the grandfathering of existing 
interconnection agreements that are filed with and accepted by the 
Commission as of the effective date of the Final Rule LGIP and Final 
Rule LGIA.
    182. Sempra argues that it is inappropriate to mandate Parties to 
agree to an interconnection agreement tendered but not fully negotiated 
prior to the issuance of the Final Rule because, otherwise, the 
tendering Party could tender them on the eve of the Final Rule going 
into effect and the

[[Page 49864]]

other Party would be compelled to negotiate under the Final Rule's 
terms and conditions. Therefore, either Party should be permitted to 
set aside unexecuted but tendered interconnection agreements prior to 
the effective date of the Final Rule.
    183. MidAmerican states that the proposed provision of Section 
5.1.2, which established a transition period from the old queue 
processes to the new Final Rule provisions that should not exceed 60 
days, is practical only for projects that are in their early stages. It 
proposes adding the phrase ``provided that any existing interconnection 
agreement or Interconnection Study Agreement shall remain in full force 
and effect'' for projects that have an executed interconnection 
agreement. MidAmerican also states that the Commission should clarify 
that this transition period is only for those outstanding requests for 
which Interconnection Studies Agreements and interconnection agreements 
have yet to be executed prior to the Final Rule going into effect. 
Similarly, Central Maine seeks clarification of the meaning of pending 
or outstanding requests.
    184. BPA states that this provision should be clarified with regard 
to the circumstances under which an Interconnection Customer with an 
existing Interconnection Request may request an extension of applicable 
deadlines.
Commission Conclusion
    185. The purpose of Proposed LGIP Section 5.1 was to ensure that a 
Generating Facility that has an established Queue Position prior to the 
Final Rule taking effect will continue to hold its position. This is 
also the case mentioned by the Midwest ISO for merging new members into 
the RTO's queue when the Transmission Provider joins an RTO. However, 
on compliance, discretion will be granted to RTOs or ISOs to propose 
queuing rules customized to their needs, in accordance with the 
``independent entity standard'' (described in part II.C.5).
    186. Under proposed LGIP Section 5.1.1, the Interconnection Studies 
for which the Parties have an executed Interconnection Study Agreement 
would be completed under the Interconnection Study Agreement's terms, 
but any remaining studies would be completed under the Final Rule LGIP 
study procedures. The Commission concludes that this situation may 
cause confusion and unnecessary complications in the event that the 
Transmission Provider's existing study procedures conflict with those 
in the Final Rule LGIP. To provide further clarification, and to 
prevent situations in which an Interconnection Customer may be forced 
to comply with conflicting or redundant study requirements, the 
Commission modifies this section to give the Interconnection Customer a 
choice. Under the Final Rule LGIP Section 5.1.1.2, if an 
Interconnection Customer has signed an Interconnection Study Agreement 
as of the effective date of the Final Rule, the Interconnection 
Customer will have the option to either continue with the rest of its 
Interconnection Studies under the Transmission Provider's existing 
study process or complete those remaining studies for which it does not 
have a signed Interconnection Study Agreement under the Final Rule 
LGIP.
    187 .In response to Central Maine, we clarify that existing 
interconnection agreements that are filed with and accepted by the 
Commission prior to the effective date of this Final Rule will remain 
in effect. Regarding Sempra's request to allow the Parties to set aside 
interconnection agreements tendered but not executed before the 
issuance of the Final Rule, the Commission concludes that this decision 
is best left to the discretion of the Parties. If the Parties decide to 
continue their negotiations, they have until the Final Rule's effective 
date to submit their agreement to the Commission to qualify for 
grandfathering. Accordingly, Final Rule LGIP Section 5.1.1.3 states 
that an executed or unexecuted interconnection agreement submitted for 
approval by the Commission before the effective date of the Final Rule 
will be grandfathered and will not be rejected simply for failing to 
conform to the Final Rule LGIA.
    188. With respect to Central Maine's and MidAmerican's requests for 
clarification of the term ``outstanding requests'' in Section 5.1.2, we 
clarify that the term refers to any request for interconnection that 
has been submitted to a Transmission Provider but has not yet been 
submitted to the Commission for approval prior to the effective date of 
this Final Rule.
    189. There is no need to adopt MidAmerican's proposed language 
regarding the adequacy of a 60 day transition period in Section 5.1.2 
since the Final Rule allows an Interconnection Customer to extend 
deadlines, and the 60 day period applies only to Interconnection 
Requests with outstanding studies for which an Interconnection Study 
Agreement has not been executed. We expect the Parties to work together 
during the transition period to ensure that no Interconnection Request 
is unreasonably delayed.
    190. Finally, we deny BPA's request to explain the circumstances 
under which an Interconnection Customer may request an extension 
because these circumstances are likely to differ in each case. However, 
we expect that a Transmission Provider will grant an extension if it 
can be reasonably accommodated in a nondiscriminatory manner in the 
transition to the Final Rule LGIP.
    191. Section 5.2--New Transmission Provider--Proposed LGIP Section 
5.2 provided that if the Transmission Provider transfers control of its 
Transmission System to a successor Transmission Provider while an 
Interconnection Request is pending, the original Transmission Provider 
would also transfer to the successor any deposit or payment that 
exceeds the cost that it has incurred. The original Transmission 
Provider would be required to coordinate with the successor to complete 
any appropriate Interconnection Study. If an Interconnection Agreement 
has not been executed or if an unexecuted Interconnection Agreement has 
been filed with the Commission, the Interconnection Customer would have 
the option to complete negotiations with either the initial 
Transmission Provider or the successor.
Comments
    192. Dairyland Power observes that the initial Transmission 
Provider should provide interest to the successor when the balance of 
deposits or payments is transferred. Also, if the study costs of the 
new Transmission Provider exceed the amount of the deposit, it is 
reasonable that the Interconnection Customer make up the difference.
    193. Without explanation, NYTO states that the Interconnection 
Customer should not have the option of negotiating with a successor 
Transmission Provider.
Commission Conclusion
    194. With respect to Dairyland Power's comment, the Commission 
clarifies that any additional costs incurred by the successor in excess 
of the deposit amounts must be treated in accordance with the Final 
Rule and paid upon completion of the Interconnection Studies. The 
Commission does not adopt NYTO's position and instead permits the 
Interconnection Customer to negotiate with the successor Transmission 
Provider.
    195. Section 6--Interconnection Feasibility Study; Section 7--
Interconnection System Impact Study; Section 8--Interconnection 
Facilities Study; Section 10--Optional

[[Page 49865]]

Interconnection Study--Proposed LGIP Sections 6, 7 and 8 describe (1) 
the analyses that would be conducted for each of the Feasibility, 
System Impact, and Facilities Studies, (2) the Interconnection 
Customer's responsibility regarding the actual cost of each study and 
of any restudies that may be required; and (3) the right an 
Interconnection Customer would have to maintain its Queue Position and 
substitute a Point of Interconnection, identified by either the 
Transmission Provider or the Interconnection Customer, if any of these 
Interconnection Studies uncovers a result that the Interconnection 
Customer and Transmission Provider did not contemplate during the 
Scoping Meeting. These sections would also allow an Interconnection 
Customer to direct that one of the alternative Points of 
Interconnection specified in the related Interconnection Feasibility 
Study Agreement and Scoping Meeting be used if the Transmission 
Provider cannot agree on a substitute Point of Interconnection.
    196. Section 10 proposed that the Interconnection Customer may ask 
the Transmission Provider to perform a reasonable number of Optional 
Interconnection Studies. An Optional Interconnection Study would be a 
sensitivity analysis based on assumptions provided by the 
Interconnection Customer. The scope of the Optional Interconnection 
Study would be to identify the Interconnection Facilities, Network 
Upgrades and the costs that may be required to provide transmission 
service or Interconnection Service.
    197. The following paragraphs group together discussions of 
Sections 6, 7, 8, and 10 because of the relationships among the topics 
and provisions.
General Comments Related to the Feasibility Study, the System Impact 
Study, the Facilities Study and the Optional Interconnection Study
    198. A number of commenters, including El Paso, FirstEnergy, the 
Midwest ISO, National Grid, and PJM, are concerned that the proposed 
Interconnection Studies will take longer to complete than the 
Interconnection Studies that a Transmission Provider typically performs 
today, and will lead to delays in the development of new generation 
projects. TVA believes that the study deadlines are unrealistic, 
particularly for Transmission Providers with medium to large 
interconnection queues. It opposes having to study the Energy Resource 
Interconnection Service and Network Resource Interconnection Service 
during each phase of the Interconnection Study process. Instead, TVA 
proposes that the Interconnection Customer should be able to designate 
only one Interconnection Service for study purposes or adjusting the 
time lines in Sections 6, 7, 8, and 10 to reflect the increased scope 
of work required by giving the Interconnection Customer such 
alternatives. Imperial Irrigation opposes the NOPR's proposed 
Interconnection Studies because it does not have enough resources to 
conduct them. NYISO urges the Commission to allow for regional 
differences in the Final Rule.
    199. Entergy opposes giving the Interconnection Customer the 
ability to continually modify its selected Point of Interconnection 
throughout the study process. TVA opposes an Interconnection Customer 
maintaining its position in the queue if the Interconnection Customer 
changes its Point of Interconnection in any of the Interconnection 
Studies. PJM believes that to allow the Interconnection Customer to 
require restudies throughout the Interconnection Study process is 
inconsistent with a workable regional planning process.
    200. Sempra opposes setting a dollar figure for good faith 
estimates of Interconnection Study costs in the standardized study 
agreements that are attached as appendices to the Final Rule LGIA. It 
supports leaving the cost estimates blank in the appendices, with the 
expectation that the Transmission Provider would provide the timely 
good faith estimate later. Sempra also supports limiting the 
Transmission Provider's ability to pass on cost overruns to the 
Interconnection Customer.
    201. Central Maine notes that the proposed Interconnection Study 
agreements would fix the ``good faith estimated cost for performance'' 
of each particular study. It argues that this is inappropriate because 
Interconnection Study costs vary greatly from one Generating Facility 
to another. It believes that Transmission Providers should be able to 
tailor each Interconnection Study agreement to the particular 
Generating Facility, and to include the good faith Interconnection 
Study cost estimate in each such agreement. If prepayment of 
Interconnection Study costs is not required, the deposit should be a 
percentage of the estimated total Interconnection Study cost, as 
opposed to a fixed dollar amount.
    202. Several commenters seek additional requirements in assigning 
cost responsibility for Interconnection Studies to the Interconnection 
Customer. Central Maine notes that there are no proposed payment terms 
governing restudies, and supports clearly stating that the 
Interconnection Customer should bear full cost responsibility for a 
restudy. BPA supports requiring the Interconnection Customer to pay the 
estimated cost of the Interconnection Feasability Study in advance 
under Sections 6.1 and 7.2. National Grid's position is that the 
Interconnection Customer should prepay the costs of all Interconnection 
Studies because the Transmission Provider is exposed to the risk of 
nonpayment. Central Vermont PSC believes that the Interconnection 
Customer should bear study costs involving an Affected System.
    203. Several entities seek clarification on the proper scope of, 
and standards for, the Interconnection Studies. Cal ISO believes that a 
study should encompass conditions that include off-peak scenarios and 
contingency conditions. Entergy and Westconnect RTO argue that the NOPR 
LGIP does not mention types of Interconnection Studies other than load 
flow, short circuit, and stability studies. They suggest that the scope 
of the Interconnection Studies not be limited to these named analyses, 
but be expanded to include additional Interconnection Studies conducted 
in accordance with Good Utility Practice. PSNM supports expanding the 
scope of Interconnection Studies to encompass any analyses dictated by 
Good Utility Practice and allow for additional time on specialized 
Interconnection Studies, if needed. PacifiCorp supports permitting the 
Transmission Provider to require additional Interconnection Studies 
recommended or required by a regional reliability council, including 
remedial action margin studies. Georgia Transmission believes that the 
Transmission Provider's obligation under Sections 6.2 and 6.3 is 
inconsistent with the limited scope of the Interconnection Feasibility 
Study, which is defined to consist only of a power flow study and a 
short circuit analysis.
    204. Southern asks whether, if one Interconnection Request is 
required to be restudied by a date certain, all other lower queued 
requests would have to be restudied by that same date. Southern 
believes that this would be unworkable and unrealistic.
    205. NYTO seeks details on specific study procedures for each of 
the Interconnection Studies.
Comments Related to Interconnection Feasibility Studies
    206. SoCal Water District argues that an Interconnection Customer 
should

[[Page 49866]]

lose its position in the queue when the Interconnection Feasability 
Study uncovers a result that was not contemplated during the Scoping 
Meeting, instead of being allowed to designate a different site for the 
Point of Interconnection, as proposed. It says that this will encourage 
the Interconnection Customer to make the right choice at the beginning. 
It also comments that the Interconnection Customer should not be 
assigned a Queue Position until after the completion of the 
Interconnection Feasability Study.
    207. NSTAR believes that Interconnection Feasibility and 
Interconnection Facilities Studies should be at the option of the 
Interconnection Customer.
    208. The Midwest ISO points out that it is not always possible to 
determine accurately when an Interconnection Customer in a high Queue 
Position will actually come on line and that this could affect the 
accuracy of the Interconnection Feasability Study requested by a lower 
queued Interconnection Customer.
    209. Sempra supports allowing a Transmission Provider or 
Transmission Owner to consider in its Interconnection Studies the In-
Service Dates of all proposed generation projects, even those lower in 
the queue. This is so that the studies produce sound results for 
reliability purposes and consider all projects that will come on line 
at approximately the same time.
Comments Related to Interconnection System Impact Studies
    210. FirstEnergy opposes as unreasonably short the proposed three 
day period of time during which a Transmission Provider must give an 
Interconnection Customer a non-binding good faith estimate of the cost 
and time frame for completing an Interconnection System Impact Study.
Comments Related to Optional Interconnection Studies
    211. Proposed LGIP Section 10.1 would allow the Interconnection 
Customer to ask the Transmission Provider to perform a reasonable 
number of Optional Interconnection Studies on or after the date the 
Interconnection Customer receives the results of the Interconnection 
System Impact Study associated with its Interconnection Request. A 
Transmission Provider would have five days from the date it receives a 
request for an Optional Interconnection Study to give the 
Interconnection Customer an Optional Interconnection Study Agreement. 
Commenters raise concerns with the requirement to perform Optional 
Interconnection Studies, cost responsibilities for such studies, and 
the proposed deadlines.
    212. Southern opposes allowing an Interconnection Customer to 
require that a Transmission Provider perform Optional Interconnection 
Studies. Southern believes that Optional Interconnection Studies will 
delay the process by tying up Transmission Provider resources that 
could be dedicated to performing the required studies. BPA contends 
that allowing the Interconnection Customer to require an unspecified 
number of Optional Interconnection Studies, while requiring that the 
standard Interconnection Studies be performed within the standard 
deadlines, places an unreasonable burden on the Transmission Provider.
    213. Nevada Power opposes having to conduct Optional 
Interconnection Studies on the grounds that allowing changes to the 
original Interconnection Request violates the queue rights of other 
Interconnection Customers by giving additional study time and priority 
to the Optional Interconnection Study request. Dominion Resources makes 
a similar point.
    214. SoCal Edison believes that the Final Rule should provide for 
Optional Interconnection Studies (1) that are performed outside the 
NOPR LGIP time line, (2) if it is understood by the Interconnection 
Customer who elects to implement a study that implements Material 
Changes, that it could impact the Generating Facility's Queue Position; 
and (3) may not exceed for each requester a maximum of two Optional 
Interconnection Studies. NYISO urges the Commission to delete Section 
10.1 to reduce the number of studies that the Transmission Provider 
must perform. The Midwest ISO believes that the Interconnection 
Feasibility Study may be elected and can serve as the Optional 
Interconnection Study described in Section 10.
    215. On the issue of cost responsibility, Central Vermont PSC 
supports having the Interconnection Customer compensate the 
Transmission Provider for the costs of an Optional Interconnection 
Study, including all charges incurred by an Affected System.
    216. With respect to the deadlines associated with Optional 
Interconnection Studies, FirstEnergy believes that the five day 
turnaround period for the Transmission Provider to provide an Optional 
Interconnection Study Agreement, as called for in Section 10.1, is too 
short and that a ten day period would be better. Cal ISO also supports 
a ten day turnaround time.
Commission Conclusion--General Comments
    217. The proposed time frames for completing Interconnection 
Studies are reasonable. For each of the studies, the NOPR LGIP allows 
for the possibility that the Transmission Provider will not be able to 
complete the study within the allotted time. In these cases, the NOPR 
LGIP provides that the Interconnection Customer and the Transmission 
Provider will come to an acceptable accommodation. As to Imperial 
Irrigation's concern that it lacks sufficient resources to conduct the 
Interconnection Studies, Section 13.4 gives the Parties the option of 
using a contractor to complete the required studies at the 
Interconnection Customer's expense and Section 4.2 allows the 
Transmission Provider to cluster Interconnection Studies, thereby 
saving time and money.
    218. We believe that the proposed Interconnection Study deposit 
amounts are high enough to ensure that an Interconnection Customer is 
serious about its Interconnection Request. In the absence of 
standardized Interconnection Study cost estimates, a Transmission 
Provider could set the Interconnection Study costs at such high levels 
so as to discourage entry by competing generators.
    219. Central Maine does not identify the benefits of making 
Interconnection Study deposits a percentage of the estimated 
Interconnection Study costs. Because the proposed dollar amounts are 
reasonable and are the result of the consensus process, the Commission 
adopts them for the Final Rule LGIP.
    220. We find that the proposed provisions regarding the payment of 
study costs by the Interconnection Customer are adequate. The NOPR LGIP 
makes clear that the Interconnection Customer is responsible for the 
actual costs of all Interconnection Studies. We reject the proposal 
that the Interconnection Customer fully prepay the costs of 
Interconnection Studies because the advance payment would be based on 
Transmission Provider estimates rather than actual costs. The 
Commission recognizes that the costs of performing Interconnection 
Studies may vary by Interconnection Customer because each 
interconnection is unique. The unique features of each interconnection 
should be identified either in the Scoping Meeting or early in the 
Interconnection Study process so that the Transmission Provider can 
offer the Interconnection Customer a reasonable estimate of what the 
actual

[[Page 49867]]

study costs will be. However, we will require the Transmission Provider 
to provide a detailed and itemized accounting of the Interconnection 
Study costs in the relevant invoices. If the Interconnection Customer 
disputes the study cost, it may pursue dispute resolution procedures as 
described in Section 13.5 of the Final Rule LGIP.
    221. With regard to commenters' various concerns about the proper 
scope of, and standards for, the Interconnection Studies, the 
Commission emphasizes that the Final Rule LGIP should not be 
interpreted as preventing the Transmission Provider from studying 
Interconnection Requests in accordance with Good Utility Practice and 
regional reliability requirements. The Transmission Provider may 
conduct necessary Interconnection Studies using any standards that are 
generally accepted within the region and consistently applied to all 
generation projects, including those of the Transmission Provider. If 
these standards differ from those specified in the LGIP, the 
Transmission Provider must include them in its compliance filing and 
may implement them only upon approval of the Commission. For this 
reason, we decline to specify detailed study procedures for each 
Interconnection Study beyond what is specified in the Final Rule LGIP.
Commission Conclusion--Interconnection Feasibility Studies
    222. With regard to the concern that allowing changes to original 
Interconnection Requests would be unworkable and would violate the 
rights of lower queued Interconnection Customers due to the need to 
conduct numerous restudies, the Final Rule allows the Transmission 
Provider to take additional time to complete the necessary work. In 
addition, although lower queued Interconnection Customers may be harmed 
when their Interconnection Requests must be restudied due to actions of 
an Interconnection Customer higher in the queue, they also benefit from 
the flexibility to request that the Transmission Provider study a 
substitute Point of Interconnection. In this respect, the Commission 
finds that the NOPR LGIP strikes an appropriate balance and, 
accordingly, adopts it in the Final Rule.
    223. Regarding Sempra's question about which projects within the 
queue should be considered when performing Interconnection Studies, the 
Commission requires the Transmission Provider to consider in its 
Interconnection Studies all generators with both higher and lower 
queued Interconnection Requests that could affect the Network Upgrades 
associated with integrating these generators with the Transmission 
System, as specified in the Final Rule LGIP.
Commission Conclusion--Interconnection System Impact Studies
    224. In response to FirstEnergy's comment that there is 
insufficient time to provide cost and time estimates for completing an 
Interconnection System Impact Study, we find that three Business Days 
is reasonable. We note that prior to the Interconnection System Impact 
Study, the Transmission Provider will have conducted the 
Interconnection Feasibility Study and the Parties will have met to 
discuss the study results. Accordingly, through this ongoing process, 
the Transmission Provider will have had ample time to anticipate and 
prepare such estimates.
Commission Conclusion--Optional Interconnection Studies
    225. The Commission finds that commenters' concerns about allowing 
an Interconnection Customer to request Optional Interconnection Studies 
are misplaced. Such studies are for informational purposes only and are 
to be completed within an agreed upon time period using Reasonable 
Efforts. If Optional Interconnection Studies place too great a burden 
on the resources of the Transmission Provider, the Final Rule permits 
the use of a contractor at the Interconnection Customer's expense. The 
Commission is neither eliminating these provisions nor, as SoCal Edison 
proposes, limiting the number of Optional Interconnection Studies an 
Interconnection Customer may request. These studies may provide 
information needed by the Interconnection Customer. Since the 
Interconnection Customer pays for the Optional Interconnection Study 
and a contractor may be used for this purposes, the impact on a 
Transmission Provider is minimal.
    226. Section 9--Engineering & Procurement (``E&P'') Agreement (In 
the NOPR: Agreements)--Proposed LGIP Section 9 provided a mechanism for 
the Transmission Provider and the Interconnection Customer to enter 
into an Engineering & Procurement Agreement prior to executing the 
LGIA. An Interconnection Customer may ask that the Transmission 
Provider begin engineering and procurement of long lead-time items 
necessary for the establishment of the interconnection. The 
Transmission Provider is not obligated to offer an agreement if the 
Interconnection Customer is in Dispute Resolution as a result of an 
allegation that the Interconnection Customer has failed to meet any 
milestones or comply with any other sections of the LGIP. This section 
also specifies the cost and other obligations of the Interconnection 
Customer.
Comments
    227. Calpine and Duke Energy propose that Section 9.1 be expanded 
to cover situations where the construction of certain Network Upgrades 
takes place prior to the execution of the LGIA. Duke Energy states that 
the Transmission Provider should be prohibited from refusing to enter 
into an interim Engineering & Procurement Agreement unless the 
Interconnection Customer's failure to meet milestones directly affects 
the Transmission Provider's ability to meet its obligation under the 
Engineering & Procurement Agreement. FirstEnergy states that it is 
inappropriate to enter into an Engineering & Procurement Agreement 
prior to the execution of an LGIA, or the filing of an unexecuted LGIA 
with the Commission.
Commission Conclusion
    228. We disagree with Calpine and Duke Energy regarding 
construction. The Final Rule does not require the construction of 
Network Upgrades prior to the execution of the LGIA; nor do we see why 
the Transmission Provider should be placed at risk by committing to the 
construction of such Network Upgrades prior to the execution of an 
LGIA. Regarding FirstEnergy's comments, we conclude that it is 
reasonable to allow the Parties to enter into an Engineering & 
Procurement Agreement for long lead-time items necessary to accommodate 
the interconnection as long as the Interconnection Customer bears the 
cost risk. Likewise, in response to Duke Energy and consistent with the 
language in the NOPR, we conclude that it is reasonable to require a 
Transmission Provider to offer an Engineering & Procurement Agreement 
only if the Interconnection Customer has met its obligations under the 
Final Rule LGIP. Accordingly, we adopt Section 9 in the Final Rule as 
proposed.
    229. Section 11--Standard Large Generator Interconnection Agreement 
(In the NOPR: Interconnection Agreement)--Proposed LGIP Section 11 
includes procedures for tendering, negotiating, executing, and filing 
an interconnection agreement.
    230. Section 11.1--Tender--Proposed LGIP Section 11.1 provided that 
the Transmission Provider simultaneously submit to the Interconnection 
Customer

[[Page 49868]]

the draft Interconnection Facilities Study Report and a draft LGIA, to 
the extent practicable, in the form of the pro forma LGIA. Within 30 
Calendar Days after the issuance of the draft Interconnection 
Facilities Study report and a draft pro forma LGIA, the Transmission 
Provider shall submit the completed draft of the LGIA.
Comments
    231. Central Maine believes that 30 days is an unreasonable time 
frame in which to prepare such technically detailed documents as the 
appendices to the interconnection agreement, and it should therefore be 
increased to 60 days.
Commission Conclusion
    232. Central Maine has not convinced us of the difficulty of 
preparing the interconnection agreement appendices in 30 Calendar Days 
or shown a need to extend the time in which to prepare them to 60 
Calendar Days. Accordingly, the Commission retains the proposed 30 
Calendar Day requirement for the Transmission Provider to tender the 
completed interconnection agreement.
    233. Section 11.2--Negotiation--Proposed LGIP Section 11.2 provided 
that the Transmission Provider and the Interconnection Customer be 
required to negotiate the terms contained in the appendices to the 
interconnection agreement for up to 60 Calendar Days after tender of 
the final Interconnection Facilities Report. If the Interconnection 
Customer determines that negotiations are at an impasse, it could 
either request termination of the negotiations and request submission 
of the unexecuted interconnection agreement to the Commission, or 
initiate Dispute Resolution procedures. If the Interconnection Customer 
requests termination of the negotiations, but within 60 Calendar Days 
thereafter fails to request either the filing of the unexecuted LGIA or 
initiate Dispute Resolution, it would be deemed to have withdrawn its 
Interconnection Request.
Comments
    234. FirstEnergy contends that the provisions of this section 
unduly restrict the ability of the Parties to negotiate a resolution. 
It argues that proposed LGIP Section 11.2 provides no recourse for the 
Transmission Provider in circumstances where the negotiations are at an 
impasse and the Interconnection Customer neither terminates the 
Interconnection Request nor continues to negotiate in good-faith. 
FirstEnergy recommends that Section 11.2 of the NOPR IA be revised to 
include the following language: ``Unless otherwise agreed to by the 
Parties, if the Interconnection Customer has not executed the 
Interconnection Agreement, requested the filing of an unexecuted 
[interconnection agreement], or initiated Dispute Resolution procedures 
within 60 days of the tender of the completed draft of the LGIA 
Appendices, the Interconnection Customer will have been deemed to have 
withdrawn its Interconnection Request.
Commission Conclusion
    235. The Commission agrees with FirstEnergy that there could be 
circumstances where the Parties could be unduly restricted in their 
negotiations and therefore adopts the language proposed by FirstEnergy 
in the Final Rule LGIP.
    236. Section 11.3--Execution and Filing--Proposed LGIP Section 11.3 
would have the Interconnection Customer demonstrate Site Control to the 
Transmission Provider, and provides specific milestones as evidence of 
Site Control. It would also provide that the Transmission Provider file 
the LGIA as soon as practicable, but not later than ten Business Days 
after receiving either the two executed originals of the LGIA, or the 
request by the Interconnection Customer to file an unexecuted LGIA.
Comments
    237. Mirant does not oppose requiring an Interconnection Customer 
to maintain Site Control and provide reasonable evidence that the 
Interconnection Customer has met some of the specified milestones. 
However, it asks the Commission to clarify what constitutes 
``reasonable evidence'' of Site Control. Other commenters, including 
PJM and PJMTO, assert that the Commission should give the 
Interconnection Customer more milestones to meet.
    238. PJM opposes letting an Interconnection Customer deposit 
$250,000 instead of demonstrating meaningful progress and believes that 
doing so can lead to clogging and gaming of the queue.
    239. Central Maine requests that the Commission extend from ten to 
30 days the obligation to file, as additional time is needed to prepare 
the filing. It claims that neither Party would be adversely affected by 
such an extension.
Commission Conclusion
    240. We shall modify Proposed LGIP Section 11.3 to better reflect 
the Commission's unexecuted agreement procedure in the OATT.\62\ 
Accordingly, the unexecuted agreement should contain terms and 
conditions deemed appropriate by the Transmission Provider for the 
Interconnection Request. But the LGIA approach differs from the OATT 
approach, since the Parties' obligations may be significantly different 
in the LGIA context. The OATT unexecuted agreement provision requires 
the Transmission Provider to commence providing service as long as the 
Transmission Customer agrees to compensate the Transmission Provider at 
the rate the Commission ultimately determined to be just and 
reasonable. Since the LGIA involves obligations different from those in 
the OATT, including facilities construction that may be undertaken by 
either Party, it is appropriate to give both Parties more flexibility 
to determine whether to proceed under the non-disputed terms of their 
unexecuted agreement. Once the unexecuted agreement is filed, if the 
Parties agree to proceed with design, procurement, and construction of 
facilities and upgrades under the agreed upon terms of the unexecuted 
agreement, they may proceed pending Commission action.
---------------------------------------------------------------------------

    \62\ See Section 15.3 of the OATT.
---------------------------------------------------------------------------

    241. In response to Mirant's request to clarify what constitutes 
``reasonable evidence'' of Site Control, the Commission notes that the 
Final Rule definition of the term specifically lists the types of 
documentation that reasonably demonstrates evidence of Site Control.
    242. PJM proposes to eliminate the $250,000 additional deposit if 
the Interconnection Customer is unable to provide evidence of Site 
Control. It would also have the Generating Facility lose its place in 
the queue if the Interconnection Customer misses a milestone. We find 
that the deposit is a sufficient showing that the Interconnection 
Customer is serious about the project and will continue to work to meet 
the requirements of Site Control and other milestones. Finally, this 
section provides sufficient milestones and penalties to reasonably 
ensure that the Interconnection Customer is intent on completing the 
project.
    243. Central Maine has not provided any support for its request to 
extend the time from ten to 30 days to meet the filing obligations. 
Accordingly, the Final Rule retains the ten Business Days requirement.
    244. Section 12--Construction of Transmission Provider's 
Interconnection Facilities and Network Upgrades--Proposed LGIP Section 
12 required the

[[Page 49869]]

Transmission Provider and the Interconnection Customer to agree to a 
schedule for the construction of Interconnection Facilities and Network 
Upgrades that are needed to accommodate the Interconnection Request. It 
also provided for an Interconnection Customer to request the 
acceleration of Network Upgrades that are needed for a higher-queued 
Interconnection Customer that would not have otherwise been completed 
in time to support the lower queued Interconnection Customer's In-
Service Date as long as it commits to pay any costs associated with 
expediting the project, including the cost of any Network Upgrades 
assigned to the higher-queued Interconnection Customer.
    245. Section 12.1--Schedule--Proposed LGIP Section 12.1 provided 
that the Transmission Provider and Interconnection Customer negotiate 
in good faith to develop a schedule for the construction of the 
Transmission Provider's Interconnection Facilities and Network 
Upgrades.
Comments
    246. Duke Energy and FirstEnergy contend that this section should 
be deleted, since it is already covered in Article 5 of the NOPR LGIA.
Commission Conclusion
    247. The Commission finds no reason to delete Section 12.1. It 
merely states that the Parties must negotiate a construction schedule 
in good faith. The fact that the negotiated construction schedule is in 
Appendix B (Milestones) of the LGIA does not require us to delete 
Section 12.1 from the Final Rule LGIP.
    248. Section 12.2--Permits--Proposed LGIP Section 12.2 provided 
that the Parties specify in the LGIA each Party's responsibility for 
obtaining permits, licenses, and authorizations necessary to construct 
the Interconnection Facilities and Network Upgrades needed to 
accommodate the proposed interconnection in conformance with all 
Applicable Laws and Regulations.
Comments
    249. Duke Energy states that the first sentence of Section 12.2 
should be stricken because it duplicates NOPR LGIA Article 14.1. 
FirstEnergy contends that the entire section should be deleted because 
the topic is more properly addressed in the LGIA. Cinergy asks the 
Commission to clarify that nothing in the section requires the 
Transmission Provider to exercise its power of eminent domain. Central 
Maine argues that the phrase ``nothing in this Section 12.2 shall be 
construed to waive any rights under Applicable Laws and Regulations'' 
should be either deleted or applied to the entire Final Rule LGIP, 
because its inclusion in just one provision creates confusion.
Commission Conclusion
    250. The Commission disagrees with Duke Energy. Proposed LGIP 
Section 12.2 merely requires the Parties to specify in the LGIA each 
Party's responsibility for obtaining permits, licenses, and 
authorizations necessary to construct the Interconnection Facilities 
and Network Upgrades. Article 14.1 of the NOPR LGIA, on the other hand, 
states that each Party's obligations under the LGIA are conditioned 
upon regulatory approval from relevant Governmental Authorities.
    251. In response to Cinergy's assertion, while the Commission does 
not require that the Transmission Provider exercise its right of 
eminent domain in all instances, we do not prohibit it from doing so. 
Rather, in the Final Rule, consistent with the Commission's discussion 
of NOPR LGIA Article 5.11 (now Final Rule LGIA Article 5.13), Lands of 
Other Property Owners, we require that a Transmission Provider or 
Transmission Owner use efforts similar to those it typically undertakes 
on its own behalf (or on behalf of an Affiliate), which may include use 
of eminent domain rights, to secure permits for the Interconnection 
Customer, unless restricted from doing so by state law.
    252. We agree with Central Maine's arguments and are therefore not 
incorporating into this section the proposed text dealing with the 
waiving of rights under Applicable Laws and Regulations.
    253. Finally, the Commission agrees with FirstEnergy that the 
issues contained in this section are more appropriately discussed in 
the Final Rule LGIA. Accordingly, proposed LGIP Section 12.2 is being 
deleted from the Final Rule LGIP and is being incorporated into the 
Final Rule LGIA as Article 5.14.
    254. Section 12.3--Construction Sequencing (In the Final Rule LGIP: 
Section 12.2)--Proposed LGIP Section 12.3 stated that an 
Interconnection Customer may ask the Transmission Provider to advance 
construction of Network Upgrades supporting other generators that were 
assumed to be completed in time to support the Interconnection 
Customer's Generating Facility's In-Service Date. The Transmission 
Provider would have to use Reasonable Efforts to advance the 
construction of such Network Upgrades, provided that the 
Interconnection Customer commits to pay the Transmission Provider the 
cost of the Network Upgrades and any associated expediting costs. The 
Transmission Provider must refund to the Interconnection Customer the 
costs of any expedited Network Upgrades after the Transmission Provider 
receives payment from the entity for which the Network Upgrades were to 
be originally constructed. Until such costs are refunded, the 
Transmission Provider must provide the Interconnection Customer with 
transmission credits for the costs of the expedited Network Upgrades.
Comments
    255. Duke Energy seeks clarification that (1) the Interconnection 
Customer earlier in the queue is obligated to pay the Transmission 
Provider only the amount not refunded, through credits, to the 
Interconnection Customer requesting the acceleration (and thus is 
eligible for transmission credits only for that amount), (2) the 
Interconnection Customer requesting the accelerated construction is 
reimbursed for Network Upgrade costs only up to the amount of the 
transmission credits not received, (3) the Transmission Provider is not 
required to advance funds for construction or to pay total credits in 
excess of the cost of the Network Upgrades; and (4) the higher-queued 
Interconnection Customer must pay for the expedited Network Upgrades on 
the date that it would have been required to pay were it not for the 
request for acceleration. Duke Energy also notes that there may be 
circumstances when acceleration requires greater expenditures than 
would be required to meet a reasonable construction schedule. It 
therefore recommends that if a Transmission Provider believes that the 
Commission would not allow such expenditures to be included in the 
revenue requirement under traditional ratemaking principles, the 
Transmission Provider should have the opportunity to challenge the 
provision of credits for these costs.
Commission Conclusion
    256. The Commission affirms that an Interconnection Customer higher 
in the queue is obligated to pay the Transmission Provider for only 
that portion of the costs of the expedited Network Upgrades not already 
paid to the Interconnection Customer that requested expedition through 
transmission credits. The Transmission Provider can then forward this 
amount to the expediting Interconnection Customer as a lump sum payment 
for

[[Page 49870]]

the balance of costs that the higher-queued Interconnection Customer is 
owed. At this point, the payment of credits will cease and the payment 
of credits to the higher-queued Interconnection Customer can begin. The 
latter credits will continue until the higher-queued Interconnection 
Customer has been reimbursed for the portion of the Network Upgrade 
costs that it has paid. The Transmission Provider is also not required 
to advance funds for construction or to pay total credits in excess of 
the cost of the Network Upgrades, including any interest that may be 
due. Finally, the higher-queued Interconnection Customer is responsible 
for paying the costs of the advanced Network Upgrade on the date that 
it would have been required to pay had there been no request for 
accelerated construction.
    257. In response to Duke Energy's final concern, the Commission 
recognizes that there may be circumstances under which the Transmission 
Provider, in attempting to accommodate the Interconnection Customer's 
request to accelerate the project, may have to incur costs that would 
exceed what would normally be required to meet a reasonable 
construction schedule. However, we will consider such costs to have 
been prudently incurred unless it is demonstrated in a rate proceeding 
that the Transmission Provider could have met the Interconnection 
Customer's requested In-Service Date at a lower cost through the 
construction of alternative Network Upgrades, or by other means. 
Consequently, the Transmission Provider should have no reason to 
challenge the provision of credits for any costs that it prudently 
incurs.
    258. Consistent with the above discussion, the Final Rule clarifies 
Section 12.3 and removes certain text that is largely redundant.
    259. This section is designated Section 12.2 in the Final Rule 
LGIP.
    260. Section 13--Miscellaneous--Proposed LGIP Section 13 included a 
variety of provisions, described below.
    261. Section 13.1--Confidentiality--Proposed LGIP Section 13.1 
would have required that the Transmission Provider afford confidential 
treatment to all information it receives from the Interconnection 
Customer to process its request for Interconnection Service except for 
information that is in the Interconnection Request and information that 
is or becomes generally available to the public. The Transmission 
Provider would be permitted to use this information only for the 
Interconnection Study and to share it only with those who need it for 
Interconnection Studies and actions to interconnect the Generating 
Facility. The Transmission Provider would not be permitted to share 
such information with the merchant generation or marketing functions of 
the Transmission Provider or its Affiliates' merchant functions or as 
otherwise prohibited by Order No. 889.
    262. The Transmission Provider would be liable to the 
Interconnection Customer for any Breach of confidentiality caused by 
its agent or contractor. If requested by the Interconnection Customer, 
the Transmission Provider would be required to destroy or return to the 
Interconnection Customer information no longer needed. If the 
Transmission Provider is required to disclose the information to any 
regulatory body, it would be obligated to request confidential 
treatment of the information. The Transmission Provider must provide 
the Interconnection Customer with prompt written notice if it receives 
a request for the Confidential Information to allow the Interconnection 
Customer an opportunity to contest the disclosure. The confidentiality 
provisions would not require the Transmission Provider or 
Interconnection Customer to disclose information in violation of any 
confidentiality obligations to third parties.
Comments
    263. Several commenters, including Central Maine and MidAmerican, 
argue that these confidentiality protections should be extended to the 
Transmission Provider as well. Central Maine seeks a clear policy about 
what information may be disclosed, what information must be disclosed, 
the manner of disclosure, and what information must remain confidential 
as part of the interconnection process.
    264. Lakeland seeks reconciliation of the differences between the 
confidentiality provisions of the NOPR LGIA and the NOPR LGIP. 
Specifically, the Final Rule LGIP should accommodate compliance with 
state Open Records laws, including Florida's, as in the NOPR LGIA.
    265. Entergy opposes requiring a Transmission Provider to provide 
Confidential Information, or disclose anything not public, to an 
Interconnection Customer. If that disclosure is required by the Final 
Rule, the confidentiality requirements should be reciprocal and a Party 
should be required to designate which materials warrant confidential 
treatment.
    266. The Midwest ISO agrees with the proposal that Confidential 
Information only be shared among employees of the Transmission Provider 
(including Transmission Owners of Affected Systems) and third parties 
that need the information to perform or review Interconnection Studies. 
Moreover, in accordance with Order No. 889, the information should not 
be shared with individuals responsible for merchant or marketing 
functions. The Midwest ISO also requests that the Commission clarify 
what type of planning information should be kept confidential for 
security reasons and what information should be made available, perhaps 
under a non-disclosure agreement executed by the Parties. Proposed LGIP 
Section 13.1 would have required that the Transmission Provider keep 
confidential all information provided by the Interconnection Customer 
related to Interconnection Service that is not provided in the 
Interconnection Request; the Midwest ISO and NERC state that some 
information in the Interconnection Request may be commercially 
sensitive, such as unit-specific data, and should be kept confidential.
    267. GE Power notes that developers generally prefer to look at 
alternative project scenarios before going ``on the record'' with their 
plans. GE Power requests that the Commission address the balance 
between commercial confidentiality or security-based secrecy and the 
need to make the data available so that studies and business 
forecasting can be completed.
    268. NERC comments that the information provided by Interconnection 
Customers that may be considered confidential under Section 13.1 is 
needed to protect reliability because it generally is shared not only 
with directly affected neighboring systems, but also with regional and 
NERC study groups for modeling inter-regional and interconnection 
reliability effects. NERC states that this data is generally provided 
in a manner that masks ownership and other commercial terms and that 
NERC has standards of conduct for Reliability Coordination and a data 
confidentiality agreement. It requests that mechanisms remain in place 
to ensure the availability and confidentiality of such data so that 
Interconnection Customers will provide data needed for reliability 
assessment. NERC proposes that an Interconnection Customer identify 
specific information to be protected as confidential and that the 
Transmission Provider share this information only with parties to 
confidentiality agreements.

[[Page 49871]]

Commission Conclusion
    269. In response to Central Maine's and several others' requests 
that the confidentiality provision in the NOPR LGIP be made more 
specific, the Commission is incorporating into Section 13.1 certain 
aspects of the confidentiality provisions in Article 22 of the LGIA. 
These include a definition of Confidential Information, procedures for 
the release of Confidential Information, and guidance regarding how 
Confidential Information should be treated when it is requested by the 
Commission as part of an investigation. Both Parties are eligible to 
use the protection afforded by the revised section as long as the 
information is identified as Confidential Information in accordance 
with the section. This revision should satisfy commenters that sought 
greater specificity regarding procedures for maintaining and disclosing 
information in the confidentiality provisions in the LGIP. It also 
eliminates any significant conflicts between the LGIP and LGIA 
confidentiality provisions. The Final Rule LGIP Section 13.1 differs 
from Final Rule LGIA Article 22 only with respect to the provisions in 
Article 22 that address the fact that the confidentiality obligations 
arise under a signed Interconnection Agreement.
    270. This revision eliminates from the Section 13.1 the exception 
for information that appears in the Interconnection Request. Under the 
revised provision, it is the Interconnection Customer's responsibility 
to designate the information submitted in its Interconnection Request 
that should remain confidential.
    271. Lakeland requests that the Commission adopt provisions that 
accommodate compliance with state open records laws. Public utilities 
also may be subject to information restrictions arising from national 
security concerns. As noted above, the Commission expects all public 
utilities to meet basic standards for system infrastructure and 
operational security. In addition, if state laws indeed conflict with 
the confidentiality and information sharing addressed in this 
provision, the Commission expects that public utilities will make 
conforming changes to these provisions in their compliance filings and 
explain the statutory basis for such changes.
    272. The Commission agrees with the Midwest ISO and NERC that the 
Final Rule must allow information to be shared with Transmission 
Provider representatives of NERC and other regional planning groups, 
since to deny them this information may undermine Transmission System 
reliability and modeling efforts. Section 13.1 of the Final Rule allows 
the Parties to share Confidential Information with an independent 
transmission administrator or reliability organization as long as the 
disclosing party agrees to promptly notify the other Party in writing 
and to seek to protect the Confidential Information from public 
disclosure by separate confidentiality agreement or other reasonable 
measures. We do not, as the Midwest ISO requests, specify the planning 
information that may be made available, as it is likely that the data 
will vary by region.
    273. Finally, GE Power proposes that this rulemaking address what 
information a Transmission Provider should make available to a would-be 
Interconnection Customer before the submission of an Interconnection 
Request. We decline to do so. This Final Rule addresses 
interconnection, not the general availability of information to all 
those who have not yet submitted an Interconnection Request.
    274. Section 13.3--Obligation for Study Costs--Proposed LGIP 
Section 13.3 would have required the Interconnection Customer to pay 
the actual costs of the Interconnection Studies. If any deposit exceeds 
the actual cost of the study, that amount would be refunded to the 
Interconnection Customer or offset against the cost of any future 
Interconnection Studies associated with the Interconnection Request. 
Proposed LGIP Section 13.3 also stated that the Transmission Provider 
would not be obligated to perform or continue to perform any 
Interconnection Studies unless the Interconnection Customer has paid 
all undisputed amounts under this section.
Comments
    275. PJM argues that the absence of significant milestones in 
Section 13.3 amplifies the opportunities for an Interconnection 
Customer to dispute its bill and string its project along at little 
cost. Any refusal to pay an invoiced study cost should be a Default 
that triggers withdrawal of the Interconnection Request.
    276. The Midwest ISO believes that the Transmission Provider should 
be permitted to collect interest on any unpaid amounts not in dispute, 
and Duke Energy believes that deposits in excess of the actual study 
cost should be entitled to earn interest from the day a deposit is 
credited to an account.
    277. Sempra would require the Interconnection Customer to pay for 
simple and inexpensive Interconnection Studies up front, and to pay for 
expensive and complicated studies through periodic payments.
Commission Conclusion
    278. The Commission declines to adopt any of the proposed changes 
to Section 13.3 in the Final Rule. While an Interconnection Customer 
could delay the interconnection process merely by disputing its bill, 
the Commission is not convinced that a significant number of 
Interconnection Customers will to act in this manner, since most 
Interconnection Customers presumably will want to have their projects 
on line as soon as possible. Furthermore, requiring the Interconnection 
Customer to pay all invoiced amounts, no matter how unreasonable, or 
lose its Queue Position would invite abuse on the part of the 
Transmission Provider.
    279. In response to the Midwest ISO and Duke Energy, the payment of 
interest on study deposits and unpaid study costs tend to offset one 
another over time. Moreover, the Commission is not persuaded that the 
interest costs would be large enough to warrant the additional 
administrative expense that the Transmission Provider would incur in 
tracking the amounts due. Also, the requirement to pay a deposit and 
then additional amounts as they come due will generally achieve the 
result that Sempra seeks.
    280. Finally, to ensure that the Interconnection Customer is 
adequately informed regarding the actual costs of Interconnection 
Studies, we revise Section 13.3 to require the Transmission Provider to 
provide a detailed and itemized accounting of the Interconnection Study 
costs in the relevant invoices.
    281. Section 13.4--Third Parties Conducting Studies--Proposed LGIP 
Section 13.4 provided that the Interconnection Customer be able to 
require the Transmission Provider, within 30 days of its notification, 
to use a consultant to complete the Interconnection Study at issue if 
(1) the Parties cannot agree to the timing of the completion of the 
Interconnection Study, or (2) the Interconnection Customer receives 
notice from the Transmission Provider that the Transmission Provider 
will not complete an Interconnection Study within the applicable time 
frame, or (3) the Interconnection Customer receives from the 
Transmission Provider neither the Interconnection Study nor a notice 
about not completing the Interconnection Study. In such situations, the 
Interconnection Study would be conducted at the Interconnection 
Customer's expense and

[[Page 49872]]

in the case of (3), the Interconnection Customer could submit a claim 
to Dispute Resolution to recover the costs of the third party study. 
The consultant would be required to follow the LGIP protocols and use 
the information it receives to do the Interconnection Study for the 
sole purpose of completing the study. The Transmission Provider would 
be required to cooperate with the consultant to complete and issue the 
Interconnection Study in the shortest reasonable time.
Comments
    282. Some commenters, including Duke Energy, EPSA, NYISO, and 
Sunflower Electric, endorse the NOPR proposal to allow an 
Interconnection Customer to request a consultant to undertake or 
complete an Interconnection Study, while others advocate the 
Transmission Provider being allowed to initiate use of a consultant to 
accelerate completion of Interconnection Studies, as well. Sunflower 
Electric sees use of a consultant as a short-term means to alleviate a 
Transmission Provider's backlog. Central Maine seeks clarification of 
the process for selecting the consultant. It argues that a 30 day 
deadline for a Transmission Provider to issue an RFP and select a 
consultant is not realistic.
    283. BPA, MidAmerican, and PJM question whether use of a consultant 
will speed up the study process, whether it will significantly reduce a 
Transmission Provider's overall study effort, and whether it will help 
a Transmission Provider to more efficiently study multiple 
Interconnection Requests. They are concerned that any benefits may be 
limited to situations in which Interconnection Customers' projects are 
studied individually, on a non-integrated basis, in isolation from 
other higher-queued Interconnection Requests and system improvements 
and expansions. Others recommend allowing a Transmission Provider to 
complete pending Interconnection Studies for higher-queued 
Interconnection Requests before turning its databases, workpapers, and 
study results over to the consultant to help it move forward with its 
study. In addition, PJM observes that an independent Transmission 
Provider, such as an RTO or ISO, has no incentive to delay completion 
of an Interconnection Study. NYISO would have the ISO direct and review 
any consultant Interconnection Studies.
    284. BPA proposes allowing a Transmission Provider to ignore the 
consultant's study if it is not completed by the deadline. BPA also 
wants sufficient time for the Transmission Provider, as ``the expert'' 
in regard to its system, to review the study to ensure that it is 
adequate and to make necessary changes to it.
Commission Conclusion
    285. Based on the foregoing comments and a balancing of the 
interests of an Interconnection Customer (to obtain the results of any 
necessary Interconnection Studies as soon as possible) and the 
responsibility of Transmission Provider (to efficiently and effectively 
plan its Transmission System), the Commission will permit use of a 
consultant upon the request of an Interconnection Customer at any time 
during the Interconnection Study process. This is subject to the 
Transmission Provider deciding that such use will (1) help maintain or 
accelerate the study process for the Interconnection Customer's pending 
Interconnection Request and (2) not interfere with the Transmission 
Provider's planning processes or hamper the Transmission Provider's 
progress on any other Interconnection Studies for pending 
Interconnection Requests. Moreover, a consultant hired to perform an 
Interconnection Study must follow the same rules and procedures as does 
a Transmission Provider that conducts the study in-house.
    286. The Commission will not specify in Section 13.4 all the terms, 
conditions, and selection processes that would be applicable. Instead, 
the Final Rule leaves it up to the Parties to negotiate the details of 
the timing and process for selecting the consultant, the deadlines for 
the consultant's work, the Transmission Provider's direction and review 
of the consultant's work, the contingency rights and obligations of the 
Parties if the consultant fails to timely deliver a study of adequate 
quality, and any other relevant matters. This added flexibility may 
increase opportunities for the use of a consultant to accelerate the 
completion of necessary Interconnection Studies when it is feasible to 
do so.
    287. Section 13.6--Disputes--Proposed LGIP Section 13.6 detailed 
requirements for the Dispute Resolution process. Upon written notice of 
a dispute arising out of the Interconnection and Operating Agreement or 
its performance, a senior representative or representatives of each 
Party would be required to try to resolve the dispute informally. 
Failing informal resolution within 30 Calendar days, by mutual 
agreement the dispute would be submitted to arbitration, or each Party 
would exercise its other legal or equitable rights. Section 13.6.2 
specified external arbitration procedures, and Section 13.6.3 stated 
that unless otherwise agreed, the arbitrator would be required to 
render a decision within 90 Calendar Days of its appointment that shall 
be binding upon each Party. Final decision affecting jurisdictional 
rates, terms, and conditions would be filed with the Commission. 
Finally, Section 13.6.4 delineated responsibility for costs related to 
the resolution of disputes.
Comments
    288. Central Maine believes that the Parties should be precluded 
from settling by binding arbitration matters that are under the 
Commission's jurisdiction.
Commission Conclusion
    289. Although Section 13.6 proposed making Dispute Resolution 
available only for disputes arising under the LGIA, the Final Rule 
extends the procedures to disputes arising under the LGIP. This section 
is designated Section 13.5 in the Final Rule LGIP.
    290. The Commission has long encouraged the use of alternative 
dispute resolution to resolve disagreements over Commission-
jurisdictional contracts. The Commission's complaint rule, in fact, 
requires Parties to specify in a formal complaint whether they have 
attempted an informal resolution of contract-related disputes, and if 
they have not done so, to explain why not.\63\ Final Rule LGIP Sections 
13.5.1 through 13.5.3 reflect the Commission's policy of encouraging 
alternative dispute resolution without compromising the Commission's 
authority. Final Rule LGIP Section 13.5.3 prevents arbitrators from 
changing the provisions of the interconnection agreement in any manner. 
Arbitrators may only interpret and apply the provisions. Any such 
changes to the interconnection agreement could be made only pursuant to 
Sections 205 and 206 of the Federal Power Act, and would require 
Commission review. Although the arbitrator's decision is binding in so 
far as it is enforceable in any court having jurisdiction, an 
arbitrator's decision must be filed with the Commission if it affects 
jurisdictional rates, terms and conditions of service, Interconnection 
Facilities, or Network Upgrades. Thus, the Commission retains the 
authority to review the arbitrator's decision. Nor do we agree that the 
provision circumscribes the Parties' right to avail themselves of the 
Commission's

[[Page 49873]]

complaint process because under Section 13.5.1, a Party that does not 
agree to arbitration may exercise its rights, including its right to 
bring a complaint to the Commission.
---------------------------------------------------------------------------

    \63\ 18 CFR 385.206(b)(9) (2003).
---------------------------------------------------------------------------

    291. The Commission also adds language to Section 13.6.1 to 
emphasize that Parties should consider using informal dispute 
resolution as well as more formal options. The Commission encourages 
Parties to settle their disputes through other mechanisms (e.g., 
mediation, assisted negotiations, settlement judge procedures) prior to 
commencing arbitration proceedings. Of course, at any point during the 
process the disputing Parties may have recourse to alternative methods 
of dispute resolution, provided that both Parties agree.\64\
---------------------------------------------------------------------------

    \64\ Disputing parties may retain mediators from outside 
sources, or they may use the Commission's Dispute Resolution Service 
or the Commission's settlement judge process.
---------------------------------------------------------------------------

    292. Appendices--Proposed Appendix 1 is the application form for 
making an Interconnection Request. Proposed Appendices 2, 3, 4, and 5 
set forth the terms for the Interconnection Feasibility Study 
Agreement, the Interconnection System Impact Study Agreement, the 
Interconnection Facilities Study Agreement, and the Optional 
Interconnection Study Agreement; and require a deposit of $10,000 for 
the Interconnection Feasibility Study, $50,000 for the Interconnection 
System Impact Study, $100,000 for the Interconnection Facilities Study, 
and $10,000 for the Optional Interconnection Study. The Final Rule LGIP 
retains these appendices. In addition, the Final Rule LGIP incorporates 
the Final Rule Standard Large Generator Interconnection Agreement at 
Appendix 6.

B. Issues Related to the Standard Large Generator Interconnection 
Agreement (LGIA)

1. Overview
    293. The proposed LGIA contained the Parties' contractual 
Interconnection Service rights and obligations. It addressed matters 
such as the effective date and termination costs; regulatory filings; 
scope of service, including interconnection product options; generator 
provided services; Interconnection Facilities engineering, procurement 
and construction; testing and inspection, including start-up and 
synchronization, system protection and controls requirements; 
emergency, and disconnect obligations; metering and communications; 
operations and maintenance; Defaults and indemnifications; transmission 
crediting; audits; and Dispute Resolution.
    294. The proposed LGIA also specified the allocation of the 
responsibilities among the Interconnection Customer, the Transmission 
Provider and Transmission Owner (where the latter is a Party other than 
the Transmission Provider that owns the facilities to which the 
interconnection is being made), in regard to obtaining all permits and 
authorizations necessary to accomplish the interconnection.
    295. Under this Final Rule, if an Interconnection Customer agrees 
to pay for any modification to the Transmission Provider's facilities 
necessitated by the requested interconnection, the Transmission 
Provider is obligated to offer an executable form of LGIA to the 
Interconnection Customer. The interconnection agreement becomes 
effective upon execution by the Parties, subject to acceptance by the 
Commission. If the Interconnection Customer executes the LGIA, the 
Transmission Provider, the Interconnection Customer, and the 
Transmission Owner must perform their respective obligations in 
accordance with the terms of the executed interconnection agreement, 
subject to modification by the Commission.
    296. If the Interconnection Customer determines that negotiations 
are at an impasse, it may initiate Dispute Resolution procedures and, 
if not successful, request submission of the unexecuted agreement to 
the Commission by the Transmission Provider in accordance with Final 
Rule LGIP Section 11. Pending Commission action, the Parties will 
comply with the unexecuted agreement to the extent they can proceed 
under the agreed upon terms.
2. Article-by-Article Discussion of the Proposed LGIA
    297. What follows is a discussion of the proposed LGIA, the 
comments received, and the Commission's conclusion. The order of 
discussion follows the organization of the proposed LGIA, covering 
Articles 1 through 30. Similar to the section-by-section discussion of 
the proposed LGIP, only articles for which issues are raised are 
presented. Readers should note again that article numbers referred to 
in the following discussion are the numbers contained in the proposed 
LGIA. Some proposed articles are renumbered in the Final Rule; mention 
of that fact is made in the Commission Conclusions discussion, where 
appropriate.\65\
---------------------------------------------------------------------------

    \65\ For some of the LGIA provisions that the Commission is 
adopting here, few if any written comments were submitted. 
Commenters tended to use the 30 pages to which they were limited to 
explain what they would change. They made statements of support for 
the rule in general, but did not make article-by-article comments on 
parts that they supported. As a result, the only comments received 
on some articles were calls for change, even if a majority of 
commenters may have indicated general support for the proposed 
articles that they did not specifically comment on.
---------------------------------------------------------------------------

    298. Article 1--Definitions--Proposed LGIA Article 1 contained the 
definitions of terms used throughout the NOPR LGIA. Many of these terms 
appear both in the NOPR LGIP as well as the NOPR LGIA and we have 
decided that a common list of all the defined terms should be included 
in both the Final Rule LGIA and Final Rule LGIP. However, for 
simplicity, discussion of commenters' concerns regarding defined terms 
are discussed in part II.A.2, Section 1 (Definitions).
    299. Article 2--Effective Date, Term and Termination--Proposed LGIA 
Article 2 included the proposed effective date, the term of the 
proposed LGIA, and the procedures for its termination.
    300. Article 2.2--Term of Agreement--Article 2.2 proposed that the 
LGIA remain in effect for ten years, or longer by request, and be 
automatically renewed for each successive one year period thereafter.
Comments
    301. Exelon, NYTO and PG&E believe that automatic renewal is 
unreasonable because it allows the LGIA to remain in effect for an 
indefinite period. PG&E argues that the LGIA should be for a fixed term 
(20 years, for example), because the ten year initial term coupled with 
automatic renewals could make it last forever without giving the 
Transmission Provider an opportunity to terminate the LGIA except in 
the case of a Default by the Interconnection Customer. PG&E further 
argues that a longer fixed term without automatic renewal gives the 
Parties the flexibility to change the terms of the LGIA at the end of 
the term to reflect new market structures as they may develop.
Commission Conclusion
    302. We adopt Article 2.2 as proposed. Automatic renewal is an 
efficient mechanism to renew the LGIA. It mitigates a non-independent 
Transmission Provider's market power by allowing the Interconnection 
Customer to renew without renegotiation. At the same time, the 
interests of the Transmission Provider

[[Page 49874]]

are adequately protected as it can terminate the LGIA in case of 
Default by the Interconnection Customer.
    303. The Commission also notes that the LGIA, in addition to 
addressing the electrical connection of the Interconnection Customer to 
the Transmission Provider's Transmission System, also fixes the 
performance, operational, and financial obligations of the Parties even 
after the Generating Facility begins commercial operation. These 
obligations and responsibilities are of indefinite duration, existing 
as long as the Generating Facility is connected to the Transmission 
Provider's Transmission System. Therefore, it is appropriate for the 
term of the LGIA to be indefinite as well.
    304. In addition, a ten year minimum term allows the Parties to 
avoid tax liability for the payments to the Transmission Provider under 
current Internal Revenue Service policy.\66\
---------------------------------------------------------------------------

    \66\ See part II.B.2 Article 5.14.1 (Interconnection Customer 
Payments Not Taxable).
---------------------------------------------------------------------------

    305. Article 2.3.1--Written Notice--Proposed LGIA Article 2.3.1 
provides that the Interconnection Customer may terminate the LGIA after 
giving the Transmission Provider 30 Calendar Days advance written 
notice.
Comments
    306. MidAmerican proposes requiring an Interconnection Customer to 
provide three years' advance notice to terminate the LGIA. According to 
MidAmerican, the unexpected retirement of the Generating Facility may 
result in reduced system reliability due to decreased generation 
resources, and a Transmission Provider may need to construct or upgrade 
its own generating or transmission facilities if this occurs. 
MidAmerican notes that three years is the time customarily required to 
construct such facilities. Therefore, a three year termination 
provision would provide a Transmission Provider the opportunity to 
maintain reliability if the Generating Facility shuts down 
unexpectedly.
Commission Conclusion
    307. We are not persuaded to increase the advance notice and 
termination period to three years as proposed by MidAmerican. 
MidAmerican's concern appears to be that the Generating Facility, due 
to several years of load growth and other changes, may be essential to 
system reliability. Utilities should not allow themselves to become 
critically dependent on one generator; however, if they do, they can 
enter into a ``reliability must-run'' contract before the 
Interconnection Customer exercises its right to terminate. While there 
may be a problem if many Interconnection Customers were to cancel 
concurrently, we do not believe that the LGIA is the best vehicle for 
addressing this problem, or that every Interconnection Customer in 
every circumstance should be constrained by a three year termination 
provision whether or not such a general problem exists.
    308. However, we extend the notice period to 90 Calendar Days in 
order to conform with the Commission's Regulations, which provide that 
the Transmission Provider is required to notify the Commission of the 
proposed cancellation or termination of a contract at least 60 Calendar 
Days, but no more than 180 Calendar Days, before the cancellation or 
termination is proposed to take effect.\67\
---------------------------------------------------------------------------

    \67\ 18 CFR 35.15 (2003).
---------------------------------------------------------------------------

    309. Article 2.3.2--No Commercial Operation--Proposed LGIA Article 
2.3.2 would have provided that the Transmission Provider be allowed to 
terminate the LGIA if the Interconnection Customer has not met its 
obligation to achieve commercial operation of its Generating Facility 
within five years of the scheduled Commercial Operation Date or fails 
to be available for operation for a period of five years unless a major 
Generating Facility upgrade is in progress.
Comments
    310. Mirant favors deleting this provision. It asserts that there 
is no valid reason for a Transmission Provider to terminate the LGIA if 
the Interconnection Customer has paid for the necessary system upgrades 
and has met every other obligation under the LGIA. Others point out 
that PJM's interconnection agreement does not include such a provision. 
Mirant argues that the Transmission Provider should be able to 
terminate the LGIA only if the Interconnection Customer defaults under 
the terms and conditions of the LGIA. PSNM and Dairyland Power also 
favor deleting this provision altogether and claim that, at best, it 
should be left to the Parties to negotiate a reasonable period for not 
achieving commercial operation without risking termination of the LGIA.
    311. Most Transmission Providers, on the other hand, object to the 
five year window for achieving commercial operation as being too long, 
claiming that one to three years is a more reasonable period of 
time.\68\ They point out that the Interconnection Customer determines 
the Generating Facility's Commercial Operation Date without any input 
from the Transmission Provider and that the Interconnection Customer 
should not have an additional five years to achieve commercial 
operation.
---------------------------------------------------------------------------

    \68\ E.g., Central Vermont PSC, Cinergy, El Paso, Exelon, 
MidAmerican, and PG&E.
---------------------------------------------------------------------------

    312. Central Vermont PSC also advocates shortening the period from 
five to two years, and expresses concern that proposed LGIA Article 
2.3.2, read with proposed Article 4.1.2, might require a Transmission 
Provider to reserve transmission capacity on its transmission system 
for an Interconnection Customer taking Network Resource Interconnection 
Service for up to five years if the Interconnection Customer fails to 
meet its scheduled Commercial Operation Date or fails to be operable 
for a consecutive five-year period.
Commission Conclusion
    313. We agree with Mirant that the Transmission Provider should not 
be allowed to terminate the LGIA if the Interconnection Customer has 
paid all costs for which it is responsible and has met all of its other 
obligations under the LGIA. The Commission is removing this provision 
from the Final Rule LGIA because it contains other provisions for 
termination, such as failure to meet milestones and other obligations. 
Furthermore, we note that an Interconnection Customer cannot begin to 
receive credits for Network Upgrades until its Generating Facility has 
achieved commercial operation, thereby providing an incentive to the 
Interconnection Customer to perform.
    314. Article 2.4--Termination Costs--Proposed LGIA Article 2.4 
would have required a Party terminating the interconnection agreement 
to pay for all costs incurred by the other Party (including costs of 
cancellation orders or contracts for Interconnection Facilities and 
equipment).
Comments
    315. Mirant argues that an Interconnection Customer should be held 
responsible only for the Network Upgrades that it has agreed to pay 
for. It and others are concerned that a higher-queued Interconnection 
Customer responsible for numerous Network Upgrades might terminate its 
LGIA and leave lower-queued Interconnection Customers to pay for the 
Network Upgrades that would otherwise have been assigned to the higher-
queued Interconnection Customer. Dominion Resources argues that if a 
higher-queued Interconnection Customer suspends or terminates 
construction of its Generating Facility, the lower-queued 
Interconnection

[[Page 49875]]

Customers must be made responsible for the costs of the Network 
Upgrades.
    316. Some Transmission Providers argue that this provision does not 
make the Interconnection Customer responsible for all costs associated 
with the termination of an interconnection agreement. For example, 
Southern says that proposed LGIA Article 2.4.1 covers only that portion 
of the Transmission Provider's Interconnection Facilities not yet 
constructed or installed, and should be modified to include all Network 
Upgrades for which the Transmission Provider has incurred expenses. BPA 
argues that proposed LGIA Article 2.4.1 should be clear about which 
Party is responsible for the termination costs and allocate costs 
accordingly. Central Maine believes that the Transmission Provider and 
its other customers should not incur any costs associated with the 
termination of the LGIA, regardless of who is responsible for the 
termination. The Midwest ISO also states that the termination provision 
must ensure that the Transmission Provider is made whole for the costs 
it incurs.
Commission Conclusion
    317. As for the obligations of the lower-queued Interconnection 
Customer with respect to the Network Upgrades that would have been paid 
for by the terminating Interconnection Customer, this issue is 
addressed in our discussion of Article 5.13 (Suspension).
    318. We clarify that if an Interconnection Customer terminates the 
LGIA, it will be held responsible for all costs associated with that 
Interconnection Customer's interconnection, including any cancellation 
costs relating to orders or contracts for Interconnection Facilities 
and equipment, and any Network Upgrades for which the Transmission 
Provider has incurred expenses and has not been reimbursed by the 
Interconnection Customer. This clarification should resolve the Midwest 
ISO's and Mirant's concerns while ensuring that the Transmission 
Provider is made whole for the costs it incurs.
    319. Article 2.5--Disconnection--Proposed LGIA Article 2.5 would 
have provided that the cost of disconnecting the Generating Facility 
from the Transmission Provider's Transmission System be borne by the 
terminating Party unless the disconnection is the result of Default by 
the other Party.
Comments
    320. A number of commenters express concern that this article 
suggests that the Transmission Provider may somehow be responsible for 
certain disconnection costs. For example, PacifiCorp emphasizes that 
the Transmission Provider must be able to disconnect (and not 
reconnect) a Generating Facility if the Interconnection Customer 
materially Breaches its obligations to maintain electrical standards or 
operational requirements, or in the event of Default by the 
Interconnection Customer. In such a situation, PacifiCorp argues, the 
Transmission Provider should not be required to bear the costs of 
disconnecting the Generating Facility. Southern and Dairyland Power ask 
that this article be revised to make the Interconnection Customer 
responsible for all costs of disconnection under all circumstances.
Commission Conclusion
    321. We agree with PacifiCorp that the Transmission Provider must 
be able to disconnect the Generating Facility from the Transmission 
System to protect its system if the Interconnection Customer fails to 
maintain electrical standards and operational requirements. 
Accordingly, the Final Rule clarifies that all disconnection costs are 
borne by the terminating Party, unless the termination results from the 
non-terminating Party's Default of the LGIA.
    322. Article 2.7--Reservation of Rights--Proposed Article 2.7 would 
have reserved to each Party their rights to unilaterally seek 
modification to the executed LGIA pursuant to Sections 205 and 206 of 
the FPA, except as restricted by the other provisions of the executed 
LGIA.
Comments
    323. Dynegy and Mirant note that this clause is redundant because 
another Reservation of Rights provision appears in proposed Article 
30.11.
Commission Conclusion
    324. We agree that this Article 2.7 is redundant, and we delete it 
from the Final Rule LGIA.
    325. Article 3--Regulatory Filings--Proposed LGIA Article 3 would 
have provided that the Transmission Provider is responsible for filing 
the LGIA with the appropriate state and federal regulatory authorities 
(collectively ``Governmental Authorities'') having jurisdiction over 
the Parties. Article 3 also describes how Confidential Information 
should be treated. It also prohibits an Interconnection Customer from 
protesting the filing of an LGIA or an amendment to an LGIA that the 
Interconnection Customer has executed.
Comments
    326. MidAmerican recommends that Article 3 be modified to make both 
Parties responsible for maintaining the confidentiality of information 
provided by the other Party. The DG Alliance states that an 
Interconnection Customer has the right to file unilaterally an 
unexecuted LGIA if the Transmission Provider declines to negotiate in 
good faith.
Commission Conclusion
    327. MidAmerican's concerns are addressed in Article 22 of the 
Final Rule LGIA, which deals with the rights and responsibilities of 
each Party with respect to treatment of Confidential Information. The 
DG Alliance's comments are addressed in Section 10.3 of the Final Rule 
LGIP, which contains the procedure for filing an unexecuted agreement.
    328. Regarding the prohibition against the Interconnection Customer 
protesting an executed and filed LGIA or amendment, the Commission 
concludes that this is contrary to the reservation of rights provision 
of the LGIA, which allows the parties to retain their respective rights 
to unilaterally amend their executed LGIA under Sections 205 and 206 of 
the FPA. Because this prohibition effectively negates the 
Interconnection Customer's Section 206 rights under the LGIA, this 
clause favors the Transmission Provider at the expense of the 
Interconnection Customer with respect to rights that, if present, 
should be mutual. Accordingly, we delete this prohibition from the 
Final Rule LGIA.
    329. Article 4--Scope of Service--Proposed LGIA Article 4 
identified two types of Interconnection Service from which the 
Interconnection Customer must choose: Energy Resource Interconnection 
Service, which is a basic or minimal service, and Network Resource 
Interconnection Service, which is a more flexible and comprehensive 
service. Because this topic generated so much controversy, and because 
the two services are addressed both in the NOPR LGIA and NOPR LGIP, 
discussion of proposed LGIA Articles 4.1 through 4.1.2.2 is included in 
part II.C.2 (Interconnection Products and Scope of Service).
    330. Article 4.3.1--Generator Balancing Service Arrangements--
Proposed LGIA Article 4.3.1 described certain requirements that the 
Interconnection Customer would have to satisfy before submitting a 
schedule for delivery service. In particular, the Interconnection 
Customer would have to ensure that the Generating Facility's actual 
output matches its scheduled delivery, on an integrated clock hour 
basis, including ramping into and out of its schedule. The 
Interconnection

[[Page 49876]]

Customer would have to arrange for the supply of energy when there is a 
difference between actual and scheduled output.
Comments
    331. Some commenters, such as NERC, PacifiCorp and American Wind 
Energy, argue that the provision of energy imbalance service is not 
related to interconnection and should not be addressed in this 
rulemaking.
    332. Cinergy and others object to the use of a clock hour basis to 
match Generating Facility output to delivery, indicating that a 10-
minute interval basis may be more appropriate so that energy injections 
will be more consistent across the scheduled hour. NERC likewise has 
concerns about adopting an integrated clock hour specification, and 
notes that the Generating Facility's scheduling period may be something 
other than a clock hour, as specified in the Transmission Provider's 
Commission-approved Tariff or market structure. NERC recommends 
revising this provision to ensure consistency with the Tariff and 
market structure.
    333. Cinergy argues that any balancing arrangement to be 
implemented by the Interconnection Customer should be determined to be 
technically feasible by the Transmission Provider and recommends that 
ramp time be excluded in the balancing arrangement because it may 
conflict with NERC scheduling requirements. Arkansas Coops notes that 
use of the clock hour may be inconsistent with operating procedures 
developed in RTOs.
Commission Conclusion
    334. The Commission concludes that a provision for balancing 
service arrangements must be included in the Final Rule LGIA because it 
describes one of the important requirements that the Interconnection 
Customer must meet before it takes delivery service. Therefore, the 
Commission retains Article 4.3 in the Final Rule LGIA.
    335. However, the Commission agrees with commenters that Article 
4.3 of the NOPR LGIA is overly prescriptive. Accordingly, in the Final 
Rule, the Commission adopts NERC's proposal to revise NOPR LGIA Article 
4.3.1 to omit the reference to an integrated clock hour basis, and to 
add the phrase, ``consistent with the scheduling requirements of the 
Transmission Provider's Commission-approved Tariff and any applicable 
Commission-approved market structure.''
    336. Article 5--Interconnection Facilities Engineering, 
Procurement, and Construction--Proposed LGIA Article 5 described 
procedures for designing, procuring, and constructing the Transmission 
Provider's Interconnection Facilities and Network Upgrades and the 
Interconnection Customer's Interconnection Facilities. Construction 
options, rights, and responsibilities were also presented. This article 
would have provided that the Interconnection Customer will not be 
directly assigned the costs of modifications made to the Transmission 
Provider's Interconnection Facilities or the Transmission System to 
facilitate interconnection of a Generating Facility of another 
Interconnection Customer or to provide transmission service under the 
Transmission Provider's Tariff.
    337. Article 5.1--Options--Proposed LGIA Article 5.1 specified the 
method for determining which Party is responsible for the construction 
of the Transmission Provider's Interconnection Facilities and Network 
Upgrades. The Interconnection Customer would specify various 
construction completion dates (such as the In-Service Date, the Initial 
Synchronization Date, and the Commercial Operation Date), and the 
Transmission Provider would then choose among three options: (1) Option 
A would have provided that the Transmission Provider construct the 
Transmission Provider's Interconnection Facilities and Network Upgrades 
using Reasonable Efforts to complete construction by the dates 
designated by the Interconnection Customer, but would not be 
responsible for any liquidated damages in case it fails to meet the 
construction completion dates established by the Interconnection 
Customer; (2) Option B(i)a would have provided that the Transmission 
Provider construct the Transmission Provider's Interconnection 
Facilities and Network Upgrades according to the construction 
completion dates established by the Interconnection Customer, and if it 
fails to meet those dates, it may be liable for liquidated damages; 
however, the Transmission Provider can opt out of this provision by 
notifying the Interconnection Customer of its intention to do so within 
30 Calendar Days; and (3) Option B(i)b would have provided that, if the 
Transmission Provider notifies the Interconnection Customer that it 
cannot meet the dates established by the Interconnection Customer, the 
Interconnection Customer could assume responsibility for the 
construction of the Transmission Provider's Interconnection Facilities 
and Stand Alone Network Upgrades.\69\ This option would also provide 
that if the Interconnection Customer does not want to assume 
responsibility for construction, the Parties would negotiate in good 
faith to revise the construction completion dates and other provisions. 
Any agreement reached by the Parties during this negotiation shall be 
binding. However, if the Parties are unable to reach an agreement, the 
Transmission Provider would assume responsibility for construction of 
its Interconnection Facilities and Network Upgrades in accordance with 
Option A. Proposed LGIA Article 5.1 would establish standards for the 
Interconnection Customer to follow if it assumes responsibility for 
constructing the Transmission Provider's Interconnection Facilities and 
system upgrades that are not Stand Alone Network Upgrades. It does not 
grant any right to the Interconnection Customer to construct upgrades 
that are not Stand-Alone Network Upgrades.
---------------------------------------------------------------------------

    \69\ Stand-Alone Network Upgrades are those Network Upgrades 
that the Interconnection Customer may construct without affecting 
day-to-day operations of the Transmission System during their 
construction.
---------------------------------------------------------------------------

Comments
    338. Cinergy states that the distinction between Options A and 
B(i)a is not clear. Monongahela Power recommends that the Commission 
rename Option B(i)a as Option B and Option B(i)b as Option C.\70\
---------------------------------------------------------------------------

    \70\ A typographical error in the NOPR added to the lack of 
clarity.
---------------------------------------------------------------------------

    339. Cinergy and NSTAR seek clarification as to whether the 
Commission intended that the Interconnection Customer take the 
responsibility for the construction of upgrades that are not Stand-
Alone Network Upgrades.
    340. Several commenters, including Cinergy, NYTO, and SoCal PPA, 
argue that the Interconnection Customer may choose unrealistic 
construction completion dates and expose the Transmission Provider to 
liquidated damages. Cinergy states that if several Interconnection 
Customers choose their construction completion dates close to each 
other, the Transmission Provider may not be able to meet the dates due 
to limited construction staff. PacifiCorp recommends that any 
construction completion date should be treated as an estimate and that 
any delays on the part of the Interconnection Customer completing its 
Generating Facility should automatically extend the time for the 
Transmission Provider to complete its Interconnection Facilities and 
Network Upgrades.

[[Page 49877]]

    341. A number of Transmission Providers oppose giving the 
Interconnection Customer the option to build or have a contractor build 
the Transmission Provider's Interconnection Facilities and Stand Alone 
Network Upgrades. TXU argues that this could threaten the reliability 
of the Transmission System. SoCal Edison argues that the Transmission 
Provider must retain adequate control of the engineering and 
construction of any Transmission Provider Interconnection Facilities 
and Stand Alone Network Upgrades because of its obligation to protect 
the safety of the public and maintain the reliability of the 
Transmission System. Cinergy and NYTO assert that if the Commission 
does not eliminate the Interconnection Customer's option to build, the 
Final Rule must provide that an Interconnection Customer exercising 
this right shall indemnify or hold harmless the Transmission Provider 
from any resulting liability.
    342. Southern states that to ensure that construction of the 
Transmission Provider's Interconnection Facilities and Stand Alone 
Network Upgrades does not impair the reliability or safety of the 
Transmission System: (1) The Transmission Provider should be allowed to 
approve the Interconnection Customer's contractors and engineers, as 
well as the vendors from which equipment and materials are purchased; 
(2) the Transmission Provider's Interconnection Facilities and Stand 
Alone Network Upgrades should be constructed, and equipment and 
materials purchased, pursuant to contracts that are reasonably 
acceptable to the Transmission Provider, including acceptable equipment 
warranty provisions; (3) the Transmission Provider should retain some 
level of supervision over the construction, with unrestricted access to 
construction sites to perform inspections; (4) the Interconnection 
Customer should provide a construction schedule to the Transmission 
Provider before construction begins; (5) the Interconnection Customer 
should be required to respond promptly to all requests for information 
from the Transmission Provider; and (6) the Transmission Provider 
should be able to require the Interconnection Customer or its 
contractors to remedy any situation that does not meet the Transmission 
Provider's specifications or standards.
    343. Similarly, the Construction Issues Coalition argues that the 
Interconnection Customers' right to build the Transmission Provider's 
Interconnection Facilities and Stand Alone Network Upgrades should be 
under specific conditions, such as: (1) The Transmission Provider must 
provide approval and oversight during design and construction; (2) the 
Transmission Provider must approve contractors in advance; (3) adequate 
time should be provided to the Transmission Provider for approval of 
engineering and construction activities; and (4) all equipment and 
construction must carry warranties to avoid risk exposure to the 
Transmission Provider. SoCal Edison argues that costs associated with 
the Transmission Provider's oversight of the construction should be 
borne by the Interconnection Customer.
    344. NERC argues that if the Interconnection Customer assumes 
responsibility for construction, it should comply with Good Utility 
Practice and the Transmission Provider's safety and reliability 
criteria.
    345. NYTO claims that several essential elements of the ERCOT model 
are absent from the Commission's proposal. It argues, for example, that 
the Commission should adopt ERCOT's 15 month minimum time period for 
completing construction after siting permits and land rights have been 
obtained.
    346. American Transmission argues that the Transmission Provider 
must have the right to step in and assume construction responsibilities 
to protect the integrity of the system and rights of the third parties 
in case of serious lapses by an Interconnection Customer.
    347. Southern argues that the Final Rule LGIA should require the 
Interconnection Customer to transfer the Transmission Provider's 
Interconnection Facilities and Stand Alone Network Upgrades to the 
Transmission Provider for ownership and operation after it completes 
construction.
    348. PJMTO asserts that Final Rule LGIA Article 5.1 should contain 
more explicit provisions addressing the Transmission Owner's role in: 
(1) Obtaining permits and authorizations, (2) obtaining land rights, 
(3) performing direct line attachment tie-in work, and (4) calibrating 
remote terminal unit settings.
    349. American Transmission states that proposed LGIP Section 8 
(Interconnection Facilities Study) requires the Transmission Provider 
to develop detailed cost estimates for constructing the Transmission 
Provider's Interconnection Facilities and Network Upgrades under the 
assumption that the Transmission Provider will perform all of the 
construction, yet the Interconnection Customer may assume the 
responsibility for part of the construction. It asks the Commission to 
clarify whether there is any relationship between the Transmission 
Provider's cost estimates and the actual cost of construction performed 
by the Interconnection Customer. It wants to require approval by the 
Transmission Provider of the Interconnection Customer's budget for the 
construction of the Transmission Provider's Interconnection Facilities 
and Stand Alone Network Upgrades.
    350. Dynegy asserts that the last sentence of Article 5.1.A(iv), 
which provides that the Interconnection Customer's selection of 
subcontractors is subject to the Transmission Provider's standards and 
specifications, is overly broad and conflicts with proposed LGIA 
Article 26.1 (Subcontractors--General), which states that ``nothing in 
this Agreement shall prevent a Party from utilizing the services of any 
subcontractor as it deems appropriate to perform its obligations under 
this Agreement.''
Commission Conclusion
    351. The Commission is revising Proposed LGIA Article 5.1 to 
distinguish the various options more clearly. NOPR Option A is now 
renamed Standard Option. Under the Standard Option, the Transmission 
Provider shall construct the Transmission Provider's Interconnection 
Facilities and Network Upgrades using Reasonable Efforts to complete 
the construction by the dates designated by the Interconnection 
Customer, but shall not be responsible for any liquidated damages if it 
fails to complete the construction by the designated dates. The 
Standard Option also serves as the default in the event the Parties are 
unable to reach an agreement under the Negotiated Option
    352. Option B(i)a is renamed Alternate Option. Under the Alternate 
Option, the Transmission Provider shall construct the Transmission 
Provider's Interconnection Facilities and Network Upgrades according to 
the construction completion dates established by the Interconnection 
Customer, and if it fails to meet those dates, it may be liable for 
liquidated damages; however, the Transmission Provider can decline to 
use this option by notifying the Interconnection Customer of its 
intention to do so within 30 Calendar Days of executing the LGIA.
    353. The last option--Option B(i)b in the NOPR--gives the 
Interconnection Customer two choices in the Final Rule LGIA: the Option 
to Build and the Negotiated Option. This is because the proposed Option 
B(i)b actually presented two options. Under the Option to Build, the 
Interconnection

[[Page 49878]]

Customer may assume responsibility for the construction of the 
Transmission Provider's Interconnection Facilities and Stand Alone 
Network Upgrades if the Transmission Provider notifies the 
Interconnection Customer that it cannot meet the dates established by 
Interconnection Customer. However, as clarified in Final Rule LGIA 
Article 5.1.3, it does not grant any right to the Interconnection 
Customer to construct upgrades that are not Stand-Alone Network 
Upgrades. Furthermore, both the Transmission Provider and the 
Interconnection Customer must agree on which facilities are the Stand 
Alone Network Upgrades and identify them in Appendix A to the LGIA.
    354. The Negotiated Option provides that, if the Transmission 
Provider notifies the Interconnection Customer that it cannot meet the 
dates established by Interconnection Customer, and the Interconnection 
Customer does not want to assume responsibility for construction, the 
Interconnection Customer may decide that the Parties shall negotiate in 
good faith to revise the construction completion dates and other 
provisions under which the Transmission Provider is responsible for the 
construction. If the Parties are unable to reach an agreement, the 
Transmission Provider shall assume responsibility for construction of 
the Transmission Provider's Interconnection Facilities and Network 
Upgrades in accordance with the Standard Option.
    355. Regarding Cinergy, NYTO, and SoCal PPA's concerns about the 
selection of unrealistic construction completion dates by an 
Interconnection Customer, the Final Rule Alternate Option allows the 
Transmission Provider to avoid unrealistic construction completion 
dates by notifying the Interconnection Customer that it is unable to 
meet the established dates. We agree with PacifiCorp that any delay on 
the part of the Interconnection Customer in meeting its construction 
completion dates should grant an automatic extension to the 
Transmission Provider. We note that Final Rule LGIA Article 5.3 
(Liquidated Damages) provides that no liquidated damages shall be paid 
to the Interconnection Customer if the Interconnection Customer is not 
ready to commence use of the Transmission Provider's Interconnection 
Facilities and Network Upgrades on the specified construction dates 
except if such delay is due to the Transmission Provider's delay.\71\
    356. With regard to the concern that giving the Interconnection 
Customer the right to construct the Transmission Provider's 
Interconnection Facilities and Stand Alone Network Upgrades could 
threaten the safety and reliability of the Transmission System, Final 
Rule LGIA Article 5.2 (General Conditions Applicable to Options to 
Build) has several safeguards. For example, the Interconnection 
Customer is required to use Good Utility Practice and the standards and 
specifications provided in advance by the Transmission Provider. In 
addition, the Transmission Provider has the right to approve the 
engineering design, the equipment acceptance tests, and the 
construction of the Transmission Provider's Interconnection Facilities 
and Stand Alone Network Upgrades.
---------------------------------------------------------------------------

    \71\ Other comments on this issue are addressed in part II.C.8.b 
(Liquidated Damages).
---------------------------------------------------------------------------

    357. In response to those comments seeking an indemnification or 
hold harmless provision to protect the Transmission Provider from 
liability arising out of the Interconnection Customer's exercising its 
right to build, the Commission adds an indemnification clause to Final 
Rule LGIA Article 5.2 (General Conditions Applicable to Options to 
Build).
    358. With respect to various modifications that Southern and the 
Construction Issues Coalition seek, Final Rule LGIA Article 5.2 
(General Conditions Applicable to Options to Build) adds several 
provisions proposed by these commenters, such as a requirement that the 
Interconnection Customer (1) provide a construction schedule in advance 
of the start of construction, (2) remedy deficiencies brought to its 
attention by the Transmission Provider, and (3) carry warranties for 
equipment similar to those carried by the Transmission Provider. 
However, the Commission declines to grant fully the high level of 
Transmission Provider control that Southern and the Construction Issues 
Coalition seek, such as approval of subcontractors and vendors. Such 
control would be overly broad, and the Transmission Provider's ability 
to seek remedy of any deficiencies should enable it to carry out its 
responsibilities. The Commission also will deny SoCal Edison's request 
that the Interconnection Customer bear the Transmission Provider's 
costs associated with the oversight of construction performed by the 
Interconnection Customer because such costs are de minimus.
    359. With respect to NERC's comment that an Interconnection 
Customer should follow Good Utility Practice and the safety and 
reliability criteria of the Transmission Provider, such standards are 
in Final Rule LGIA Article 5.2 (General Conditions Applicable to Option 
to Build).
    360. Regarding NYTO's argument that a minimum of 15 months is 
needed to complete construction of the Transmission Provider 
Interconnection Facilities and Network Upgrades, we conclude that 
specifying such a minimum period is unnecessary because under the 
Alternate Option, the Transmission Provider will be protected from 
incurring liquidated damages liability due to delays beyond its 
reasonable control or reasonable ability to cure.
    361. The Commission rejects American Transmission's proposal that 
the Transmission Provider have a right to step in and assume 
construction responsibilities in case of lapses by an Interconnection 
Customer. Since Article 5.1 permits the construction of only 
Transmission Provider Interconnection Facilities and Stand Alone 
Network Upgrades, the Commission believes that any such lapses would 
affect only the Interconnection Customer. If it has the potential to 
affect anyone other than the Interconnection Customer, the Commission 
will address such concerns when brought to its attention.
    362. The Final Rule does not require that the Interconnection 
Customer transfer ownership of the Transmission Provider's 
Interconnection Facilities and Stand Alone Network Upgrades to the 
Transmission Provider after the Interconnection Customer completes 
them; however, the Commission will require transfer of control of such 
facilities. Reliability does not require ownership, but it does require 
control by the Transmission Provider.\72\
---------------------------------------------------------------------------

    \72\ See Arizona Public Service Company, 102 FERC ] 61,303 
(2003). We also note that the ownership of Stand Alone Network 
Upgrades by an Interconnection Customer is discussed further under 
``Rules Governing the Payment of Credits'' in part C.1 of this 
Preamble.
---------------------------------------------------------------------------

    363. With respect to PJMTO's request for provisions regarding the 
Transmission Owner's role in obtaining permits and land rights, Final 
Rule LGIA Articles 5.12 (Access Rights) and 5.13 (Lands of Other 
Property Owners) do not distinguish between the role of the 
Transmission Provider and the Transmission Owner in assisting the 
Interconnection Customer in obtaining land rights and permits. The 
Final Rule LGIA is not the appropriate place to set forth the nature of 
the relationship between the Transmission Owner and Transmission 
Provider. In addition, the Commission is stating in this Final Rule 
that it will give an independent transmission provider such as an RTO

[[Page 49879]]

or ISO the flexibility to propose different rules in its compliance 
filing.
    364. The Commission denies American Transmission's request to 
include a provision in the Final Rule LGIA for the Transmission 
Provider to review and approve the Interconnection Customer's budget if 
an Interconnection Customer assumes the responsibility to construct the 
Transmission Provider's Interconnection Facilities and Stand Alone 
Network Upgrades. The Interconnection Customer is likely to act in its 
best interests to keep the costs down because it initially funds the 
construction costs. In addition, allowing a Transmission Provider 
unfettered discretion to review the budget would encourage 
anticompetitive behavior.
    365. With regard to Dynegy's concern regarding subcontractors, 
Article 26.1 provides that nothing in the LGIA prevents a Party from 
using the services of any subcontractor to perform its obligations 
under the LGIA and that it is up to the Party to ensure that the 
subcontractor complies with the LGIA. In addition, the hiring Party 
remains primarily liable to the other Party for the performance of the 
subcontractor. Thus, if the subcontractor fails to meet the 
Interconnection Customer's obligations under the LGIA or to the 
Transmission Provider, the Interconnection Customer is obligated to 
remedy any deficiencies. Accordingly, the Commission is removing the 
words ``including selection of subcontractors'' from Article 5.1 to 
ensure consistency between that article and Article 26.1.
    366. Article 5.2--Power System Stabilizers (In the Final Rule LGIA: 
Article 5.4)--Proposed LGIA Article 5.2 would have required the 
Interconnection Customer to install, operate and maintain power system 
stabilizers, if required by the Interconnection System Impact Study. 
The Transmission Provider would establish minimal acceptable settings 
subject to the design and operating limitations of the Generating 
Facility.
Comments
    367. Several commenters, including Cal ISO, Dairyland Power, 
Dominion Resources, and NSTAR, argue that the Transmission Provider's 
ability to require the installation of a power system stabilizer should 
not be limited to when required by the Interconnection System Impact 
Study because the Generating Facility may become a source of power 
system oscillations on the Transmission System many years after 
operations commence. Dominion Resources contends that a Transmission 
Provider should be able to require an Interconnection Customer to 
install a power system stabilizer any time it determines through its 
operating experience that a power system stabilizer is needed.
    368. Cal ISO argues that the requirement to install a power system 
stabilizer should not be based on the ``Interconnection System Impact 
Study,'' but should be based on the ``guidelines and procedures of the 
Applicable Reliability Council.'' NERC points out that the Transmission 
System reliability criteria and use of power system stabilizers vary 
from one region to another, depending on the electrical characteristics 
of the system. NERC states that, as a result, it is important that the 
system operator be notified if a power system stabilizer is inoperable 
or removed from service.
Commission Conclusion
    369. The Commission agrees with Cal ISO that an Interconnection 
Customer should be required to install a power system stabilizer in 
accordance with the standards of the Applicable Reliability Council. 
This also addresses Dominion Resources' concern that installation of a 
power system stabilizer on a Generating Facility may be needed at a 
later time; such a requirement should be covered in the guidelines of 
the Applicable Reliability Council. If the Applicable Reliability 
Council guidelines do not cover such matters, a Transmission Provider 
may justify its reasons for wishing to require a power system 
stabilizer despite the lack of such a requirement in the Applicable 
Reliability Council guidelines when it makes its compliance filing.
    370. The Commission will adopt NERC's recommended language 
requiring notification when power system stabilizers are removed or are 
not available for automatic operation.
    371. This article is designated Article 5.4 in the Final Rule LGIA.
    372. Article 5.8.1--Generator Specifications (In the Final Rule 
LGIA: Article 5.10.1)--Proposed LGIA Article 5.8.1 would have required 
that the Interconnection Customer submit the final specifications for 
the Interconnection Customer's Interconnection Facilities, including 
System Protection Facilities, to the Transmission Provider for review 
at least 90 Calendar Days prior to the Initial Synchronization Date. It 
proposed to require the Transmission Provider to provide comments to 
the Interconnection Customer within 30 Calendar Days of the 
Interconnection Customer's submission.
Comments
    373. Cleco and NYTO assert that the Interconnection Customer should 
have to submit initial specifications for the Interconnection 
Customer's Interconnection Facilities to the Transmission Provider at 
least 180 Calendar Days prior to the Initial Synchronization Date with 
the understanding that the initial specifications are subject to 
change. Such initial specifications would give them an opportunity to 
perform the planning required for the new facilities and upgrade.
Commission Conclusion
    374. The Commission agrees with Cleco and NYTO and adopts their 
proposal in the Final Rule.
    375. This article is designated Article 5.10.1 in the Final Rule 
LGIA.
    376. Article 5.8.2--Transmission Provider's Review (In the Final 
Rule LGIA: Article 5.10.2)--Proposed LGIA Article 5.8.2 would have 
required that the Interconnection Customer to modify the 
Interconnection Customer's Interconnection Facilities as may be 
reasonably required by the Transmission Provider to ensure that they 
are compatible with the telemetry communications and safety 
requirements of the Transmission Provider.
Comments
    377. NERC requests that the word ``reasonably'' be removed from the 
article and recommends referring to Good Utility Practice.
Commission Conclusion
    378. The Final Rule revises this article to refer to Good Utility 
Practice, as requested by NERC, but it does not eliminate the term 
``reasonably.'' The Interconnection Customer's Interconnection 
Facilities are installed at the expense of the Interconnection 
Customer, but must be reviewed and meet the specifications and 
requirements established by the Transmission Provider. The term 
``reasonably'' helps to ensure that the Transmission Provider does not 
require the installation of equipment beyond what is necessary for 
compatibility and reliability, or beyond the standards the Transmission 
Provider would apply to its own Interconnection Facilities.
    379. This article is designated Article 5.10.2 in the Final Rule 
LGIA.
    380. Article 5.8.3--Interconnection Customer Interconnection 
Facilities Construction (In the Final Rule LGIA: Article 5.10.3)--
Proposed LGIA Article 5.8.3 would have required the Interconnection 
Customer to provide to

[[Page 49880]]

the Transmission Provider certain ``as built'' drawings, information, 
and documents pertaining to the construction of the Interconnection 
Customer's Interconnection Facilities.
Comments
    381. NERC proposes that the Interconnection Customer also provide 
the Transmission Provider specifications for the excitation system, 
automatic voltage regulator, generator control and protection settings, 
transformer tap settings, and communications.
Commission Conclusion
    382. The Commission adopts NERC's proposal and revises Proposed 
LGIA Article 5.8.3 to make clear that the list of information to be 
provided is not exhaustive.
    383. This article is designated Article 5.10.3 in the Final Rule 
LGIA.
    384. Article 5.11--Lands of Other Property Owners (In the Final 
Rule LGIA: Article 5.13)--Article 5.11 proposed that Transmission 
Providers would be required to use Reasonable Efforts, including use of 
its eminent domain authority if necessary, to facilitate the 
interconnection of Generating Facilities. The Interconnection Customer 
would be required to pay any expenses related to obtaining rights of 
use, rights of way, easements, or eminent domain costs that the 
Transmission Provider might incur, up to the fair market value of the 
land or ``such other price as required by the applicable inter-
affiliate transaction requirements.''
Comments
    385. EPSA and several Interconnection Customers, including Calpine, 
El Paso, and Reliant Energy, request that the Transmission Provider or 
Transmission Owner be required to use its eminent domain authority to 
facilitate the exercise of the Parties' rights and obligations under 
the LGIA to the extent it is permitted to do so. Numerous Transmission 
Provider commenters express concern that the eminent domain provisions 
of the NOPR are too broad, placing the Transmission Provider in an 
untenable situation. Specifically, several argue that the Commission's 
proposal conflicts with state limitations on their eminent domain 
authority.\73\ Cleco, for example, states that in Louisiana, a utility 
cannot legally request eminent domain on behalf of another entity. 
National Grid and the Construction Issues Coalition argue that many 
states require that eminent domain authority be used only ``to further 
a public need''--something that is lacking in the NOPR. Cinergy 
proposes deleting the entire eminent domain provision, arguing that it 
imposes an inappropriate burden on the Transmission Provider and 
reiterates that it conflicts with existing state laws. Similarly, El 
Paso requests that the use of eminent domain be at the sole discretion 
of the Transmission Provider or Transmission Owner, citing the numerous 
factors that must be considered in such an undertaking.
---------------------------------------------------------------------------

    \73\ E.g., Cinergy, Cleco, the Construction Issues Coalition, 
Duke Energy, National Grid, PJMTO, Salt River Project, SoCal Edison, 
and Southern.
---------------------------------------------------------------------------

    386. Duke Energy proposes that the Commission require a 
Transmission Provider to use eminent domain only when it reasonably 
determines that (1) other alternatives are not available and (2) use of 
eminent domain is permissible under state law. Duke Energy also asserts 
that the Transmission Provider should provide a written explanation of 
why other alternatives are appropriate or why the use of eminent domain 
would not be permitted under state law.
    387. National Grid argues that the Commission should eliminate the 
eminent domain provision, citing the long delays and heavy litigation 
that often accompany the seizure of property. National Grid, the 
Construction Issues Coalition, and others argue that regulation of 
eminent domain differs from state to state, making the type of national 
contract clause envisaged by the Commission impossible.
    388. PJMTO also opposes the eminent domain provision, arguing that 
eminent domain is an unpopular last resort and one that is rarely 
exercised even by a Transmission Provider or Transmission Owner on its 
own behalf. Instead, it proposes requiring that a Transmission Provider 
or Transmission Owner, upon receipt of a reasonable request, to assist 
an Interconnection Customer in acquiring land rights using efforts 
similar to those it typically undertakes on its own behalf.
    389. PJMTO also argues for eliminating the cap on land value, 
noting that individual state laws already contain mechanisms for 
valuing property. The Commission may lack authority to require a price 
cap on property sold by an Affiliate of a Transmission Provider, 
according to National Grid and the Construction Issues Coalition.
    390. Salt River Project also opposes the eminent domain language 
and instead proposes that the Commission work with federal land holding 
agencies to streamline the procurement of land rights. SoCal Edison 
adds that it does not believe the Commission has the authority to 
impose an eminent domain requirement. Instead, it proposes requiring 
Transmission Providers to exercise good faith efforts in using whatever 
eminent domain authority state law may allow on an Interconnection 
Customer's behalf.
Commission Conclusion
    391. We agree that a mandatory eminent domain requirement can be 
difficult for a Transmission Provider or Transmission Owner. The Final 
Rule requires that a Transmission Provider or Transmission Owner use 
efforts similar to those it typically undertakes on its own behalf (or 
on behalf of an Affiliate) to secure land rights for the 
Interconnection Customer. We are also clarifying that the Transmission 
Provider or Transmission Owner's efforts must also comply with state 
law.
    392. If the Transmission Provider is an independent entity, the 
Transmission Owner, the Transmission Provider, and the Interconnection 
Customer may all sign the LGIA. This allows a Transmission Owner and a 
Transmission Provider to jointly undertake efforts to secure land 
rights for the Interconnection Customer.
    393. Regarding the cap on land value, while the Commission remains 
concerned that Affiliates of a Transmission Provider or Transmission 
Owner might request above-market compensation for land necessary to 
facilitate the interconnection, the Commission also recognizes that the 
valuation of property is a matter of state law. Therefore, we eliminate 
this cap in the Final Rule.
    394. This article is designated Article 5.13 in the Final Rule 
LGIA.
    395. Article 5.12--Early Construction of Base Case Facilities--
Proposed LGIA Article 5.12 would have required that, at the 
Interconnection Customer's request, the Transmission Provider must 
construct, using Reasonable Efforts to accommodate the Interconnection 
Customer's In-Service Date, all or any portion of Network Upgrades 
reflected in the Base Case of the Interconnection Customer's Facilities 
Study that are necessary to accommodate the Interconnection Customer's 
In-Service Date. Construction of the Network Facilities would be 
required even if the Network Facilities are shared with other 
interconnecting generators that would not be completed in time to meet 
the Generating Facility's In-Service Date.
Comments
    396. MidAmerican contends that this article is inconsistent with 
Section 12.3

[[Page 49881]]

of the NOPR LGIP (Construction Sequencing), which requires that the 
Transmission Provider use Reasonable Efforts to accommodate the 
Generating Facility's In-Service Date. Accordingly, it proposes that 
Article 5.12 be revised.
    397. Cleco argues that the Party requesting early construction 
should pay all Network Upgrade costs associated with the early 
construction. FP&L argues that to avoid the need to continuously 
restudy and revise Network Upgrades, the LGIA should require the timely 
construction of Network Upgrades relied upon by lower-queued 
Interconnection Customers.
    398. Entergy, Dairyland Power, and others state that the Final Rule 
should address which Interconnection Customer finances Network Upgrades 
in the event of a delay by the higher-queued Interconnection Customer 
to whom the Network Upgrades are assigned. Cal ISO states that language 
regarding milestones should be inserted between proposed LGIA Articles 
5.12 and Article 5.13.
Commission Conclusion
    399. In response to the concerns of Entergy and others, the 
Commission notes that a lower-queued Interconnection Customer always 
has the right under this article to accelerate its construction 
schedule by completing all required Network Upgrades on schedule 
despite any delays by higher-queued Interconnection Customers. This 
would require the lower-queued Interconnection Customer to fund those 
Network Upgrades at least initially; however, in the absence of 
participant funding, it would be reimbursed over time through credits, 
with interest. Article 5.12 does not need to be changed to allow this.
    400. Regarding ``best'' versus ``reasonable'' efforts, the 
Commission agrees with MidAmerican that there was an inconsistency 
between proposed LGIA Article 5.12 and proposed LGIP Section 12.3, 
which requires the Transmission Provider to use Reasonable Efforts to 
accommodate the Interconnection Customer's requested In-Service Date. 
Article 5.12 is the more stringent of the two because it requires the 
Transmission Provider to construct facilities necessary to accommodate 
the Interconnection Customer's In-Service Date. The Commission's intent 
is to expedite the interconnection of new generators in a manner that 
does not undermine the reliability of a Transmission Provider's 
Transmission System. However, there may be circumstances beyond the 
Transmission Provider's control that would prevent it from meeting the 
construction deadline. To address this concern and to ensure 
consistency between this article and LGIP Section 12.3, the Commission 
agrees with MidAmerican's comment that the term ``Reasonable Efforts'' 
is appropriate. This article, which is designated Article 5.15 in the 
Final Rule LGIA, uses that term.
    401. An additional article regarding milestones is not needed. By 
the time the LGIA is executed, the Parties will have already 
established under Article 5.1 the milestones Cal ISO refers to.
    402. Article 5.13--Suspension (In the Final Rule LGIA: Article 
5.16)--Proposed LGIA Article 5.13 would allow the Interconnection 
Customer, upon written notice to the Transmission Provider, to suspend 
work on Interconnection Facilities or Network Upgrades as long as the 
Interconnection Customer agrees to be responsible for all reasonable 
and necessary costs incurred by the Transmission Provider in suspending 
work. This article proposed that the LGIA be deemed terminated if the 
Interconnection Customer has not requested the Transmission Provider to 
recommence work within three years from the date of the suspension 
request.
Comments
    403. Peabody supports allowing an Interconnection Customer to 
suspend work on the interconnection for up to three years because this 
offers the Interconnection Customer the flexibility that large-scale 
generation projects need to accommodate permitting and other delays. 
Other commenters, including BPA, Cinergy, and SoCal PPA, argue that a 
three year suspension period is unreasonably long. SoCal PPA further 
states that substantial changes to the Transmission System could occur 
during that time. Western believes that letting an Interconnection 
Customer contract with a Transmission Provider for an interconnection 
and then suspend operation for as long as three years could allow the 
Interconnection Customer to game the system. Consequently, Western and 
other commenters argue that the suspension period should be limited to 
six months, while Cinergy recommends limiting the suspension period to 
one year. NYTO believes the entire provision is unreasonable.
    404. Cinergy requests that Article 5.13 make it clear that if an 
Interconnection Customer gives a Transmission Provider written notice 
of suspension of work, the Transmission Provider does not have to 
obtain written permission from the Interconnection Customer to cancel 
or suspend material, equipment and labor contracts associated with that 
work, and that the Commission clarify what is included in the 
definition of ``suspension of work.'' Further, to prevent gaming the 
process, Cinergy proposes that an Interconnection Customer be allowed 
to provide written notice of suspension of work only once per 
Generating Facility.
    405. Dominion Resources questions whether the responsibility for 
funding the cost of Network Upgrades would fall on the Interconnection 
Customer suspending or terminating construction or on other 
Interconnection Customers remaining in the queue. The Interconnection 
Customer actually using the Network Upgrades should be required to pay 
for them. Dominion Resources recognizes that this may shift costs from 
the Interconnection Customer requesting the suspension to 
Interconnection Customers further down the queue, which could mean that 
an Interconnection Customer will be subject to potential cost increases 
even after signing an LGIA. However, it views this as a more acceptable 
allocation of cost responsibility than requiring an Interconnection 
Customer that desires to suspend or terminate its project to bear the 
full cost of Network Upgrades it may never use. In order to avoid 
gaming of the interconnection queue, if the suspending Interconnection 
Customer later continues with its project, it should be required to 
reimburse any lower-queued Interconnection Customers for any Network 
Upgrade costs related to its suspension.
    406. NERC and MidAmerican comment that there must be a requirement 
to leave the system in a safe and reliable condition, consistent with 
Good Utility Practice, if a project is suspended in a partially 
complete state.
    407. The Midwest ISO requests that Article 5.13 make it clear that 
a suspending Interconnection Customer must provide notice to the 
Transmission Owner and to any independent Transmission Provider.
    408. The Midwest ISO and Georgia Transmission request clarification 
that the Transmission Provider will be reimbursed for any expenses 
related to the suspension.
Commission Conclusion
    409. Many commenters express concern over the effect that a 
suspending Interconnection Customer might have on lower-queued 
Interconnection Customers. We agree with Dominion Resources that, in 
some cases, a subsequent (i.e., lower queued) Interconnection Customer 
may be responsible for funding the costs of completing the Network 
Upgrades constructed for a higher-queued

[[Page 49882]]

Interconnection Customer that suspends or terminates construction of 
such Network Upgrades. However, the Commission is not obligating in 
this Final Rule a subsequent (i.e., lower queued) Interconnection 
Customer to pay for these costs regardless of whether that 
Interconnection Customer benefits from the facilities, since this would 
subject that Interconnection Customer to significant financial risk. 
Prices quoted for interconnection in the LGIA are estimates based on 
the results of studies conducted during the LGIP phase of the 
interconnection process. If it is apparent to the Parties at the time 
they execute the LGIA that contingencies (such as other Interconnection 
Customers terminating their LGIAs) might affect the financial 
arrangements, the Parties should include such contingencies in their 
LGIA and address the effect of such contingencies on their financial 
obligations. If no such contingencies are accounted for in the executed 
LGIA, since the costs of Network Upgrades may influence an 
Interconnection Customer's decision whether it can enter into an 
Interconnection Agreement, we leave it to the subsequent 
Interconnection Customer and the Transmission Provider to revisit the 
negotiated terms of their executed Interconnection Agreement. We deny 
the requests to revise or delete Proposed LGIA Article 5.13 on these 
grounds.\74\
---------------------------------------------------------------------------

    \74\ An RTO or ISO with participant funding may propose an 
alternative policy for Commission approval.
---------------------------------------------------------------------------

    410. We also retain the three year period. The Commission agrees 
with Peabody that allowing the Interconnection Customer to have the 
Transmission Provider suspend work for up to three years allows 
generation projects the flexibility necessary to accommodate permitting 
and other delays that are particularly likely to affect large projects.
    411. The Final Rule requires the Interconnection Customer to pay 
all reasonable costs that the Transmission Provider incurs in 
suspending work on its Interconnection Facilities, as well as costs 
that are reasonable and necessary to ensure the safety and integrity of 
the Transmission Provider's Transmission System during the suspension.
    412. We reject Cinergy's proposal that an Interconnection Customer 
be limited to one suspension period per Generating Facility. The LGIA 
is designed to be a standard agreement that will operate in any number 
of situations, and to limit arbitrarily each Generating Facility to 
only one suspension period, regardless of circumstances, is 
unreasonable.
    413. We adopt NERC's proposal that Article 5.13 require a 
suspending Interconnection Customer to leave the system in a safe and 
reliable condition in accordance with Good Utility Practice and the 
Transmission Provider's safety and reliability criteria.
    414. In response to Cinergy's request for clarification of the term 
``suspension of work,'' the Commission clarifies that a Transmission 
Provider, upon receiving written notice of suspension from the 
Interconnection Customer, is authorized to cancel or suspend material, 
equipment and labor contracts associated with that work. If reliability 
could be compromised by stopping construction, the Transmission 
Provider must continue construction until it reaches a stage where it 
can safely discontinue work. Any costs associated with suspension (or 
of completing a discrete Network Upgrade) shall be deducted from the 
Interconnection Customer's security deposit.
    415. With respect to the Midwest ISO's request to require an 
Interconnection Customer to notify both the Transmission Owner and the 
Transmission Provider, we clarify that if both Parties are signatories 
to the LGIA, the Interconnection Customer is required to notify both 
the Transmission Owner and the Transmission Provider.
    416. This article is designated Article 5.16 in the Final Rule 
LGIA.
    417. Article 5.14--Taxes--Proposed LGIA Article 5.14 addressed the 
allocation of responsibilities that would apply with respect to the tax 
treatment of an Interconnection Customer's payments or property 
transfers to the Transmission Provider for the installation of the 
Transmission Provider's Interconnection Facilities and Network 
Upgrades.
    418. Internal Revenue Service policy, as expressed in IRS Notice 
2001-82 and IRS Notice 88-129, delineates the standards under which an 
Interconnection Customer's payments to build interconnections 
facilities will not create a current tax liability for a Transmission 
Provider. The ``safe harbor'' provisions described in these notices 
generally prevent the transaction from being considered a taxable 
transfer. If the IRS changes its policy, or if the transaction no 
longer qualifies for safe harbor protection and tax liability results, 
under the provisions in Article 5.14 the Interconnection Customer would 
indemnify the Transmission Provider for any tax liability that may 
arise from the payments to build the Transmission Provider's 
Interconnection Facilities and Network Upgrades.
Comments
    419. Several entities argue that the IRS safe harbor does not 
eliminate all risk of these payments being treated as taxable income to 
the Transmission Provider because the IRS may revisit its policies in a 
manner that establishes tax liability for interconnections, including 
the credits provided against transmission service in exchange for the 
reimbursement of Network Upgrades.\75\ These commenters argue that 
Article 5.14 should account for these risks.
---------------------------------------------------------------------------

    \75\ E.g., EEI, FP&L, MidAmerican, and TXU.
---------------------------------------------------------------------------

    420. Some commenters, including Duke, EPSA, NYTO, and PG&E, argue 
that the Commission should adopt Article 5.16.5 of the Consensus LGIA, 
which ensures that a Transmission Owner is made whole when a 
contribution from an Interconnection Customer is non-taxable when made, 
but the IRS later imposes tax liability. NYTO further suggests that the 
two revisions to Consensus LGIA Article 5.16.5 that were proposed by 
the Transmission Owners should be retained. These provisions would 
ensure that the Transmission Owner would be reimbursed for taxes 
imposed more than ten years after the date the Interconnections 
Facilities are placed in service and allow for security for such 
potential tax liability.
Commission Conclusion
    421. The Commission finds that Article 5.14 as proposed 
appropriately addresses the risk that the contracting Parties face 
because of the uncertainties regarding IRS policy, because it requires 
the Interconnection Customer to indemnify the Transmission Provider in 
the event that the IRS changes or clarifies its policy.
    422. The Commission concludes that a discussion of subsequent 
taxable events is appropriate for the Final Rule LGIA.\76\ The two 
additions NYTO requests are unnecessary because Final Rule LGIA Article 
5.17.3 addresses limitation of indemnification and the ability of the 
Transmission Provider to require security from the Interconnection 
Customer.
---------------------------------------------------------------------------

    \76\ Subsequent taxable events are discussed in Final Rule LGIA 
Article 5.17.6. This discussion retains the article numbers that 
appeared in the NOPR LGIA.
---------------------------------------------------------------------------

    423. Article 5.14.1--Interconnection Customer Payments Not Taxable 
(In the Final Rule LGIA: Article 5.17.1)--Proposed LGIA Article 5.14.1 
would have provided that, consistent with IRS Notice 2001-82 and IRS 
Notice 88-129 (discussing the IRS safe harbor provisions), all payments 
made by the Interconnection Customer to the

[[Page 49883]]

Transmission Provider for the installation of Transmission Provider's 
Interconnection Facilities and Network Upgrades are non-taxable, either 
as contributions to capital, or as advances.
Comments
    424. Peabody endorses this proposed provision. It argues that it is 
in the best interest of Interconnection Customers, Transmission 
Providers and customers to take advantage of the tax exemption for 
payments that Interconnection Customers make to Transmission Providers 
for Network Upgrades made pursuant to an LGIA.
    425. Progress Energy argues that an Interconnection Customer's 
right to terminate the LGIA on 30 Calendar Days' written notice may 
jeopardize the safe harbor treatment of Interconnection Customer 
contributions because the IRS safe harbor provisions apply only to 
interconnection agreements with a minimum term of ten years.
Commission Conclusion
    426. In response to Progress Energy, the mere existence of the 30 
day termination provision does not mean that the Interconnection 
Agreement conflicts with the IRS minimum term requirement of ten years. 
Nevertheless, if either Party in fact terminates the LGIA before ten 
years have passed, the IRS may then conclude that the Interconnection 
Customer's payments are indeed taxable. Accordingly, the Parties should 
consider these possible tax consequences when deciding whether to 
terminate an LGIA within ten years.
    427. This article is designated Article 5.17.1 in the Final Rule 
LGIA.
    428. Article 5.14.2--Representations and Covenants (In the Final 
Rule LGIA: Article 5.17.2)--Proposed LGIA Article 5.14.2 set forth the 
representations and covenants that would be agreed to by the Parties to 
conform to the requirements of the IRS safe harbor provisions set forth 
in the relevant IRS Notices.
Comments
    429. FirstEnergy argues that in order for the Interconnection 
Customer's payments to the Transmission Provider to be deemed non-
taxable under the IRS safe harbor provisions, ownership of the 
electricity generated at the Generating Facility must pass to another 
entity prior to the transmission of the electricity on the Transmission 
System. FirstEnergy asks the Commission to clarify the representations 
and proposed covenants in proposed LGIA Article 5.14.2 to refer to the 
Point of Interconnection or Point of Change of Ownership.
Commission Conclusion
    430. We do not intend to interpret the IRS safe harbor provisions, 
and so we leave it to the Parties to ensure that their conduct, 
including the point at which the ownership of electric energy produced 
by the Generating Facility changes hands, conform to IRS policy.
    431. This article is designated Article 5.17.2 in the Final Rule 
LGIA.
    432. Article 5.14.3--Indemnification for Taxes Imposed Upon 
Transmission Provider--Proposed LGIA Article 5.14.3 would have required 
that the Interconnection Customer indemnify (hold harmless) the 
Transmission Provider from income taxes imposed against the 
Transmission Provider as a result of payments or property transfers 
made by Interconnection Customer to the Transmission Provider under the 
LGIA--that is, if the IRS safe harbor provisions do not keep the 
Transmission Provider from having to pay income taxes. The Transmission 
Provider would not include a gross-up \77\ for income taxes unless 
either it has made a good faith determination that the payment or 
transfers should be recorded as income subject to taxation, or any 
Governmental Authority directs Transmission Provider to treat the 
payment or transfers as subject to taxation. As an alternative to the 
gross-up, the Transmission Provider would be able to require the 
Interconnection Customer to provide security in a form reasonably 
acceptable to the Transmission Provider and in an amount equal to the 
Interconnection Customer's estimated tax liability.
---------------------------------------------------------------------------

    \77\ A gross-up for income taxes is a dollar amount calculated 
to determine the Interconnection Customer's estimated tax liability 
to the Transmission Owner.
---------------------------------------------------------------------------

Comments
    433. MidAmerican supports Article 5.14.3 and recommends that the 
Transmission Owner be added to this provision by changing Transmission 
Provider to Transmission Provider or Transmission Owner.
    434. LADWP argues that although Section 5 of the Commission's OATT 
provides that the transmission customer must indemnify the Transmission 
Provider that owns facilities financed by tax-exempt debt, it is not 
clear whether that provision would apply to an Interconnection 
Customer. LADWP asks the Commission to clarify that an Interconnection 
Customer is liable for the cost of any adverse tax consequences visited 
on the public power Transmission Owner because of the interconnection.
    435. SoCal PPA believes that the Interconnection Customer's 
obligation to reimburse the Transmission Provider for taxes should 
cover ad valorem property taxes and other taxes assessed against the 
Transmission Provider.
    436. NE Utilities seeks an alternative method for a Transmission 
Provider to recover tax liability for which it is not reimbursed due to 
circumstances beyond its control--for example, if the security 
instrument provided by the Interconnection Customer does not cover the 
full tax liability or if the Interconnection Customer defaults on its 
obligation to indemnify the Transmission Provider. It argues that in 
these situations, the Commission should authorize the Transmission 
Provider to recover the remaining balance from customers.
    437. TXU says that the Commission should provide comprehensive 
protection for a Transmission Provider if the IRS decides that 
Interconnection Customer payments are taxable. A letter of credit, as 
provided for in proposed LGIA Article 5.14.3, would provide some 
security for the Transmission Provider, but may limit the process of 
contesting IRS positions and may prove otherwise difficult to 
administer. Without elaborating, TXU requests that a more comprehensive 
security device be required until definitive guidance is received from 
the IRS.
    438. SoCal Edison states that if a Transmission Provider or 
Transmission Owner is unable to recover from a generator any income tax 
incurred as a result of an interconnection arrangement, the Commission 
should provide Transmission Providers and Transmission Owners with a 
regulatory backstop that would guarantee the recovery of these income 
taxes in transmission rates. It adds that to the extent that a 
Transmission Provider or Transmission Owner is unable to include income 
taxes in transmission rates because of other regulatory restrictions 
(such as a rate freeze or the requirement to have state commission 
approval for such rates), the Transmission Provider or Transmission 
Owner should have discretion in determining the appropriate form and 
level of security required from the generator at the time the IA 
becomes effective, and a right to offset any tax liability against any 
transmission credit owed. Further, SoCal Edison says Article 5.14 must 
state that any future payment shall include interest and penalties, as 
well as any other costs imposed by the IRS.

[[Page 49884]]

    439. Progress Energy advocates that Article 5.14.3 include certain 
requirements regarding the Interconnection Customer-provided financial 
guaranty, such as requiring that the guaranty be issued by a financial 
entity acceptable to the Transmission Provider and that it be non-
revocable for the term of the LGIA.
    440. Dynegy proposes that the Commission make the security 
obligation mutual. The Final Rule should state that, when the 
Transmission Provider requires the Interconnection Customer to pay a 
tax gross-up because the Transmission Provider has determined in good 
faith that the payments or property transfers made to Transmission 
Provider should be reported as income subject to taxation, the 
Transmission Provider must post security for the amount of the gross-
up, plus interest. This will protect the Interconnection Customer from 
becoming an unsecured creditor in the event of a Transmission Provider 
insolvency before the issuance of a private letter ruling that could 
result in the refund of the tax gross-up payment and interest to the 
Interconnection Customer.
    441. Calpine argues that the security requirement should bear a 
reasonable relationship to the risk to which a transmission owner is 
exposed. Instead of allowing the Transmission Provider to require an 
Interconnection Customer to meet a costly security requirement--using 
funds that the Interconnections Customer could put to better use 
developing generation and infrastructure--the Commission should 
authorize the Transmission Provider to recover in its rates any future 
tax liability. If the Commission is unwilling to expose ratepayers to 
this risk, it should modify the Final Rule to ensure that any residual 
security that the Interconnection Customer would be obligated to post 
be reasonably related to the actual risk to which the Transmission 
Provider is exposed.
    442. EPSA argues that an Interconnection Customer should not be 
required to pay the taxes of a Transmission Owner unless the 
Interconnection Customer is entitled to a refund if it is ultimately 
determined that the amounts paid for Interconnection Facilities and 
Network Upgrades are not subject to tax. If the Transmission Owner in 
an Affected System is not a Party to the Interconnection Customer's 
LGIA, the Interconnection Customer will have no means to enforce its 
right to a refund of any amounts it has previously paid in taxes. A 
Transmission Owner is able to insist on security indefinitely, to 
protect against the remote possibility of a change in circumstances 
that might become a subsequent taxable event, the balance reflected in 
the Consensus Tax Provisions would be upset.
Commission Conclusion
    443. In response to MidAmerican's request that proposed LGIA 
Article 5.14.3, which is designated Article 5.17.3 in the Final Rule 
LGIA, specify that the Transmission Owner as well as the Transmission 
Provider is indemnified, the term ``Transmission Provider'' in the LGIA 
includes the Transmission Owner, where applicable. Accordingly, there 
is no need to revise this provision.
    444. SoCal PPA raises tax issues beyond the scope of Article 5.17, 
since this article addresses only federal tax liability. The Commission 
rejects the proposal that ad valorem property taxes be included in the 
Interconnection Customer's obligation to reimburse the Transmission 
Provider for taxes, since these expenses are annual and are more 
analogous to operating expenses that are not covered under the LGIA.
    445. The Commission rejects requests that the Transmission Provider 
may recover any outstanding federal tax liability balance from 
customers. A Transmission Provider is to use the security option in 
Article 5.17.3 to protect itself from the risk that an Interconnection 
Customer will not pay the potential tax liability, so there should not 
be any outstanding liability. This, along with the ability to require 
security or, where appropriate, a gross-up, should sufficiently protect 
the Transmission Provider from potential tax liability. Should the 
Transmission Provider be unable for some reason to recover the full 
cost of its tax liability, it may propose to recover such costs in its 
rates, but the Commission is not pre-authorizing the recovery of these 
costs generically.
    446. In response to SoCal Edison's request for a requirement that 
future payment include interest and penalties, as well as any other 
costs imposed by the IRS, this requirement is in Article 5.17.3.
    447. The Commission rejects as unnecessary Progress Energy's 
request for greater specificity regarding the guaranty because Article 
5.17.3 already gives the Transmission Provider the discretion to choose 
the security in a form ``reasonably acceptable'' to the Transmission 
Provider. Accordingly, the Transmission Provider has the discretion to 
require the Interconnection Customer to offer security that meets the 
criteria Progress Energy specifies.
    448. The Commission agrees with Dynegy that the Interconnection 
Customer should receive security if a Transmission Provider determines 
that the payments or property transfers should be reported as income 
subject to taxation. It is reasonable to require the Transmission 
Provider to post security, since the gross-up puts the Interconnection 
Customer at risk in the event that it turns out that taxes do not have 
to be paid, but the Transmission Provider has become insolvent. Final 
Rule LGIA Article 5.17 gives the Interconnection Customer the option to 
request such security when the Transmission Provider has made an 
independent determination that taxes should be payable.\78\
---------------------------------------------------------------------------

    \78\ Security will not be available when a Governmental 
Authority directs a Transmission Provider to report payments of 
property as income subject to taxation.
---------------------------------------------------------------------------

    449. Regarding EPSA's argument that an Interconnection Customer 
should not be required to pay a gross-up unless it is entitled to a 
refund if the amounts paid ultimately are not taxed, the Commission 
notes that the refund protection is already in Article 5.17.7. This 
protection, together with the ability to require security for a gross-
up, should afford an Interconnection Customer sufficient protection 
against the risk of nonrecovery.
    450. EPSA raises issues regarding tax liability and Network 
Upgrades on Affected Systems. Obligations regarding tax liability and 
related indemnification should be set forth in a separate agreement 
between the Interconnection Customer and the Affected System related to 
the Network Upgrade.\79\
---------------------------------------------------------------------------

    \79\ See Part II.A.2--Section 3.5 (Coordination with Affected 
Systems).
---------------------------------------------------------------------------

    451. Finally, in response to EPSA's argument that proposed LGIA 
Article 5.14.3 of the LGIA permits a Transmission Provider to insist on 
security indefinitely, the Final Rule has been revised to state that 
indemnification will terminate at the earlier of the expiration of the 
ten year testing period, as contemplated by the IRS safe harbor 
provisions, or the applicable statute of limitations, or the occurrence 
of a subsequent taxable event contemplated by this article and the 
payment of any related indemnification obligation. These are reasonable 
end points for the indemnification obligation because once the earlier 
of either of these events occurs, there is no further risk of new tax 
liability and, therefore, no further need for indemnification.
    452. Article 5.14.4--Tax Gross-Up Amount (In the Final Rule LGIA: 
Article 5.17.4)--Proposed LGIA Article 5.14.4

[[Page 49885]]

described how the Parties would calculate the Tax Gross-Up Amount.
Comments
    453. FP&L argues that the tax gross-up methodology in proposed LGIA 
Article 5.14.4, when combined with the requirement that the 
Transmission Provider provide refunds in the form of transmission 
service credits for its full costs of Network Upgrades (including 
income taxes), will not allow the Transmission Provider to be made 
whole for the income tax payments for Network Upgrades. It states that 
Article 5.14.4 requires the Interconnection Customer to pay up front 
the net present value of the income taxes due on Network Upgrades, 
based on the assumption that the Transmission Provider will get income 
taxes back through the future stream of tax depreciation benefits. But 
if the Transmission Provider is also required to give back to the 
Interconnection Customer the net present value of income tax payments, 
plus interest, through refunds, then the Transmission Provider is 
paying the full cost of income taxes on assets that it is purchasing 
and it will not be made whole. FP&L further states that the Commission 
should authorize two alternatives for the tax gross-up methodology: (1) 
The Interconnection Customer pays the full amount of taxes up front, 
but then receives refunds for its tax payments; or (2) the 
Interconnection Customer pays a reduced amount for the taxes up front, 
which is the present value of the Transmission Provider's carrying 
costs, calculated at its current weighted average cost of capital, for 
its tax payment associated with the contribution in aid of construction 
until it receives the payment back over time through tax depreciation, 
but then does not receive refunds for the payment of taxes. Under 
either alternative, it is essential that the Interconnection Customer 
not receive interest from the Transmission Provider on tax payments 
actually made to the government because, if it does, the Transmission 
Provider will not be made whole.
    454. Southern asks the Commission to modify this article so that 
the calculation of the tax gross-up for payments that entitle the 
Interconnection Customer to credits is not reduced by depreciation 
deductions available to the Transmission Provider. FirstEnergy says the 
method of calculating the Present Value Depreciation Amount, should be 
clarified by adding the phrase ``used for Federal and state purposes'' 
after ``* * * Transmission Provider's anticipated tax deductions as * * 
*.''
    455. EPSA supports the tax gross-up calculation in Proposed LGIA 
Article 5.14.4. It argues that the calculation was drafted by tax 
professionals during the ANOPR process in an effort to ensure that the 
Transmission Provider is made whole. The drafting group determined that 
the most appropriate manner for calculating the tax gross-up is the 
methodology set forth in Ozark Gas Transmission Corp., 56 FERC ] 61,349 
(1991). EPSA also states that this formula has been approved by the 
Commission and many existing interconnection agreements use the Ozark 
Gas methodology to compute tax gross-ups for both interconnection 
facilities and network upgrades, without regard to whether the 
Interconnection Customer will receive transmission credits. EPSA 
further argues that the calculation takes into account a Transmission 
Provider's federal and state tax rate and the present value of all tax 
depreciation deductions to which the Transmission Provider is entitled 
over the life of the Interconnection Facilities and Network Upgrades. 
Finally, EPSA argues that the tax benefits associated with depreciation 
are not returned to the Interconnection Customer as transmission 
credits, as some commenters contend. Although the Transmission Provider 
will return the gross tax costs to the Interconnection Customer in the 
form of Transmission Credits, the Transmission Provider still benefits 
from being able to deduct the cost of the Interconnection Facilities 
and Network Upgrades.
Commission Conclusion
    456. The Commission agrees with EPSA that Proposed LGIA Article 
5.14.4 offers the appropriate methodology for ensuring that a 
Transmission Provider is fully compensated for tax consequences. FP&L 
and Southern have not sufficiently explained how the calculation fails 
to make the Parties whole, and we do not revise this article.
    457. This article is designated Article 5.17.4 in the Final Rule 
LGIA.
    458. Article 5.14.5--Private Letter Ruling or Change or 
Clarification of Law (In the Final Rule LGIA: Article 5.17.5)--Proposed 
LGIA Article 5.14.5 would have required that, at the Interconnection 
Customer's request and expense, a Transmission Provider file with the 
IRS a request for a private letter ruling as to whether any property 
transferred or sums paid or to be paid by the Interconnection Customer 
to the Transmission Provider under the LGIA would be subject to federal 
income taxation. The point of obtaining such a ruling is to get a 
definitive answer up front as to whether taxes will be due. If a 
private letter ruling concludes that such sums are not taxable, the 
Interconnection Customer's obligations would be reduced accordingly.
Comments
    459. Commenters criticize the proposed relationships between the 
Interconnection Customer and the Transmission Provider in seeking a 
private letter ruling. El Paso argues that the Transmission Provider 
should have sole discretion to decide how to minimize its taxes, 
including whether to seek a private letter ruling or to contest a tax 
determination. While the Interconnection Customer must indemnify the 
Transmission Provider for tax liability, El Paso argues that this does 
not justify allowing the Interconnection Customer to require the 
Transmission Provider to dedicate its taxpayer status, time, and 
resources to seeking a private letter ruling or contesting a tax 
determination. This inappropriately places the Interconnection Customer 
in the position of deciding how the Transmission Provider will meet its 
obligations to the Interconnection Customer. In addition, even if the 
Interconnection Customer pays filing and legal fees associated with a 
private letter ruling or contest, this does not compensate the 
Transmission Provider for its internal costs of prosecuting such 
proceedings.
    460. Dynegy generally supports this provision but contends that it 
should be revised because it (1) fails to recognize that the 
Interconnection Customer is the Party at risk of paying a tax gross-up 
that turns out not to have actually been required by the tax laws, and 
(2) unduly restricts the Interconnection Customer's ability to make the 
arguments it wants made in pursuing a private letter ruling. For 
instance, Dynegy says, Article 5.14.5 allows the Interconnection 
Customer to prepare only the ``initial draft'' of the private letter 
ruling request, and Article 5.16.6 provides for only one level of 
judicial review for appeals of adverse rulings. Such restrictions 
should be removed because it is the Interconnection Customer, not the 
Transmission Provider, that is paying the gross-up and funding the 
efforts to obtain a private letter ruling.
    461. Salt River Project notes that this provision would require a 
Transmission Provider to file a private letter ruling, at an 
Interconnection Customer's request and expense, but establishes that 
the Interconnection Customer would prepare the initial draft of the 
letter. This will give rise to disclosure and

[[Page 49886]]

confidentiality problems and is a bad business practice.
    462. FP&L proposes, without elaboration, that the Commission modify 
proposed LGIA Article 5.14.5 to permit the Transmission Provider to 
require a jointly filed request for a private letter ruling.
    463. FirstEnergy asks the Commission to clarify that the last 
sentence of this article refers to the need to maintain a parental 
guarantee or letter of credit as required by proposed LGIA Article 
5.14.3, and not the Interconnection Customer's indemnification 
obligations under proposed LGIA Article 5.14 generally.
    464. NYTO argues, without elaboration, that a provision is needed 
to ensure that a Transmission Owner can ask the Interconnection 
Customer to provide financial security to backstop its potential tax 
liability where the Transmission Owner has not asked for a gross-up 
payment from the Interconnection Customer pending any ruling from the 
IRS.
Commission Conclusion
    465. The Commission rejects comments that seek to deny the 
Interconnection Customer the right to ask the Transmission Provider, at 
the Interconnection Customer's expense, to seek a private letter ruling 
from the IRS. The Interconnection Customer would otherwise be without 
recourse if it disagrees with the Transmission Provider's conclusion 
regarding either tax liability (and gross-up) or the need for security, 
and it is the Interconnection Customer that pays the taxes.
    466. In response to Dynegy, we will not grant the Interconnection 
Customer greater latitude with respect to the Transmission Provider's 
request for a private letter ruling because the proposed provision 
already offers a fair balance between the interests of the Parties. 
While the Interconnection Customer funds the request for a private 
letter ruling, permitting it to submit an ``initial draft'' of the 
private letter ruling request, and to insist on a single appeal, allows 
the Interconnection Customer to have adequate participation in the 
effort to secure an IRS determination.
    467. The Commission disagrees with Salt River Project's argument 
that allowing the Interconnection Customer to prepare the initial draft 
of the request for a private letter ruling from the IRS gives rise to 
disclosure and confidentiality problems. The Commission leaves it to 
the Parties to work within the confidentiality and other provisions of 
the LGIA to determine the most appropriate means for allowing the 
Interconnection Customer to draft the request.
    468. FP&L offers no explanation for why the Transmission Provider 
should be permitted to require a jointly filed request for a private 
letter ruling. As a result, we reject FP&L's request.
    469. The Commission agrees with FirstEnergy that the last sentence 
of Proposed LGIA Article 5.14.5 should be revised. This sentence refers 
to the Interconnection Customer's obligations if a private letter 
ruling concludes that the transfers or sums paid to the Transmission 
Provider are not subject to federal income taxation. In this event, the 
Interconnection Customer's obligations with respect to the guaranty or 
gross-up allowed under Final Rule LGIA Article 5.17.3 will be reduced 
or eliminated. The private letter ruling would not eliminate the 
Interconnection Customer's obligation to indemnify the Transmission 
Provider in the event that the IRS changes its ruling or policy or a 
subsequent taxable event occurs.
    470. As for NYTO's argument that the Transmission Provider should 
be able to ask the Interconnection Customer to provide financial 
security when the Transmission Provider has foregone the gross-up, such 
authority is already in Final Rule LGIA Article 5.17.3. Under this 
article, the Transmission Provider may secure a guaranty from the 
Interconnection Customer in an amount equal to the Interconnection 
Customer's estimated tax liability. Since the article does not specify 
the timing of such a request, the request may be made at any time the 
Transmission Provider believes that it is appropriate.
    471. This article is designated Article 5.17.5 in the Final Rule 
LGIA.
    472. Article 5.14.6--Contests--Proposed LGIA Article 5.14.6 
described the obligations that would apply if any Governmental 
Authority determines that the Transmission Provider's receipt of 
payments or property is income subject to taxation. At the 
Interconnection Customer's sole expense, the Transmission Provider 
would appeal or oppose such a determination. Proposed LGIA Article 
5.14.6 also described the procedures for settling the contested ruling.
Comments
    473. Southern proposes clarifying that the Interconnection 
Customer's obligation for the settlement amount is calculated on a 
basis that is fully grossed-up for taxes.
    474. NYTO argues that the Transmission Owner's obligation to 
contest a determination by a Governmental Authority should be subject 
to the Interconnection Customer providing an opinion of tax counsel 
that there is high likelihood of success.
Commission Conclusion
    475. The Commission rejects the commenters' requests. The 
Transmission Provider may determine if the settlement amount is 
appropriate under Article 5.14.6, which is designated Article 5.17.7 in 
the Final Rule, and, therefore, has the opportunity to ensure that the 
amount is calculated in an acceptable manner. The Commission will not 
require that the Interconnection Customer tender a tax counsel opinion. 
Under Article 5.17.7, the Interconnection Customer must pay all of the 
costs of an appeal of the ruling. The Commission believes that the 
prospect of paying for an appeal with a low likelihood of success 
should be a sufficient incentive not to pursue a weak case.
    476. Article 5.14.7--Refund (In the Final Rule LGIA: Article 
5.17.8)--Proposed LGIA Article 5.14.7 described the conditions under 
which a refund would be payable to the Interconnection Customer for any 
payments made related to income tax liability and the formula for 
calculating the refund.
Comments
    477. The Florida PSC recommends that the indemnification treatment 
in the LGIA be subject to review by state commissions on a case-by-case 
basis since there are local consequences. In some instances, 
indemnification alone is insufficient and letters of credit, parental 
involvement or other forms of guarantees may be required to protect 
retail customers adequately from becoming the default responsible 
Party. The Transmission Provider should be able to petition the state 
commission for a more stringent indemnification standard.
Commission Conclusion
    478. The Commission does not grant Florida PSC's request. When the 
Commission, under the authority of sections 201, 205 and 206 of the 
Federal Power Act \80\ sets a rate, term or condition for such 
transmission, a state may not exercise its jurisdiction over a retail 
rate to review the reasonableness of the rate, term or condition set by 
the Commission.\81\
---------------------------------------------------------------------------

    \80\ 16 U.S.C. 824, 824d and 824e (2000).
    \81\ See, e.g., Mississippi Power & Light v. Mississippi ex rel. 
Moore, 487 U.S. 354, 371-72 (1988); Nantahala Power & Light Co. v. 
Thornburg, 476 U.S. 953, 970 (1986) (both applying the same 
principle to the Commission's jurisdiction over wholesale sales of 
electric energy).
---------------------------------------------------------------------------

    479. This article is designated Article 5.17.8 in the Final Rule 
LGIA.

[[Page 49887]]

    480. Article 5.14.8--Taxes Other Than Income Taxes (In the Final 
Rule LGIA: Article 5.17.9)--Proposed LGIA Article 5.14.8 described the 
Parties' obligations if taxes other than federal or state income taxes, 
and for which the Interconnection Provider may be required to reimburse 
the Transmission Provider under the terms of the LGIA, are imposed. At 
the Interconnection Customer's expense, the Transmission Provider would 
appeal or oppose such a determination. Proposed LGIA Article 5.14.8 
also described the procedures for settling the contested ruling.
Comments
    481. FP&L asks the Commission to clarify Article 5.14.8 to require 
the Interconnection Customer to pay tax costs, other than income tax, 
related to interconnection payments.
Commission Conclusion
    482. The Commission notes that Article 5.14 does not limit recovery 
to state or federal income taxes related to interconnection payments. 
This provision by itself does not create additional tax liability 
beyond income taxes. Because FP&L offered no justification for why 
additional tax protection is necessary, the Commission rejects its 
request.
    483. This article is designated Article 5.17.9 in the Final Rule 
LGIA.
    484. Article 5.15--Tax Status (In the Final Rule LGIA: Article 
5.18)--Proposed LGIA Article 5.15 provided that each Party cooperate 
with the other to maintain the other Party's tax status. It also 
proposed that the LGIA would not be intended to adversely affect any 
Transmission Provider's tax exempt status with respect to the issuance 
of bonds.
Comments
    485. NYTO proposes modifying the LGIA to be consistent with the 
tax-exempt bond provisions of the Transmission Owner's (or the ISO's) 
OATT. Thus, the LGIA would provide that the Transmission Owner is not 
obligated to take any action, and the Interconnection Customer is 
prohibited from taking any action, that would adversely affect the tax-
exempt status of the Transmission Owner's (or the ISO's) local 
furnishing bonds.
    486. Several commenters, including LADWP and TANC, are concerned 
about the effect that providing Interconnection Service will have on 
the tax-exempt status of their bond funding. TANC asks the Commission 
to provide flexibility for municipal utilities that adopt the Tariff 
additions. NRECA-APPA is concerned that contributions by an 
Interconnection Customer for construction of interconnection facilities 
and Network Upgrades may result in loss of its tax-exempt status. A 
tax-exempt cooperative must ensure that at least 85 percent of its 
income comes from members.
    487. LPPC urges the Commission to give public power utilities the 
option to: (1) Refuse to provide an interconnection if doing so would 
jeopardize the tax-exempt status of the public power utility's 
financing; or (2) proceed with the interconnection with an 
indemnification provision that would require Interconnection Customers 
to reimburse public power entities if any aspect of compliance with the 
Final Rule causes the utility to lose the tax-exempt status of its 
bonds.
Commission Conclusion
    488. The Commission concludes that the tax status of the Parties is 
sufficiently protected by Proposed LGIA Article 5.15.
    489. As described more fully in the reciprocity discussion in this 
preamble, public power and other nonjurisdictional entities with ``safe 
harbor'' tariffs may add the Final Rule LGIP and Final Rule LGIA to 
their safe harbor tariffs if they wish to continue to have safe harbor 
protection.\82\ The Commission limits reciprocity compliance to those 
services a nonjurisdictional entity is capable of providing on its 
system.\83\ The Commission will consider the restrictions on 
nonjurisdictional and jurisdictional entities' conduct that would 
endanger the tax exempt status of their bond funding during compliance 
or upon submission of amended safe harbor tariffs, and we will act to 
ensure that they retain their tax-exempt status. Accordingly, the 
Commission need not address further here the argument raised by LPPC.
---------------------------------------------------------------------------

    \82\ See part II.C.7 (OATT Reciprocity Requirements Applied to 
the Final Rule LGIP and Final Rule LGIA).
    \83\ Order No. 888-A, FERC Stats. & Regs ] 31,048 at 30,286.
---------------------------------------------------------------------------

    490. This article is designated Article 5.18 in the Final Rule 
LGIA.
    491. Article 6--Testing and Inspection--Proposed LGIA Article 6 
provided that, prior to the Commercial Operation of the Generating 
Facility, the Transmission Provider shall test the Transmission 
Provider Interconnection Facilities and Network Upgrades, and the 
Interconnection Customer shall test the Generating Facility and the 
Interconnection Customer's Interconnection Facilities to ensure their 
safe and reliable operation. The Interconnection Customer would bear 
the cost of these tests and any modifications. After the Commercial 
Operation Date, each Party shall conduct routine inspection and testing 
of its own facilities, at its own expense, in accordance with Good 
Utility Practice.
Comments
    492. Entergy generally supports the testing and inspection 
provisions, but urges that Article 6.1 provide the Parties with 
additional scheduling flexibility if testing reveals the need for 
modifications to the Generating Facility. Entergy therefore proposes 
that the Parties' schedules for completing their respective obligations 
to construct and install facilities shall be extended to the extent 
reasonably necessary to complete any necessary modifications to the 
Generating Facility.
    493. Arkansas Coops propose that Article 6.1 of the NOPR LGIA be 
modified to prohibit a Transmission Provider from preventing an 
Interconnection Customer sale of test energy to an entity other than 
the Control Area operator.
Commission Conclusion
    494. The Commission does not believe that a change to the LGIA is 
required in order to satisfy Entergy's concern. The LGIA is premised on 
the idea that the Interconnection Customer and Transmission Provider 
will coordinate the interconnection of the Interconnection Customer's 
Interconnection Facilities on an ongoing basis. If the testing reveals 
a problem with the Interconnection Facilities or Network Upgrades, the 
LGIA contemplates that the Parties will work together to modify the 
schedule.
    495. In response to Arkansas Coops, the Interconnection Customer 
may sell its energy to anyone; the LGIA does not need to address this 
matter, as it is not an interconnection matter.
    496. Article 7--Metering--Proposed LGIA Article 7 would have 
required that, unless otherwise agreed to by the Parties, the 
Transmission Provider shall install, own, operate, and maintain 
Metering Equipment at the Point of Interconnection, with the 
Interconnection Customer bearing all reasonable documented costs.
    497. Article 7.2--Check Meters--Proposed LGIA Article 7.2 provided 
that the Interconnection Customer, at its own expense, may install one 
or more meters on its side of the Point of Interconnection to check the 
accuracy of Transmission Provider's meters.
    498. Article 7.3--Standards--Proposed LGIA Article 7.3 provided 
that if Article 7 conflicts with the manuals,

[[Page 49888]]

standards or guidelines of the Applicable Reliability Council, the 
latter shall control.
    499. Article 7.4--Testing of Metering Equipment--Proposed LGIA 
Article 7.4 provided that if at any time Metering Equipment fails to 
register or is found to be inaccurate by more than one percent, the 
Transmission Provider shall correct all measurements made by the 
inaccurate meter.
    500. Article 7.5--Metering Data--Proposed LGIA Article 7.5 provided 
that the official measurement of the amount of energy delivered from 
the Generating Facility to the Point of Interconnection is the metered 
data, which would be telemetered to one or more locations designated by 
the Transmission Provider and one or more locations designated by the 
Interconnection Customer.
Comments
    501. Cal ISO and SoCal Edison argue that, in California, it is the 
Cal ISO Tariff that governs metering provisions. They further argue 
that many provisions of proposed LGIA Article 7 appear to be at odds 
with Cal ISO's Tariff and WECC requirements. For example, Cal ISO 
points out that proposed Article 7.1 appears to require metering only 
at the Point of Interconnection which would mean ``net metering,'' 
whereas WECC requires Cal ISO to meter a generator's gross output.
    502. SoCal Edison and WEPCO argue that the Transmission Provider 
should not be required to own the meters because owning meters carries 
with it some liability associated with inaccurate meter readings.
    503. Dynegy comments that meters should be installed at an agreed-
upon location rather than at the Point of Interconnection, and metering 
information should be provided in analog and digital form to no more 
than two locations specified by the Transmission Provider. It also 
proposes that check meter measurements be used when the primary meter 
is inaccurate, and that the Final Rule specify in more detail the cost 
responsibility of the Transmission Provider if it does not properly 
maintain the metering equipment.
    504. Baker & McKenzie and Dynegy argue that proposed LGIA Article 
7.2 incorrectly references Article 7.3 and should refer instead to 
Article 7.4. Several commenters, including Baker & McKenzie, the Bureau 
of Reclamation, Dynegy, and Monongahela Power, propose that language 
should be added to Article 7.4 to use check meters to correct the 
measurements read by failed or inaccurate Metering Equipment. Baker & 
McKenzie proposes several editorial changes to clarify Article 7.4.
    505. FirstEnergy argues that the one percent metering accuracy is 
very difficult to achieve and its current interconnection agreement as 
well as the industry standard allows for a two percent metering error. 
It asserts that the provision should be changed to allow for a metering 
error of two percent. Monongahela Power argues that the allowed 
metering error should be 1.5 percent.
    506. Several commenters including EEI, FirstEnergy, and Southern 
argue that the last sentence of proposed LGIA Article 7.5 incorrectly 
states that ``metering data [is] provided by the Interconnection 
Customer'' because the metering data is being provided by the 
Transmission Provider to the Interconnection Customer.
Commission Conclusion
    507. Cal ISO's concern with regard to metering being allowed only 
at the Point of Interconnection is misplaced. Proposed LGIA Article 
7.1, which provides that ``[u]nless otherwise agreed by the Parties, 
Transmission Provider shall install Metering Equipment at the Point of 
Interconnection,'' clearly allows Metering Equipment to be placed at an 
agreed upon location different from the Point of Interconnection. 
However, in response to Cal ISO's and SoCal Edison's concern that their 
metering provisions are governed by WECC requirements, we are adding 
the following language to Article 7.1: ``Each Party shall comply with 
the Applicable Reliability Council requirements.'' The Commission does 
not expect that Applicable Reliability Council requirements will 
conflict with our provisions in Final Rule LGIA Article 7. Accordingly, 
we find the following language to be unneeded and are deleting it from 
Article 7.3 (Standards): ``To the extent this Article 7 conflicts with 
the manuals, standards, or guidelines of the Applicable Reliability 
Council regarding interchange metering and transactions, the manuals, 
standards and guidelines of such Applicable Reliability Council shall 
control.''
    508. In response to SoCal Edison and WEPCO, we are not revising 
proposed LGIA Article 7.1 because the Final Rule contains the phrase 
``[u]nless otherwise agreed by the Parties'' which allows any Party to 
own the meters. In response to Dynegy and Baker & McKenzie we are 
changing the reference in Final Rule LGIA Article 7.2 to Article 7.4. 
We are also adding language in Final Rule LGIA Article 7.4 for the use 
of check meters to correct the measurements read by failed or 
inaccurate Metering Equipment. In response to FirstEnergy and 
Monongahela Power's argument, the Commission adopts a metering error of 
two percent because, as pointed out by FirstEnergy, two percent is the 
industry standard. Finally, we are correcting the error in the last 
sentence of proposed LGIA Article 7.5 noted by EEI, FirstEnergy and 
Southern.
    509. Article 8--Communication--Proposed LGIA Article 8 described 
the operating communications and dedicated data circuits between the 
Parties that would be necessary and the cost and maintenance 
responsibility for such equipment.
    510. Article 8.1--Interconnection Customer Obligations--Proposed 
LGIA Article 8.1 would have required the Interconnection Customer to 
maintain satisfactory operating communications with the Transmission 
Provider's Transmission System dispatcher or designated 
representatives.
Comments
    511. NERC and Western recommend that a Transmission Provider be 
permitted to use a voice communications system that does not rely on 
the public telephone system.
    512. Dairyland Power proposes that maintenance be performed by the 
Transmission Provider, in an agreed upon manner, at the Interconnection 
Customer's expense.
    513. Cleco and FirstEnergy propose that the Interconnection 
Customer be responsible for the cost of maintaining any communications 
and computer equipment belonging to either Party, as well as the 
hardware and software necessary for the Transmission Provider to 
interface properly with the Interconnection Customer's system.
    514. Progress Energy requests that the first sentence of proposed 
LGIA Article 8.2 be rewritten to read: ``Prior to the Initial 
Synchronization Date of the [Generating] Facility, a remote terminal 
unit, or equivalent data collection and transfer equipment acceptable 
to both Parties shall be installed * * *''
    515. The Bureau of Reclamation believes that cyber-security and 
data security issues should be addressed in the body of the LGIA, and 
not in an Appendix.
Commission Conclusion
    516. The Commission concurs with the recommendations of NERC, 
Western and Progress Energy, and revises Proposed LGIA Articles 8.1 and 
8.2 to allow greater flexibility.
    517. In response to the Bureau of Reclamation, the Commission notes 
that

[[Page 49889]]

the Appendices are as binding as provisions within the body of the 
LGIA.
    518. Articles 8.1 and 8.2 require that the Interconnection Customer 
transmit the data to a point specified by the Transmission Provider. 
Once the data has reached that point, it becomes the responsibility of 
the Transmission Provider to maintain its own hardware and software 
equipment. In response to Dairyland Power, the Commission notes that 
the Parties may enter into an agreement regarding which Party actually 
performs the data system maintenance, but the Interconnection Customer 
is ultimately responsible for paying for that maintenance.
    519. Article 9--Operations--Proposed LGIA Article 9 would have 
required the Interconnection Customer and Transmission Provider to 
operate their facilities in a safe and reliable manner. It also 
proposed reactive power requirements and provided that the 
Interconnection Customer will be compensated for capital expenses 
incurred based on the use of the Interconnection Facilities by the 
Transmission Provider, all third party users, and the Interconnection 
Customer.
    520. Article 9.1--General--Proposed LGIA Article 9.1 would have 
required the Parties to comply with LGIA Appendix G (Interconnection 
Guidelines). It would also require that each Party provide to the other 
Parties all information that may be required to comply with Applicable 
Laws and Regulations.
Comments
    521. Southern, Lakeland, and FirstEnergy state that Article 9.1 
should refer to Applicable Reliability Council requirements instead of 
Appendix G Interconnection Guidelines, which is blank. FirstEnergy 
states that each Party should be required to comply with the 
requirements of any RTO or ISO and any procedures agreed to by the 
Joint Operating Committee.
    522. Exelon requests that proposed LGIA Article 9.1 be modified to 
include the following language: ``To the extent interconnection 
requirements are inconsistent with ISO/RTO rules, the ISO/RTO rules 
shall govern.''
Commission Conclusion
    523. In the Final Rule, Article 9.1 refers to Applicable 
Reliability Council requirements. The Commission is deleting Appendix G 
(Interconnection Guidelines). With respect to FirstEnergy's request 
that Parties be required to comply with any procedures agreed to by the 
Joint Operating Committee, the Commission does not believe that any 
language changes are required. We clarify that the Parties are expected 
to comply with the procedures established by the Joint Operating 
Committee. We also clarify that the RTO or ISO rules, once approved by 
the Commission, shall govern the LGIA.
    524. Article 9.2--Control Area Notification--Proposed LGIA Article 
9.2 would have required the Interconnection Customer to notify the 
Transmission Provider in writing of the location of its Control Area at 
least three months before the Generating Facility's Initial 
Synchronization Date. The proposed article also provided that the 
Interconnection Customer has the right to change the Control Area after 
the Initial Synchronization Date.
Comments
    525. Some commenters, including PG&E and Cal ISO, believe that the 
Generating Facility must be the Control Area to which it is 
electrically connected.
    526. MidAmerican believes that the Interconnection Customer must 
provide the metering and communications necessary to be a part of a 
Control Area other than the Transmission Provider's Control Area. Cleco 
proposes that since switching Control Areas is labor-intensive for the 
employees of both Control Areas, the Interconnection Customer should be 
required to remain in a Control Area for at least 12 months before 
switching.
    527. NERC asks that proposed LGIA Article 9.2 be clarified to 
ensure that the host Control Area (the Control Area to which the 
Interconnection Customer is physically connected, regardless of whether 
the Generating Facility is electrically telemetered to another Control 
Area through a dynamic transfer) can enforce an Interconnection 
Customer's power factor, voltage control, and other similar 
obligations. Others commenters, including WEPCO, MidAmerican, Avista, 
National Grid, Southern, express concerns that a separate agreement and 
control equipment modification should be required, and that if the 
Interconnection Customer designates a different Control Area, it should 
be required to follow the rules for all applicable Control Areas.
    528. Duke Energy asks what the consequence would be if an 
Interconnection Customer fails to notify a Transmission Provider of its 
Control Area three months prior to its Commercial Operating Date. The 
Maine PSC requests that Article 9.2 permit waiver of Control Area 
notification in certain situations.
Commission Conclusion
    529. In response to Cal ISO, PGE, and Cleco, the Commission does 
not prohibit dynamic scheduling of a Generating Facility physically 
connected in one Control Area but scheduled into another. Nor does it 
place restrictions on changing Control Areas and how long an 
Interconnection Customer must remain in a Control Area. Moreover, in 
Order No. 888 the Commission did not require that Transmission 
Providers offer dynamic scheduling.\84\ However, we also agree with the 
concerns expressed by NERC and other commenters that the process of 
changing Control Areas and the attendant implementation brings about 
requirements for coordination, control equipment modification, and 
agreement on operational details. In such cases, the Commission 
confirms that the Transmission Provider's OATT shall apply.
---------------------------------------------------------------------------

    \84\ Order No. 888 at 31,709-10.
---------------------------------------------------------------------------

    530. We also confirm that the Interconnection Customer must notify 
the Transmission Provider at least three months before the Initial 
Synchronization Date of the Control Area in which it will be located. 
Failure of an Interconnection Customer to make the appropriate Control 
Area designation would be treated as a Breach of the Final Rule LGIA, 
subject to opportunity to cure. Similarly, while an Interconnection 
Customer could request that the Transmission Provider waive the three 
month notice requirement, we decline to make that a provision of the 
Final Rule LGIA.
    531. Article 9.3--Transmission Provider Obligations--Proposed LGIA 
Article 9.3 would have required the Transmission Provider to operate 
and maintain its Transmission System in a safe and reliable manner and 
in accordance with the LGIA. It also proposed that the Interconnection 
Customer would not be obligated to follow the Transmission Provider's 
instructions if those instructions would undermine the safe and 
reliable operation of the Generating Facility.
Comments
    532. NERC proposes deleting the proposed language allowing an 
Interconnection Customer to not follow the Transmission Provider's 
instructions if doing so would cause material damage to the Generating 
Facility. NERC is concerned that the language appears to grant the 
Interconnection Customer a blanket right not to follow operating 
instructions of the Transmission Provider.

[[Page 49890]]

    533. NYTO proposes revising Article 9.3 of the NOPR LGIA to remove 
any incentive for the Interconnection Customer to ``create'' 
circumstances (e.g., emergencies) that would warrant noncompliance.
    534. Southern asserts that it is inappropriate to impose broad 
obligations on a Transmission Provider's Transmission Systems in the 
LGIA. The LGIA should govern only the interconnection of an 
Interconnection Customer and the Interconnection Facilities necessary 
to achieve the interconnection, not the entire Transmission System.
    535. Dynegy states that proposed LGIA Article 9.3 fails to consider 
the economic effect of operating instructions on the Interconnection 
Customer, which could be financially devastating, and that the article 
should make clear that the Transmission Provider must compensate the 
Interconnection Customer for responding to such operating instructions.
Commission Conclusion
    536. We agree with NERC's concern that the proposed language 
appears to grant the Interconnection Customer a blanket right not to 
follow the operating instructions of the Transmission Provider during 
normal operating conditions and accordingly delete the proposed 
language in the Final Rule. We expect a Transmission Provider to follow 
NERC procedures and to take every precaution not to cause any material 
adverse impact on the safe and reliable operation of the Generating 
Facility. It is essential that the Interconnection Customer follow all 
orders given by the Transmission Provider, unless they would result in 
impairment to public health or safety, since otherwise the Transmission 
Provider would be unable to effectively manage its Transmission 
System.\85\ Final Rule LGIA Article 13.6 (Interconnection Customer 
Authority) allows Interconnection Customers to take ``actions or 
inactions'' necessary to ``preserve the reliability of the 
Interconnection Customer's Generating Facility'' during an Emergency 
Condition.
---------------------------------------------------------------------------

    \85\ Pacific Gas and Electric Company, et al., 81 FERC ] 61,122 
at 61,456 (1997).
---------------------------------------------------------------------------

    537. In response to NYTO's comments, all Parties are obligated to 
follow Good Utility Practice and to abide by their obligations under 
the LGIA. If a Party were to manufacture an Emergency Condition, it 
would be a violation of the LGIA, as well as a serious Breach of NERC 
and other reliability rules.
    538. Southern's concerns are misplaced. Proposed LGIA Article 9.3 
simply stated that the Transmission Provider shall maintain its system 
in a safe manner and that the Interconnection Customer is required to 
follow the instructions of the Transmission Provider under normal 
circumstances.
    539. Dynegy's comment also appears to be misplaced. Proposed LGIA 
Article 9.3 dealt with the obligations of the Transmission Provider, 
not the obligations of the Interconnection Customer. Assuming that 
Dynegy's comment applies to Article 9.4 instead, we clarify that a 
Party is not obligated to follow a Transmission Provider's instructions 
that would cause harm to its Generating Facility, unless public health 
and safety would be threatened by noncompliance.
    540. Article 9.6.1--Power Factor Design Criteria--Proposed LGIA 
Article 9.6.1 would have required the Generating Facility to be 
designed so that at the continuous rated power output, its power factor 
would be within a range of 0.97 leading to 0.95 lagging, unless the 
Transmission Provider has established different requirements applicable 
to all Interconnection Customers in the Control Area on a comparable 
basis.
Comments
    541. NERC proposes that the Commission require power factor 
capabilities to be ``within a range required by Good Utility 
Practice,'' which incorporates NERC standards by reference. It cites 
its own Planning Standard, which allows a generator to be within the 
range of 0.95 leading to 0.90 lagging and argues that such a range 
provides more responsive reactive absorption and supply than the range 
proposed in Article 9.6.1. That Planning Standard also requires that if 
the Generating Facility does not meet the requirements, the 
Interconnection Customer must make alternate arrangements for supplying 
dynamic reactive power to meet the area's reactive power requirements. 
However, NERC concedes that a power factor requirement of 0.95 leading 
to 0.95 lagging is a common practice in some NERC regions.
Commission Conclusion
    542. We adopt the power factor requirement of 0.95 leading to 0.95 
lagging because it is a common practice in some NERC regions. If a 
Transmission Provider wants to adopt a different power factor 
requirement, Final Rule LGIA Article 9.6.1 permits it to do so as long 
as the power factor requirement applies to all generators on a 
comparable basis.
    543. Article 9.6.3--Payment for Reactive Power--Proposed LGIA 
Article 9.6.3 would have provided that the Transmission Provider pay 
the Interconnection Customer for reactive power that the Generating 
Facility provides or absorbs. Such payment would be in accordance with 
the Interconnection Customer's rate schedule unless service is subject 
to a Commission-approved RTO or ISO rate schedule. If no rate schedule 
is in effect, the Transmission Provider would compensate the 
Interconnection Customer in an amount that would be due the 
Interconnection Customer had the rate schedule been in effect when the 
service commenced; provided, however, that the rate schedule must be 
filed with the Commission within 60 Calendar Days of the commencement 
of service.
Comments
    544. El Paso and others maintain that the Interconnection Customer 
should not be compensated for reactive power provided or absorbed 
within the power factor range established in Article 9.6.1 (Power 
Factor Design Criteria) since it is only meeting its obligation to do 
so. MidAmerican, Cleco, El Paso, Nevada Power, PG&E, and Western state 
that the Interconnection Customer should be compensated for the 
reactive power it provides or absorbs when the Transmission Provider 
asks the Interconnection Customer to operate its Generating Facility 
outside the established power factor range. Cleco and Nevada Power also 
contend that if the Transmission Provider pays for reactive power, so 
should the Interconnection Customer, when it does not meet the 
Transmission Provider's voltage schedule that can be met by the 
established power factor range.
    545. MidAmerican and Cleco argue that reactive power should be paid 
for only if the Interconnection Customer has filed a rate schedule with 
the Commission prior to the commencement of service. Duke argues that 
the last sentence of the NOPR LGIA Article 9.6.3 that provides for 
filing of a rate schedule within 60 Calendar Days of having provided 
reactive service without a rate schedule should be moved to Article 
11.6 (Interconnection Customer Compensation) to cover a similar 
situation during an Emergency Condition. Cal ISO believes that the 
procurement of reactive power should be left to another proceeding 
(such as a Regional Market Design proceeding),

[[Page 49891]]

and NYISO states that this issue is already being dealt with in its 
Market Administration and Control Area Services Tariff.
Commission Conclusion
    546. We agree that the Interconnection Customer should not be 
compensated for reactive power when operating its Generating Facility 
within the established power factor range, since it is only meeting its 
obligation. Proposed Article 9.6.3 required payment for reactive power 
to an Interconnection Customer only when the Transmission Provider 
requests the Interconnection Customer to operate its Generating 
Facility outside the range established in Article 9.6.1 (Power Factor 
Design Criteria). In response to Cleco and Nevada Power, we agree that 
the Interconnection Customer should be penalized or otherwise 
compensate the Transmission Provider if the Interconnection Customer 
does not meet the Transmission Provider's voltage schedule 
requirements, so long as the voltage schedule requirements can be met 
by the established power factor range. The Commission is not including 
a standard penalty or compensation provision here, but will entertain 
reasonable requests to do so on compliance. We agree with Duke and move 
the last sentence of Article 9.6.3 to 11.6.
    547. With respect to the argument that payment for reactive power 
should be required only if the Interconnection Customer has a rate 
schedule on file when service commences, we note that the Commission's 
Regulations allow an applicant to file a rate schedule within 60 days 
of the commencement of service.\86\
---------------------------------------------------------------------------

    \86\ See 18 CFR 35.3 (2003).
---------------------------------------------------------------------------

    548. An RTO or ISO, at the time its compliance filing is made, may 
propose variations from this policy, as discussed below.\87\ An RTO or 
ISO has different operating characteristics depending on its size and 
location and is less likely to act in a discriminatory manner than a 
Transmission Provider that is also a market participant. An RTO or ISO 
will have greater flexibility to customize its LGIP and LGIA to respond 
to regional needs.
---------------------------------------------------------------------------

    \87\ See Part II.C.5 (Variations from the Final Rule and 
Regional Differences).
---------------------------------------------------------------------------

    549. Article 9.7.1.2--Outage Schedule--Proposed LGIA Article 
9.7.1.2 would have a Transmission Provider post transmission facility 
outages on the Open Access Same-Time Information System (OASIS) and 
require an Interconnection Customer to schedule its maintenance on a 
rolling 24 month basis. It also stated that a Transmission Provider may 
ask the Interconnection Customer to reschedule its maintenance as 
necessary to maintain the reliability of the Transmission System; 
however, the Transmission Provider will compensate the Interconnection 
Customer for any costs of rescheduling such maintenance.
Comments
    550. Several commenters argue that the Transmission Provider should 
not be required to compensate the Interconnection Customer for the 
costs of rescheduling maintenance when the purpose of rescheduling the 
maintenance is to ensure the reliability of the Transmission System. 
For example, Cal ISO claims that the compensation issue should be 
resolved by deferring to the RTO or ISO outage coordination provisions 
in its Tariff. Southern contends that the Interconnection Customer 
benefits from a reliable Transmission System and should therefore 
maintain the reliability of the Transmission System without any 
compensation for rescheduling its outages. Southern also argues that 
the provision seems to require the Transmission Provider to compensate 
the Interconnection Customer for rescheduling maintenance even if such 
rescheduling is required to interconnect another Interconnection 
Customer. If the provision is adopted, Southern requests clarification 
that the Interconnection Customer, not the Transmission Provider, is 
required to pay the costs that other Interconnection Customers incur to 
reschedule their maintenance. Southern also requests clarification that 
the reimbursed costs are limited to direct costs and will not include 
consequential or indirect costs (such as lost profits).
    551. Dairyland Power, PSNM, and Western assert that an 
Interconnection Customer may try to game the outage scheduling process. 
It could revise its maintenance schedule to coincide with a maintenance 
project (by listing it on the Transmission Provider's OASIS) and thus 
create congestion or reliability conditions on the Transmission System 
for the purpose of receiving compensation from the Transmission 
Provider. PSNM further states that while curtailment and redispatch 
costs under the OATT generally are shared on a pro rata basis when 
transmission service is not available, this article anticipates that 
the Transmission Provider will compensate an Interconnection Customer 
for changes in the Interconnection Customer's maintenance plan, with no 
reciprocal compensation if the Interconnection Customer changes its own 
plans.
    552. Western believes that requiring the Transmission Provider to 
compensate for ``any costs'' leaves too much to interpretation. The 
provision should be limited to actual costs incurred by the 
Interconnection Customer, such as remobilization costs, to prevent 
gaming. AEP believes that compensation should be provided on rare 
occasions when maintenance must be rescheduled for reliability 
purposes. Cleco believes that the payment to the Interconnection 
Customer should occur only if the Transmission Provider is initially 
allowed to approve the maintenance schedule proposed by the 
Interconnection Customer.
Commission Conclusion
    553. We agree that the proposed requirement to compensate 
Interconnection Customers for ``any costs'' incurred in rescheduling 
maintenance is overly broad. Compensation should be limited to the 
additional, direct costs that the Interconnection Customer incurs as a 
result of having to reschedule maintenance.
    554. We also agree that this article, as proposed, could create an 
opportunity for gaming on the part of the Interconnection Customer, 
which might schedule its maintenance at a time when the Transmission 
Provider could be expected to ask it to reschedule. Therefore the 
proposed article is modified so that an Interconnection Customer will 
not receive compensation if it had modified its schedule of maintenance 
activities during the year before the date of the initially scheduled 
maintenance.
    555. Article 9.7.1.3--Outage Restoration--Proposed LGIA Article 
9.7.1.3 would have provided that if an outage on a Party's 
Interconnection Facilities or Network Upgrades harms the other Party's 
facilities, the Party owning or controlling the facility that is out of 
service will use Reasonable Efforts to promptly restore it to a normal 
operating condition.
Comments
    556. NERC proposes to require the first Party to provide the other 
Party information on the nature of the Emergency Condition, including 
an estimated time of restoration, and on any corrective actions 
required, as soon as practical, followed by a written explanation of 
the nature of the outage. The clarification is necessary because the 
outage may affect outage clearances on other equipment, calculation of

[[Page 49892]]

transfer capabilities, system deratings, and so on.
Commission Conclusion
    557. We incorporate NERC's proposed change. NERC's proposal 
recognizes not only the importance of restoration after an outage, but 
the necessity of coordinated restoration and information-sharing to 
make all affected Parties aware of the restoration, the corrective 
actions taken, and the time the restoration occurred, so that all 
Parties may determine whether the interconnected system has been 
returned to a normal operating condition.
    558. Article 9.7.2--Interruption of Service (In the NOPR: 
Continuity of Service)--Proposed LGIA Article 9.7.2 would have provided 
that the Transmission Provider may require the Interconnection Customer 
to reduce or interrupt deliveries of electricity if such delivery of 
electricity would adversely affect the Transmission Provider's ability 
to perform activities that are necessary to safely and reliably operate 
and maintain the Transmission System. It also would require the 
Transmission Provider to schedule the reduction or interruption to 
either coincide with the scheduled outage of the Generating Facility or 
during periods of low demand.
Comments
    559. Several commenters, mostly Transmission Providers such as 
Exelon, MidAmerican, PG&E and Southern, argue that the last sentence of 
proposed LGIA Article 9.7.2.4 that requires the Transmission Provider 
to schedule the reduction or interruption to either coincide with the 
scheduled outage of the Generating Facility or during periods of low 
demand unreasonably limits the Transmission Provider when it can 
perform maintenance and repair work. PG&E asserts that the periods of 
low demand either occur at night or during winter, and those times are 
not suitable for performing maintenance and repair work because it may 
jeopardize the safety of maintenance personnel. MidAmerican argues that 
the impact on both the Transmission Provider and Interconnection 
Customer should be considered when scheduling maintenance and repair 
work on the Transmission System. MidAmerican offers this alternative 
last sentence of proposed LGIA Article 9.7.2.4: ``Transmission Provider 
shall coordinate with the Interconnection Customer using Good Utility 
Practice to schedule the interruption or reduction during periods of 
least impact to the Interconnection Customer and the Transmission 
Provider.''
    560. Exelon argues that a separate provision should be added to 
require the Transmission Provider to notify the Interconnection 
Customer before the Transmission Provider undertakes any construction, 
repair or maintenance work on its Transmission System that may require 
the Interconnection Customer to reduce output from its Generating 
Facility.
Commission Conclusion
    561. In response to MidAmerican and PG&E's concern, we adopt 
MidAmerican's proposed language because it balances the interests of 
both the Transmission Provider and the Interconnection Customer. With 
regard to Exelon's argument, we note that Article 9.7.2.4 of the Final 
Rule LGIA provides that: ``Except during the existence of an Emergency 
Condition, when the interruption or reduction can be scheduled without 
advance notification, Transmission Provider shall notify 
Interconnection Customer in advance regarding the timing of such 
scheduling and further notify Interconnection Customer of the expected 
duration.''
    562. Article 9.7.3--Under-Frequency and Over-Frequency Conditions 
(In the NOPR: Under-Frequency Load Shed Event)--Proposed LGIA Article 
9.7.3 stated that the Transmission System is designed to activate a 
load-shed program automatically in the event of an under-frequency 
system disturbance. It proposed that an Interconnection Customer shall 
implement an under-frequency relay set point for the Generating 
Facility to ensure ``ride through''\88\ capability of the Transmission 
System, to the extent allowed by equipment limitations or warranties.
---------------------------------------------------------------------------

    \88\ ``Ride through'' means a Generating Facility staying 
connected to and synchronized with the Transmission System during 
system disturbances within a range of over- and under-frequency 
conditions, in accordance with Good Utility Practice.
---------------------------------------------------------------------------

Comments
    563. NERC, MidAmerican, and SoCal Edison state that the scope of 
Article 9.7.3 should be expanded to include over-frequency conditions 
as well.
    564. NERC, Florida RCC, and TECO Energy oppose relying on equipment 
limitations or warranties as an excuse for an Interconnection Customer 
to avoid following Applicable Reliability Council rules. They claim 
that in a limited number of instances where equipment limitations do 
exist, the Applicable Reliability Council's rules permit the 
Interconnection Customer to propose alternative load shedding 
procedures. They also express concern that should the Commission retain 
the language relating to equipment limitations or warranties, load 
shedding procedures may not be effective to prevent full collapse of an 
electrical ``island,'' thereby threatening the reliability of the 
Transmission System.
    565. NERC recommends that the Generating Facility's response to 
both under- and over-frequency conditions be studied and coordinated 
with the Transmission Provider's Transmission System in accordance with 
Good Utility Practice.
Commission Conclusion
    566. We agree with many commenters that their proposed changes 
would better protect reliability. Therefore, we revise Article 9.7.3 to 
refer to Applicable Reliability Council requirements and to include 
over-frequency conditions. Equipment limitations or warranties should 
not be an excuse for not following Applicable Reliability Council 
rules; in case of genuine equipment limitations, Applicable Reliability 
Council rules permit the Interconnection Customer to offer alternative 
proposals. As such, the Commission eliminates the phrase ``equipment 
limitations or warranties'' in the Final Rule. In addition, the 
Commission is adopting NERC's proposed language regarding studies to 
determine the Generating Facility's response to frequency deviations 
because of its importance in stabilizing the power system during an 
electrical disturbance.
    567. Article 9.7.4.1--System Protection Facilities (In the NOPR: 
Protection and System Quality)--Proposed LGIA Article 9.7.4.1 would 
have required that the Interconnection Customer, at its expense, 
install, operate and maintain System Protection Facilities.
Comments
    568. NERC states that the title of proposed LGIA Article 9.7.4.1 
should be changed from ``Protection and System Quality'' to 
``Protection Required by Study'' because system quality issues are not 
addressed here.
Commission Conclusion
    569. The title of Final Rule LGIA Article 9.7.4.1 is changed to 
``System Protection Facilities.'' This change addresses the NERC 
comment to eliminate reference to ``System Quality.''
    570. Article 9.7.4.2--Proposed LGIA Article 9.7.4.2 would have 
required that

[[Page 49893]]

each Party's facility be designed to isolate any fault or abnormality 
that would negatively affect the other Party or third parties connected 
to the Transmission Provider's Transmission System.
Comments
    571. NERC notes that the term ``negatively affect'' is too vague. 
It proposes that proposed LGIA Article 9.7.4.2 be revised to state that 
each Party's protection facilities will be designed and coordinated 
with other systems in accordance with Good Utility Practice.
Commission Conclusion
    572. The Commission adopts NERC's proposed change.
    573. Article 9.7.5--Requirements for Protection--Proposed LGIA 
Article 9.7.5 would have required the Interconnection Customer, in 
compliance with Applicable Reliability Standards, to install, operate 
and maintain protective devices necessary to remove faults ``promptly'' 
and to protect the Generating Facility from other conditions, such as 
negative sequence currents and over- or under-frequency.
Comments
    574. NERC comments that the term ``promptly'' is not useful when 
describing requirements for, or actions taken to preserve, system 
reliability. It also notes that the Generating Facility's fault 
protection must be coordinated with system protection. ``Good Utility 
Practice'' should replace ``Applicable Reliability Standards,'' since 
Applicable Reliability Standards is a subset of Good Utility Practice.
Commission Conclusion
    575. The Commission agrees with NERC and adopts its proposals.
    576. Article 9.9--Use of Transmission Provider's Interconnection 
Facilities by Third Parties--Proposed LGIA Article 9.9 would have 
provided, among other things, that third parties may use the 
Transmission Provider's Interconnection Facilities if required by 
Applicable Laws and Regulations, or if the Parties agree.
Comments
    577. APS believes that it is inappropriate to prohibit the use of 
Interconnection Facilities for other functions such as the housing of 
fiber optic circuits.
Commission Conclusion
    578. Since proposed LGIA Article 9.9 specifically allows the 
Parties to agree to permit third party usage of the Interconnection 
Facilities, there is no need to revise it.
    579. Article 9.10--Disturbance Analysis Data Exchange (In the NOPR: 
Data Exchange)--Proposed LGIA Article 9.10 would have provided that the 
Parties cooperate with one another in the analysis of disturbances to 
either the Generating Facility or the Transmission Provider's 
Transmission System by the gathering and sharing of any information 
related to any disturbance.
Comments
    580. NERC states that since this article is limited to data 
exchange for disturbance analysis, the title should be ``Disturbance 
Analysis Data Exchange.'' NERC also recommends covering ``and any 
disturbance information required by Good Utility Practice.''
Commission Conclusion
    581. The Commission adopts NERC's proposals in the Final Rule.
    582. Article 10--Maintenance--Proposed LGIA Article 10 would have 
made the Interconnection Customer responsible for all reasonable 
expenses of owning, operating and maintaining Interconnection Customer 
and Transmission Provider Interconnection Facilities (except for 
operations and maintenance expenses associated with modifications 
necessary for providing service to a third party that pays for such 
expenses). No significant comments were submitted on this article. 
Accordingly, the Commission adopts in the Final Rule LGIA Article 10 as 
proposed.
    583. Article 11--Performance Obligation--Proposed LGIA Article 11 
described the Transmission Provider's and the Interconnection 
Customer's obligations with respect to construction of Interconnection 
Facilities and Network Upgrades, security arrangements and deposits, 
refunds in the form of transmission credits with interest for amounts 
funded by the Interconnection Customer, and compensation to the 
Interconnection Customer for services the Transmission Provider 
requests.
    584. Most of the issues in Proposed LGIA Article 11 relate to 
pricing. All pricing matters are discussed in part II.C.1 
(Interconnection Pricing Policy).
    585. Article 11.5--Financial Security Arrangements--Proposed LGIA 
Article 11.5 would have required the Interconnection Customer to 
provide the Transmission Provider with a form of security at least 90 
Calendar Days before the procurement, installation, or construction of 
discrete Transmission Provider Interconnection Facilities or Network 
Upgrades begins. The security amount would have had to be sufficient to 
cover the costs of procuring, constructing, and installing the 
Transmission Provider's Interconnection Facilities or Network Upgrades, 
and it would have been reduced on a dollar-for-dollar basis as payments 
were made. Articles 11.5.1.1, 11.5.1.2 and 11.5.1.3 would have required 
that the issuer of the guarantee, letter of credit, surety bond or 
other form of security meet the creditworthiness requirements of, or be 
acceptable to, the Transmission Provider and that the security 
instrument contain specified provisions, such as a reasonable 
expiration date.\89\
---------------------------------------------------------------------------

    \89\ NOPR LGIA Article 11.5.1 is identical to Article 11.5 
except that the former required the Interconnection Customer to 
provide the Transmission Provider with a form of security at least 
30 Calendar Days prior to the commencement of the procurement, 
installation, or construction of discrete Transmission Provider 
Interconnection Facilities or Network Upgrades. The inclusion of 
both provisions in the NOPR LGIA was an error. As explained below, 
we are eliminating Article 11.5 in the Final Rule LGIA.
---------------------------------------------------------------------------

Comments
    586. Commenters identify three areas of concern with this 
provision. First, some commenters believe that 30 days is insufficient 
time for the Interconnection Customer to provide a reasonable form of 
security to the Transmission Provider. For example, Dairyland Power 
argues that 30 days is not enough time for delivery of the necessary 
equipment and materials. SoCal PPA maintains that the security should 
be provided 90 days in advance. Progress Energy argues that security 
should be provided when an interconnection agreement is executed, and 
FP&L requests that security should be provided within 30 days of either 
execution of the interconnection agreement or its acceptance by the 
Commission.
    587. Exelon argues that the amount of the security should be 
allowed to increase (or decrease), based on any changes in the 
construction cost estimate. According to Progress Energy, the 
Interconnection Customer should offer security to cover the full cost 
of the Network Upgrades. EPSA contends that the Interconnection 
Customer should be allowed to provide security on a rolling six month 
basis based on the Transmission Provider's cost exposure at each six 
month interval to ensure that the security costs paid by the 
Interconnection Customer are reasonable at any given time and are 
consistent with the Transmission Provider's obligations. In the 
alternative, EPSA supports the 30 day period. Duke

[[Page 49894]]

Energy also supports the 30 day requirement.
    588. NMA and Peabody state that while a Transmission Provider 
should not be placed at risk financially if an Interconnection Customer 
either terminates its interconnection agreement or breaches its 
obligation to make monthly payments to the Transmission Provider, at no 
time will the Transmission Provider be exposed to the financial costs 
of all the amounts of Network Upgrades or additions as contemplated 
under the NOPR LGIA. Requiring an Interconnection Customer to guarantee 
the total cost of the Network Upgrades is unfair because it causes the 
Interconnection Customer seeking to interconnect a very large generator 
to incur significant interest costs that it will never be able to 
recover, and this does not represent the true financial exposure the 
Transmission Provider faces for Network Upgrades. Further, limiting the 
security requirement to an amount that reflects the Transmission 
Provider's cost exposure during a 120 day forward-looking period is 
more appropriate than requiring an Interconnection Customer with a very 
large generator to provide security for the total cost of the project. 
Calpine warns that unnecessary financial security would be a barrier to 
entry.
    589. Several commenters, mostly Transmission Providers, believe 
that the Transmission Provider or Transmission Owner should determine 
the form of security to be provided by the Interconnection 
Customer,\90\ since they bear the risk if an Interconnection Customer 
abandons a project. The Financial Security Issues Coalition argues that 
the specific reference to surety bonds should be deleted from proposed 
LGIA Article 11.5 because surety bonds are not in the OATT as an 
acceptable form of collateral. Also, to reduce bankruptcy and 
fraudulent conveyance issues, any proposed guaranty should be from a 
parent, and not merely an Affiliate, of the Interconnection Customer. 
Finally, any proposed guarantor should have a BBB+ bond rating or 
higher.
---------------------------------------------------------------------------

    \90\ E.g., BPA, Central Maine, Duke Energy, Exelon, the 
Financial Security Issues Coalition, Georgia Transmission, NSTAR, 
and NYTO.
---------------------------------------------------------------------------

    590. Sempra argues that proposed LGIA Article 11.5.1 should be 
revised to clarify that the decision whether to provide security is the 
option of the Interconnection Customer. The provision should require an 
Interconnection Customer to provide a substitute security if it suffers 
serious financial erosion and financial-ratings downgrades that could 
lead the Transmission Provider to require assurances of a guarantor's 
ability to perform its financial and performance obligations. Dominion 
Resources does not object to the NOPR provision, provided that a 
subsequent Interconnection Customer is responsible for the costs of 
completing Network Upgrades if a higher-queued Interconnection Customer 
chooses to suspend or terminate construction of the Interconnection 
Facilities.
    591. Arkansas Coops argue that Article 11.5.1 should require the 
Transmission Provider to accept security from the National Rural 
Utilities Cooperative Finance Corporation (CFC), since this is critical 
for cooperatives that obtain financing from the CFR.
Commission Conclusion
    592. We note at the outset that Article 11.5 and Article 11.5.1 are 
substantially identical, and the inclusion of both provisions in the 
NOPR was redundant. We are therefore deleting Article 11.5 in the Final 
Rule, and renumbering the remaining articles accordingly. The 
discussion that follows, however, will refer to article numbers 
contained in the NOPR LGIA.
    593. With respect to commenters' concern that the 30 day window for 
providing a reasonable form of security is too short, the NOPR stated 
that the form of security must be provided by the Interconnection 
Customer at least 30 Calendar Days in advance of the procurement, 
installation, or construction of Interconnection Facilities or Network 
Upgrade projects. Parties, therefore, remain free to agree to an 
earlier deadline for the security if they foresee circumstances such as 
a long lead time for delivery of equipment. We expect that an 
Interconnection Customer will honor a reasonable request for an earlier 
deadline for providing a reasonable form of security. And, we will not 
require that the security be available at an earlier time, or at some 
specified period after execution of an interconnection agreement, 
because the purpose of the security is to fund procurement and 
construction. Since it is uncertain when procurement and construction 
will begin, it is reasonable to make such activity the trigger for 
tendering the security.
    594. We are not persuaded that providing security on a 120 day or 
six month rolling basis is superior to the approach proposed in the 
NOPR. We retain the article as proposed for the following reasons. 
First, the Final Rule LGIA provides for the reduction of the security 
amount on a dollar-for-dollar basis as payments are made; this protects 
the Interconnection Customer against providing too much security and 
ensures that the Transmission Provider is always adequately protected 
against its cost exposure. Second, commenters provide inadequate 
support for their claim that they would be unduly burdened if the 
article remained unchanged, or that a Transmission Provider and its 
other customers would suffer no financial harm if the Commission 
adopted a rolling 120 Calendar Days or six month security period. 
Third, retaining the proposed language will help to ensure that only a 
financially sound generation project will advance to the point where a 
Transmission Provider must make an irreversible financial commitment on 
its behalf. Fourth, the approach proposed by the commenters could 
expose a Transmission Provider and its other customers to financial 
risk if the Interconnection Customer defaults before the construction 
of new facilities and Network Upgrades have advanced to the point where 
those facilities can be put to productive use.
    595. In response to Exelon's concern that the amount of security be 
permitted to increase as well as decrease, Final Rule Article 11.5 does 
not prohibit the Parties from increasing the total amount of security 
required under an executed LGIA. The prices quoted for interconnection 
in the LGIA are estimates based on the results of studies conducted 
during the LGIP phase of the interconnection process. As a result, the 
final cost of Network Upgrades may rise or fall and with it, the 
security required under the LGIA.
    596. We disagree with commenters' contention that the article 
requires the Interconnection Customer to guarantee the total cost of 
the Network Upgrades. Final Rule Article 11.5 requires the 
Interconnection Customer to provide security to the Transmission 
Provider for discrete portions of the Transmission Provider's 
Interconnection Facilities or Network Upgrades, not the total amount of 
the Network Upgrades. It also provides that the security amount is 
reduced on a dollar-for-dollar basis for payments made to the 
Transmission Provider, thereby protecting the Interconnection Customer 
from having to provide too much security.
    597. With respect to commenters' arguments as to the form of 
security, the Final Rule states that the Interconnection Customer has 
the right to select a form of security that is acceptable to the 
Transmission Provider and that the Transmission Provider cannot 
unreasonably refuse to accept a


[[Continued on page 49895]]


From the Federal Register Online via GPO Access [wais.access.gpo.gov]
]                         
 
[[pp. 49895-49944]] Standardization of Generator Interconnection Agreements and 
Procedures

[[Continued from page 49894]]

[[Page 49895]]

particular form. As the Commission has noted in recent orders, allowing 
the Interconnection Customer to provide an ``irrevocable letter of 
credit * * * or an alternative form of security proposed by the 
Transmission Customer and acceptable to the Transmission Provider and 
consistent with commercial practices'' is not unreasonable, and no 
commenter has convinced us otherwise.\91\ Granting the Transmission 
Provider absolute discretion on what forms of security to allow would 
provide too great an opportunity to erect hurdles to new generation, by 
allowing it to act in an unduly discriminatory or preferential 
manner.\92\ Moreover, Final Rule Article 11.5 grants the Transmission 
Provider the discretion to reject security from a financial institution 
that is not reasonably acceptable. As a result, the Commission rejects 
comments that would grant the Transmission Provider greater discretion 
with respect to the Interconnection Customer's chosen security or 
eliminate forms of credit specified in the article.
---------------------------------------------------------------------------

    \91\ See Florida Power & Light Company, 98 FERC ] 61,226 at 
61,893-94, reh'g granted in part on other grounds, 99 FERC ] 61,318 
(2002); Florida Power & Light Company, 98 FERC ] 61,324 at 62,358-59 
(noting that Florida Power & Light Company's practice of limiting 
interconnection customers to a letter of credit is unreasonable), 
reh'g rejected as moot, 100 FERC ] 61,094 (2002).
    \92\ Southwest Power Pool, Inc., 100 FERC ] 61,096 at P 12 
(2002).
---------------------------------------------------------------------------

    598. In response to Sempra, Final Rule Article 11.5 clearly states 
that the Interconnection Customer ``shall provide'' security to the 
Transmission Provider. It is only the form of that security that is the 
Interconnection Customer's option, within the restrictions specified. 
We are not adding language to the provision to establish requirements 
if an Interconnection Customer receives a financial downgrade that 
makes it difficult to secure a guaranty. The Interconnection Customer 
remains responsible for providing an acceptable form of guaranty under 
the existing terms of the article.
    599. Regarding Dominion Resources' comment, this issue is addressed 
in our discussion of Article 5.13 (Suspension).
    600. Regarding the Arkansas Coops' concern that a Transmission 
Provider would not accept security from the CFC, we would not consider 
such a rejection to be a reasonable decision on the part of the 
Transmission Provider under the existing terms of Article 11.5. 
Accordingly, we are not revising the provision.
    601. Article 12--Invoice--Proposed LGIA Article 12 set out a 
monthly invoice and billing dispute procedure. The Transmission 
Provider would have been required to provide an invoice for the final 
cost of construction of the Transmission Provider's Interconnection 
Facilities and Network Upgrades within six months, in sufficient detail 
to enable the Interconnection Customer to compare actual costs with 
estimates. No significant comments were submitted on this article. 
Accordingly, the Commission adopts in the Final Rule LGIA Article 12 as 
proposed.
    602. Article 13--Emergencies--Proposed LGIA Article 13 explained 
the Transmission Provider's and the Interconnection Customer's 
responsibilities when Emergency Conditions arise.
    603. Article 13.1--Definition--Proposed LGIA Article 13.1 would 
define Emergency Condition as a condition or situation: (1) That in the 
judgment of the Party making the claim is imminently likely to endanger 
life or property, or (2) that, in the case of the Transmission Provider 
making the claim, is imminently likely (as determined in a non-
discriminatory manner) to cause a material adverse effect on the 
security of, or damage to the Transmission System, the Transmission 
Provider Interconnection Facilities, or the Transmission Systems of 
others to which the Transmission System is directly connected, or (3) 
that, in the case of the Interconnection Customer making the claim, is 
imminently likely (as determined in a non-discriminatory manner) to 
cause a material adverse effect on the security of, or damage to, the 
Generating Facility or its Interconnection Facilities. Any condition or 
situation that results from a lack of sufficient generating capacity to 
meet load requirements and that results solely from economic conditions 
would not, on its own, be an Emergency Condition.
Comments
    604. PG&E and Cal ISO believe that lack of sufficient generation to 
meet load requirements that results solely from economic conditions can 
be a genuine Emergency Condition. PG&E states that when insufficient 
generation occurs, regardless of the reason, the Transmission Provider 
is still responsible for maintaining system stability to the extent 
possible. It believes that taking away the tools necessary in such an 
emergency could harm the Transmission System. Cal ISO and Salt River 
Project make a similar point; they consider lack of generation, for any 
reason, to be an Emergency Condition that can endanger reliability and, 
at a minimum, warrants an emergency notification such as those provided 
for under the Cal ISO's procedures. According to Cal ISO, without a 
declaration of an Emergency Condition, the Transmission Provider will 
not be able to invoke its obligation under Article 13.5 of the NOPR 
LGIA to take actions necessary to preserve reliability.
    605. El Paso seeks to revise both the proposed definition of the 
term Emergency Conditions and NOPR LGIA Article 13 to include a 
definition of an abnormal condition and to provide the Transmission 
Provider and Interconnection Customer the discretion to prevent an 
Emergency Condition (by taking action or inaction) during an abnormal 
condition.\93\ El Paso notes that such action or inaction would require 
prompt oral notification to the other Party as well as compensation for 
changes in real power output and reactive power production.
---------------------------------------------------------------------------

    \93\ El Paso would define Abnormal Condition as ``any condition 
at the [Generating] Facility, on the Interconnection Facilities, on 
the Transmission System, or on the transmission system of other 
utilities which is outside normal operating parameters such that 
facilities are operating outside their normal ratings or reasonable 
operating limits have been exceeded and would result in an Emergency 
Condition if these conditions continue. Any condition or situation 
that results from lack of sufficient planned generating capacity to 
meet load requirements or that results solely from economic 
conditions will not, standing alone, constitute an Abnormal 
Condition.''
---------------------------------------------------------------------------

Commission Conclusion
    606. The Commission agrees with the comments concerning the 
potential harm to the Transmission Provider's Transmission System by 
reducing its flexibility to respond during Emergency Conditions. The 
Commission is removing from the Final Rule LGIA Article 13.1 definition 
of Emergency Condition the sentence that reads, ``Any condition or 
situation that results from a lack of sufficient generating capacity to 
meet load requirements that results solely from economic conditions 
shall not, on its own, constitute an Emergency Condition.'' The 
Commission denies El Paso's request to add a definition of an abnormal 
condition and to provide the Transmission Provider and Interconnection 
Customer the discretion to take certain actions or inactions in the 
event of an Emergency Condition. The Commission would expect the 
Parties to treat any abnormal conditions appropriately, regardless of 
whether it is a defined term in the Final Rule.
    607. Article 13.5.1--Transmission Provider Authority--General--
Proposed LGIA Article 13.5.1 provided that the

[[Page 49896]]

Transmission Provider would be able to take whatever actions or 
inactions it deems necessary during an Emergency Condition to preserve 
the safety and reliability of the Transmission System or the 
Transmission Provider Interconnection Facilities.
Comments
    608. Dynegy contends that during an Emergency Condition, the 
Transmission Provider should compensate the Interconnection Customer 
for starting up or shutting down a Generating Facility or increasing or 
decreasing its real or reactive output.
Commission Conclusion
    609. Compensation during an Emergency Condition is appropriately 
addressed in Final Rule LGIA Article 11.6.1 (Generator Compensation for 
Actions During Emergency Conditions).
    610. Article 13.6--Interconnection Customer Authority--Proposed 
LGIA Article 13.6 would allow the Interconnection Customer to take 
actions or inactions necessary to protect the integrity of its 
Generating Facility or Interconnection Facilities during an Emergency 
Condition.
Comments
    611. NERC proposes that Article 13.6 be revised to read as follows: 
``Consistent with Good Utility Practice and the [LG]IA and [LG]IP, the 
Interconnection Customer may take actions or inactions with regard to 
the [Generating] Facility or the [Interconnection Customer's] 
Interconnection Facilities during an Emergency Condition in order to 
(1) preserve public health and safety, (2) preserve the reliability of 
the [Generating] Facility or the [Interconnection Customer's] 
Interconnection Facilities, (3) limit or prevent damage, and (4) 
expedite restoration of service.'' Central Maine requests that proposed 
LGIA Article 13.6 be revised to require that an Interconnection 
Customer exercise its rights in an Emergency Condition in accordance 
with Good Utility Practice.
Commission Conclusion
    612. We adopt NERC's proposed language in Final Rule Article 13.6 
because it provides greater specificity concerning the Interconnection 
Customer actions or inactions that may be taken during the course of an 
Emergency Condition.
    613. Article 14--Regulatory Requirements and Governing Law--
Proposed LGIA Article 14 described the regulatory requirements and 
governing law for each Party's obligations under the LGIA.
    614. Article 14.1--Regulatory Requirements & Article 14.2--
Governing Law and Applicable Tariffs--Article 14.1 of the NOPR LGIA 
proposed that each Party's obligations shall be subject to its receipt 
of any required approval or certificate from Governmental Authorities 
in a form and substance satisfactory to the applying Party, or the 
Party making any required filings with, or providing notice to, such 
Governmental Authorities. Article 14.1 also stated that nothing in the 
LGIA shall require an Interconnection Customer to take any action that 
could result in its inability to obtain, or its loss of, status or 
exemption under the Federal Power Act or the Public Utility Holding 
Company Act of 1935, as amended. Article 14.2 of the NOPR LGIA provided 
that the LGIA is governed by the laws of the state where the Point of 
Interconnection is located, without regard to conflicts of state law 
principles, and that the LGIA is subject to all Applicable Laws and 
Regulations.
Comments
    615. The Bureau of Reclamation states that it does not have 
investors or shareholders, is not subject to the Commission's 
jurisdiction under sections 205 or 206 of the Federal Power Act, and is 
not subject to the jurisdiction of state public utility commissions. 
The Bureau of Reclamation has sovereign immunity except to the extent 
that immunity has been waived by Congress. It believes that proposed 
LGIA Article 14.2 does not reflect that, as a federal agency, it must 
comply with the Constitution of the United States and all applicable 
laws. It states that this includes statutory and regulatory limitations 
on its ability to submit disputes to arbitration. SoCal PPA requests 
that Parties have the option of selecting the laws of a state other 
than the state where the interconnection will occur as the governing 
law for the LGIA.
Commission Conclusion
    616. The Bureau of Reclamation and SoCal PPA argue that public 
power entities cannot adopt Article 14 without variation. We will not 
require these entities to adopt provisions that they are legally 
forbidden to adopt in order to have their reciprocity tariffs approved. 
As described more fully in the reciprocity discussion,\94\ 
nonjurisdictional entities with safe harbor status for their tariffs 
may add the Final Rule LGIP and Final Rule LGIA if they wish to 
continue to have safe harbor protection, but only need to provide 
services they are ``capable'' of providing.\95\ We will consider the 
legal restrictions on nonjurisdictional entities when we evaluate their 
reciprocity compliance filings.
---------------------------------------------------------------------------

    \94\ See Part II.C.7 (OATT Reciprocity Requirements Applied to 
the Final Rule LGIP and Final Rule LGIA).
    \95\ Order No. 888-A, FERC Stats. & Regs ] 31,048 at 30,286.
---------------------------------------------------------------------------

    617. Article 15--Notices--Proposed LGIA Article 15 contained the 
addresses at which the Transmission Provider and Interconnection 
Customer will receive, among other things, notices, bills and payments. 
No significant comments were submitted on this article. Accordingly, 
the Commission adopts this article in the Final Rule as proposed.
    618. Article 16--Force Majeure--A Force Majeure clause excuses 
performance under a contract due to an event beyond a Party's control. 
Article 16 of the NOPR LGIA proposed to adopt the Force Majeure 
language of the OATT. It defined Force Majeure events as: ``[A]ny act 
of God, labor disturbance, act of the public enemy, war, insurrection, 
riot, fire, storm, or flood, explosion, breakage or accident to 
machinery or equipment, any curtailment order, regulation or 
restriction imposed by governmental military or lawfully established 
civilian authorities, or any other cause beyond a Party's control * * 
*.'' The NOPR provision would have required the Parties ``to make all 
Reasonable Efforts'' to comply with their obligations and resolve the 
Force Majeure condition.
Comments
    619. Several commenters ask that the Commission establish a list of 
non-Force Majeure events.\96\ More specifically, some commenters 
believe that Article 16 should exclude economic hardship from the 
definition of Force Majeure,\97\ while the Coalition for Contract Terms 
and PSEG comment that the Commission should not treat ``removable or 
remediable causes'' as Force Majeure.
---------------------------------------------------------------------------

    \96\ E.g., The Coalition for Contract Terms, Monongahela Power, 
PJMTO, and PSEG.
    \97\ E.g., The Coalition for Contract Terms, Entergy, Mirant, 
PJMTO, and PSEG.
---------------------------------------------------------------------------

    620. Some commenters request that the Commission establish a formal 
notice requirement that Parties must follow when claiming Force 
Majeure.\98\ NYTO asks the Commission to require the Party claiming 
Force Majeure to notify those affected of what steps the

[[Page 49897]]

Party is taking to remedy the Force Majeure condition. Dominion 
Resources and Progress Energy request that the Commission clarify the 
obligations and responsibilities of each Party during a Force Majeure 
occurrence. Specifically, they ask the Commission to clarify how a 
Party invokes the Force Majeure provision.
---------------------------------------------------------------------------

    \98\ E.g., The Coalition for Contract Terms, Dominion Resources, 
Mirant, Monongahela Power, and Progress Energy.
---------------------------------------------------------------------------

    621. A number of commenters ask the Commission to clarify that the 
Party claiming Force Majeure must return to complying with the LGIA as 
soon as the Force Majeure event ends and that the other Party's 
obligation to pay for services rendered is not suspended during the 
Force Majeure event.\99\
---------------------------------------------------------------------------

    \99\ E.g., The Coalition for Contract Terms, Exelon, PSEG, and 
PJMTO.
---------------------------------------------------------------------------

    622. PacifiCorp argues that the Force Majeure clause should cover 
acts of negligence or intentional wrongdoing by someone other than the 
claimant, while MidAmerican requests the opposite. Cinergy comments 
that the NOPR does not define curtailment, and is concerned that this 
term might unnecessarily broaden the definition of Force Majeure.
Commission Conclusion
    623. We agree that the contracting Parties would benefit from 
greater specificity in the Force Majeure provision, so the Final Rule 
LGIA sets forth the procedural obligations and responsibilities of the 
Parties during a Force Majeure event. We adopt a requirement that the 
Party experiencing a Force Majeure event formally notify the other 
Party and that it keep the other Party informed about its attempt to 
remedy the situation. A Party shall exercise due diligence to remove 
the disability with reasonable dispatch, and it will resume its duties 
under the LGIA as soon as reasonably possible. For instance, a fire 
that triggers a Force Majeure claim may be put out within hours, but it 
may take the Party days or weeks to resume normal operation. The Party 
would not be in Default of its obligations during that time. The Final 
rule article also clarifies that the obligation to pay money when due 
is not suspended by reason of Force Majeure.
    624. We agree that it would be useful to identify economic hardship 
as a non-Force Majeure event. Economic hardship is not considered an 
event outside the control of the Party. However, it is unnecessary to 
specify that a ``removable or remediable'' cause does not qualify as 
Force Majeure event. Final Rule Article 16 defines a Force Majeure 
event as one that is ``beyond a Party's control.''
    625. NOPR Article 16.1 proposed to except from the list of Force 
Majeure events acts of ``negligence or intentional wrongdoing.'' We 
clarify in the Final Rule LGIA that acts of negligence or intentional 
wrongdoing committed by an entity other than the Party claiming Force 
Majeure would qualify for Force Majeure protection. This is an event 
beyond a Party's reasonable control.
    626. With respect to Cinergy's comments regarding use of the term 
``curtailment,'' we conclude that while the curtailments imposed by 
governmental military or lawfully established civilian authorities are 
considered Force Majeure events under Section 10.1 of the OATT, it is 
an inappropriate Force Majeure event in the Final Rule LGIA. 
Curtailments to transmission service should not serve as the cause for 
excusing performance under an interconnection contract. As a result, 
the Commission omits curtailment from the definition of Force Majeure 
in the Final Rule LGIA.
    627. Article 17--Default--Proposed LGIA Article 17 defined Default 
as the failure of either Party to perform any obligation in the time or 
manner provided in this LGIA. No Default would exist as a result of 
Force Majeure or an act or omission of the other Party. Article 17 also 
described notice and cure procedures: the defaulting Party would have 
30 Calendar Days from receipt of a Default notice to cure the Default; 
or, if the Default cannot be cured within 30 Calendar Days, the 
defaulting Party must begin the cure within 30 Calendar Days and must 
complete the cure within 90 Calendar Days. NOPR Article 17.1.2 provided 
the non-defaulting Party with the right to terminate the LGIA and 
recover damages if a Default is not cured, or is not capable of being 
cured, within the time provided in Article 17.1.1.
Comments
    628. Calpine is concerned that not all Defaults are capable of 
being cured within 90 Calendar Days, especially if they involve the 
purchase, modification or installation of equipment. It therefore 
argues that it is sufficient to require that the cure begin in 30 
Calendar Days, and that the defaulting Party ``continuously and 
diligently complete such cure,'' as required under Article 17.1.1.
Commission Conclusion
    629. The Commission declines to adopt Calpine's proposed change. 
The non-defaulting Party needs to be protected from lengthy Defaults by 
having the right to terminate, even if the Default cannot be cured 
within 90 Calendar Days through diligent action by the defaulting 
Party. The LGIA does not prevent the Parties from agreeing to an 
extension of the time permitted to cure a Default. Calpine's proposal 
would provide the non-defaulting Party with too little protection.
    630. Article 18--Indemnity--Indemnification is defined as 
compensating another for a loss suffered due to a third party's act or 
Default.\100\ In the NOPR, we proposed that the LGIA incorporate the 
indemnity provision currently found in the OATT. Thus, the 
indemnification provision in NOPR LGIA Section 18.1 would indemnify the 
Transmission Provider and Interconnection Customer for legal costs due 
to claims by third persons arising from performance of the Transmission 
Provider's or Interconnection Customer's obligations under the LGIA on 
behalf of the other contracting Party, and would not explicitly allow 
indemnification for disputes arising over enforcement of this 
provision. The Commission sought comments on this approach and the 
relative merits of the alternative provisions in the Consensus LGIA and 
ERCOT interconnection agreement. The Consensus LGIA does not extend 
indemnity protection to cases of ordinary negligence or willful 
misconduct, and the ERCOT provision does not extend indemnity 
protection to cases of gross negligence or intentional wrongdoing. 
Additionally, the Consensus LGIA, unlike the ERCOT interconnection 
agreement, sets forth detailed procedures for pursuing an indemnity 
claim and makes the recovery of legal costs available as part of an 
indemnity claim.
---------------------------------------------------------------------------

    \100\ Black's Law Dictionary 772 (7th ed. 1999).
---------------------------------------------------------------------------

Comments
    631. Commenters generally support the inclusion of an 
indemnification provision, but ask that the Final Rule cover other 
charges, such as attorneys' fees, and explain the process for invoking 
this protection.\101\ Several commenters, including Duke Energy, 
Monongahela Power, PacifiCorp, and Sempra, point out a typographical 
error that would have excepted negligence or intentional wrongdoing by 
the indemnifying Party rather than the indemnified Party. Some 
commenters recommend extending the protection to ordinary negligence by 
the Transmission Provider, but denying

[[Page 49898]]

protection for gross negligence.\102\ NYTO and Cinergy request that the 
provision cover an Interconnection Customer's performance of 
construction activities. PSEG requests that the provision be revised to 
offer specific limitations on the damages provision and a provision 
limiting liability arising from an emergency. El Paso requests that the 
Final rule specifically indemnify the Transmission Provider from 
penalties incurred due to the actions or inactions of the 
Interconnection Customer.
---------------------------------------------------------------------------

    \101\ E.g., Central Maine, Dominion Resources, Exelon, 
Monongahela Power, NYTO, and Progress Energy.
    \102\ E.g., Central Maine, the Coalition for Contract Terms, 
Midwest ISO TO, PSEG, Salt River Project, and Southern.
---------------------------------------------------------------------------

    632. PJMTO argues that the OATT provision does not contain enough 
specific provisions and inadequately constrains the potential financial 
risk to each Party. Specifically, it argues that the provision should 
limit damages and set forth the proper standard for assessing liability 
(i.e., gross negligence and willful misconduct). It also expresses 
concern that lending institutions would shy away from investing in new 
generation without liability limits.
    633. Southern proposes to require that each Party indemnify and 
hold the other Party harmless from any liability resulting from 
activities on the indemnifying Party's own side of the Point of Change 
of Ownership, except in cases of gross negligence or intentional 
misconduct. Each Party should also indemnify the other Party for 
failure to adhere to operating requirements and Breaches of the LGIA. 
SoCal PPA notes that it applies a more stringent ``willful action'' 
standard. It warns that if the Commission retains the proposed 
standard, a Transmission Owner will have to procure insurance to cover 
this exposure, for which the Interconnection Customer should pay.
    634. NYTO takes issue with the provision's bilateral effect, 
arguing that a Transmission Owner should not have to indemnify an 
Interconnection Customer, since the Interconnection Customer requests 
interconnection for its own benefit. Similarly, NYISO argues that the 
provision should protect the active Parties to an agreement, here the 
Transmission Owner or ISO, but not the Interconnection Customer.
    635. Salt River Project notes that it is unclear whether the 
Commission intends to preempt the appropriate tribunal's consideration 
of whether liability should attach for injuries to third parties.\103\ 
It also argues that compliance with an Interconnection Customer's 
request should not be required if it will result in violation of 
statutory restrictions, bond covenants, creditor agreements or private 
use restrictions.
---------------------------------------------------------------------------

    \103\ Citing Avista Corp., 96 FERC ] 61,058 at 61,181 (2002).
---------------------------------------------------------------------------

Commission Conclusion
    636. We are amending the proposed indemnity standard to match the 
customary legal standard of conduct and better address the potential 
for liability. Because risk exposure can increase interconnection 
costs, we are revising the indemnity standard to provide protection for 
acts of ordinary negligence, but not for acts of gross negligence or 
intentional wrongdoing. Similarly, commenters have convinced us that 
interconnection presents a greater risk of liability than exists for 
the provision of transmission service and that, therefore, the OATT 
indemnity provision is not suitable in the interconnection context. 
While several commenters request a dollar limit on liability, we 
conclude that the tightened standards serve as an acceptable limit on 
liability and that a monetary limitation on damages is not necessary to 
adequately protect the Parties.
    637. Because construction of Interconnection Facilities may expose 
both a Transmission Provider and an Interconnection Customer to 
liability for acts taken on the other Party's behalf, we are retaining 
the bilateral nature of the provision. In response to the concern of 
some commenters, the indemnity provision of the Final Rule also 
describes the process for pursuing and securing indemnity from claims 
in more detail. Additionally, the Final Rule LGIA gives an indemnified 
Party the right to collect the legal costs of defending an 
indemnification claim if the indemnifying Party fails to adequately 
defend the claim on its own. We also adopt El Paso's proposal that 
indemnification be available because of action or inaction by the 
Interconnection Customer, and modify the provision accordingly.
    638. In response to NYTO's request that the provision cover an 
Interconnection Customer's construction activities, the Final Rule 
provision covers construction activities as well as all other 
activities performed on behalf of the other Party. Where an 
Interconnection Customer constructs the Transmission Provider's 
Interconnection Facilities and Stand Alone Network Upgrades under the 
Option to Build in Final Rule LGIA Article 5.1, a Transmission Provider 
will be protected by the indemnification clause that appears in that 
article. Indemnification applies to all work, regardless of the side of 
the Point of Interconnection on which the work occurs.
    639. With regard to cost allocation, we clarify that each Party is 
responsible for paying its own insurance. This is equitable and helps 
keep the costs of interconnection low, which should encourage the 
construction of new generation resources. Additionally, we are 
eliminating indemnification for gross negligence or intentional 
wrongdoing, which will also reduce the Parties' risk exposure and cost 
of insurance.
    640. It is not our intent to preempt the ``appropriate tribunal's'' 
assignment of liability for injuries to third parties, as proposed by 
Salt River Project. The indemnification provision is a common 
contractual risk-sharing provision and does not strip any court or 
other tribunal of jurisdiction. To the extent that this provision would 
cause a specific Transmission Provider to violate statutory or other 
restrictions, the issue should be raised on compliance in a filing 
explaining the special circumstances.
    641. Article 19--Assignment--Proposed LGIA Article 19 provided the 
conditions for assigning the LGIA to another entity. It stated that any 
assignment under the LGIA shall not relieve a Party of its obligations, 
nor shall a Party's obligations be expanded.
    642. Article 19.1--Assignment--Article 19.1 of the NOPR LGIA stated 
that written consent ordinarily would be required to assign the LGIA, 
but assignment may be secured without consent if the assignee is an 
Affiliate that meets certain qualifications. Article 19 also provided 
that no consent would be required if an Interconnection Customer 
assigns the LGIA for collateral security purposes to aid in financing.
Comments
    643. The Bureau of Reclamation argues that there are limitations on 
its ability to comply with Article 19.1. It does not typically allow 
assignments without approval by both entities and assurance that 
assigns and successors are bound by the original terms of the 
interconnection agreement. It states that there are standard articles 
that it would be required to include that are not contained in the 
NOPR, such as ``Officials Not to Benefit,'' ``Use of Convict Labor,'' 
``Prompt Payment Provisions,'' and ``Tort Claims.''
Commission Conclusion
    644. The Bureau of Reclamation's concerns are addressed in the 
reciprocity discussion at Article 14.1 (Regulatory Requirements) and 
Article

[[Page 49899]]

14.2 (Governing Law and Applicable Tariffs).
    645. Article 20--Severability--Article 20 of the NOPR LGIA 
explained that if a court or Governmental Authority determines that any 
provision of the LGIA is invalid, void, or unenforceable, such 
determination would not invalidate any other provision in the LGIA. No 
significant comments were submitted on this article. Accordingly, the 
Commission adopts this article in the Final Rule LGIA as proposed.
    646. Article 21--Comparability--Article 21 of the NOPR LGIA would 
have required that the Parties comply with all applicable comparability 
requirements and code of conduct laws, rules and regulations. No 
significant comments were submitted on this article. Accordingly, the 
Commission adopts this article in the Final Rule LGIA as proposed.
    647. Article 22--Confidentiality--Article 22 of the NOPR LGIA 
described what constitutes Confidential Information and the protection 
proposed for such information when shared between Parties. It set forth 
proposed procedures for the release of Confidential Information and 
guidelines regarding how Confidential Information should be treated 
when it is subject to a request from the Commission as part of an 
investigation. The information of both Parties is protected by this 
article as long as the information is identified as Confidential 
Information in accordance with the article.
Comments
    648. Cal ISO argues that an RTO or ISO should have access to 
operational, performance and maintenance data.
    649. The Bureau of Reclamation argues that it may not be able to 
conform to the proposed confidentiality provisions because it must 
adhere to the Freedom of Information Act (FOIA) \104\ when addressing 
confidentiality. It further explains that FOIA requires federal 
agencies to release most documents in their possession upon request, 
except to the extent their contents meet certain exceptions. The Bureau 
of Reclamation also notes that Article 22 should be revised to reflect 
security concerns raised by the release of information.
---------------------------------------------------------------------------

    \104\ 5 U.S.C. 552(a) (2000).
---------------------------------------------------------------------------

Commission Conclusion
    650. In the Final Rule, the Commission adopts NOPR Article 22, with 
minor modifications, as described below.
    651. In response to Cal ISO, the Final Rule allows an RTO or ISO to 
have access to certain data. Final Rule Article 22.1.11 permits a 
Transmission Provider to make available information ``necessary to 
fulfill its obligations * * * as a transmission service provider or a 
Control Area operator including disclosing the Confidential Information 
to the RTO/ISO.'' A Transmission Provider that is obliged to disclose 
information to an RTO or ISO must notify the other Party in writing, 
assert confidentiality, and cooperate in seeking to protect the 
Confidential Information from public disclosure ``by confidentiality 
agreement, protective order or other reasonable measures.'' Thus a 
Transmission Provider may make available any required operational, 
performance or maintenance data as long as it maintains the 
confidentiality of the requested Confidential Information.
    652. Regarding the Bureau of Reclamation's argument about its 
obligations under FOIA, the Commission recognizes that Parties may be 
subject to statutory or regulatory information restrictions, some of 
which may address security concerns. If state or federal laws indeed 
conflict with the Final Rule's confidentiality and information sharing 
provisions, the Commission expects that public utilities will make 
conforming changes to these provisions in their compliance filings and 
explain the statutory basis for such changes. This also applies to non-
public utilities that plan to amend their safe harbor tariffs with a 
conforming Final Rule LGIP and Final Rule LGIA.
    653. The Commission is also making several minor changes to NOPR 
LGIA Article 22.1.10 that addresses disclosure to the Commission or its 
staff. A Party must provide requested information to the Commission or 
its staff, even when the Party otherwise would be required by the LGIA 
to maintain this information in confidence. The Party receiving the 
request must ask the Commission to treat this information as 
confidential and non-public, consistent with Section 388.112 of the 
Commission's Regulations.\105\ A Party must notify the other Party when 
it learns that the Commission has received a request that such 
information be made public pursuant to Section 388.112. Commission 
policy prohibits a contracting Party from revealing to a counter-Party 
that it has received a request for information from the Commission, 
when such request is made pursuant to an investigation or 
otherwise.\106\ The Commission likewise prohibits a Party from 
notifying the other Party prior to the release of the Confidential 
Information to the Commission or its staff.\107\
---------------------------------------------------------------------------

    \105\ 18 CFR 388.112 (2003).
    \106\ American Electric Power Service Corp., 99 FERC ] 61,312 at 
PP 22-24 (2002).
    \107\ Id.
---------------------------------------------------------------------------

    654. The Commission is also revising Article 22.1.10 in the Final 
Rule LGIA to clarify that the Party receiving the request from the 
Commission or its staff will not contact the other Party before 
releasing the Confidential Information. In addition, because requests 
for information may be made under the investigation rules in Section 
1b.20 of the Commission's Regulations, the Final Rule article includes 
this reference.
    655. Article 23--Environmental Releases--Proposed LGIA Article 23 
described the procedures that would be required for notifying the other 
Party of the release or remediation of Hazardous Substances. No 
significant comments were submitted on this article. Accordingly, the 
Commission adopts this article in the Final Rule as proposed.
    656. Article 24--Information Requirements--Proposed LGIA Article 24 
described the proposed requirements for sharing information regarding 
the electrical characteristics of the Parties' respective facilities, 
including monthly status reports on construction and installation of 
the Transmission Provider's Interconnection Facilities and Network 
Upgrades.
    657. Article 24.4--Information Supplementation--Proposed LGIA 
Article 24.4 required the Parties, before the Commercial Operation Date 
of the Interconnection Customer's Generating Facility, to provide 
either updated test and other technical information or written 
confirmation that the new technical data and the originally submitted 
data are consistent. It also describes the types of voltage tests that 
would be conducted by the Interconnection Customer and the type of 
recordings it is required to provide to the Transmission Provider. It 
provides that when there are multiple units at a Generating Facility, 
the Interconnection Customer would be required to provide recordings 
for only one generating unit if the other units have identical design 
and response characteristics.
Comments
    658. NERC recommends that Article 24.4 be revised to require that 
tests conducted on the Generating Facility be consistent with Good 
Utility Practice. It also recommends requiring the Interconnection 
Customer to provide the Generating Facility's characteristics based on 
validated test recordings, as opposed to raw test data. It asks that 
the

[[Page 49900]]

Commission not permit the test results for one generating unit to be 
allowed to represent the characteristics of all generating units, if 
there is more than one unit at the Generating Facility with the same 
design characteristics. NERC believes that it is necessary to verify 
modeling characteristics of each generating unit for system planning 
purposes and to verify the operational capabilities of each generating 
unit for operations purposes. NERC states that the electrical 
characteristics of each Generating Facility are unique.
Commission Conclusion
    659. We concur with NERC's position and adopts its recommended 
revisions.
    660. Article 25--Information Access and Audit Rights--Proposed LGIA 
Article 25 required that each Party make information available to the 
other Party necessary to verify costs for which the other Party is 
responsible under this LGIA and to carry out its obligations and 
responsibilities under the LGIA. No significant comments were submitted 
on this article. Accordingly, the Commission adopts this article in the 
Final Rule as proposed.
    661. Article 26--Subcontractors--Proposed LGIA Article 26 provided 
that the Parties would be able to use subcontractors to perform 
obligations under the LGIA if the subcontractors comply with the 
applicable terms and conditions of the LGIA and each Party remains 
liable to the other for the subcontractor's performance. The hiring 
Party would retain all of its obligations under this article. No 
significant comments were submitted on this article. Accordingly, the 
Commission adopts this article in the Final Rule as proposed.
    662. Article 27--Disputes--Proposed LGIA Article 27 explained the 
Dispute Resolution and arbitration procedures that would apply to the 
LGIA. No significant comments were submitted on this article. 
Accordingly, the Commission adopts this article in the Final Rule as 
proposed with one change to emphasize that Parties should consider 
using informal dispute resolution as well as more formal options.
    663. Article 28--Representations, Warranties and Covenants--
Proposed LGIA Article 28 would have required that each Party be 
organized and qualified to do business in the relevant jurisdiction. 
Each Party would be required to have the authority to enter into this 
LGIA, and performance of its duties would not conflict with 
organizational or formation documents. No significant comments were 
submitted on this article. Accordingly, the Commission adopts this 
article in the Final Rule as proposed.
    664. Article 29--Joint Operating Committee (in the NOPR: Operating 
Committee)--Proposed LGIA Article 29 provided that the Transmission 
Provider shall set up: (1) An Operating Committee made up of a member 
from the Interconnection Customer and a member from the Transmission 
Provider, and (2) a Joint Operating Committee made up of members of all 
of its Operating Committees, in order to coordinate operating and 
technical considerations of Interconnection Service. The Operating 
Committee would meet when necessary, but not less than once each 
calendar year. The duties of the Operating Committee would include, 
among other things, establishing and maintaining control and operating 
procedures, data requirements and operating record requirements, 
reviewing outage forecasts, and coordinating outage schedules.
Comments
    665. Avista and FirstEnergy oppose this requirement as unduly 
burdensome and unnecessary because it will impose additional costs on 
them. Moreover, some of the tasks envisioned for the Operating 
Committee are being performed either by NERC or an Applicable 
Reliability Council. For example, Avista argues that NERC is 
responsible for establishing standards for operating and control 
procedures for generators. Dynegy, on the other hand, would keep the 
Operating Committee and proposes some minor changes to the proposed 
language of this provision.
    666. PJM and Cal ISO argue that ISOs should be exempt from this 
requirement because they already perform the tasks envisioned for 
Operating Committee in the normal course of their business.
Commission Conclusion
    667. The Final Rule LGIA eliminates the requirement that the 
Transmission Provider constitute an Operating Committee for each 
Interconnection Customer. However, we are requiring a Joint Operating 
Committee because it provides Interconnection Customers and 
Transmission Providers a forum in which to discuss and coordinate 
operating and technical considerations of Interconnection Service. We 
are revising Final Rule LGIA to eliminate tasks that are already being 
performed by NERC, thereby responding to Avista's concern.
    668. Finally, we agree with PJM and Cal ISO's proposal that the 
Final Rule article exempt an RTO or ISO from this requirement because 
an RTO or ISO performs Joint Operating Committee-type functions in 
their normal course of business.
    669. Article 30--Miscellaneous--Proposed LGIA Article 30 addressed 
matters such as rules of interpretation, a prohibition on third party 
beneficiaries, and the right to amend the LGIA by mutual agreement. No 
significant comments were submitted on this article. Accordingly, the 
Commission adopts this article in the Final Rule as proposed.
    670. Article 30.11--Reservation of Rights--Proposed Article 30.11 
would have reserved to each Party their rights to unilaterally seek 
modification to the LGIA pursuant to sections 205 and 206 of the FPA, 
except as restricted by the other provisions of the executed LGIA.
Comments
    671. Dynegy and Mirant note that this clause is redundant because 
another Reservation of Rights provision appears in Proposed Article 
2.7.
Commission Conclusion
    672. The Commission deletes proposed Article 2.7, and modifies 
proposed Article 30.11 in this Final Rule. As proposed, Article 30.11 
contains a redundancy. The Commission deletes the second paragraph of 
this Article, because it repeats the reservation of rights set forth in 
the first paragraph of the Article.
    673. Appendices--The NOPR LGIA contained appendices for 
Interconnection Facilities and Network Upgrades, time schedule, 
interconnection details, standard LGIA, security arrangement details, 
Commercial Operation Date, and interconnection guidelines. The 
Commission adopts these appendices in the Final Rule LGIA, with the 
exception of Appendix G (Interconnection Guidelines) since the Final 
Rule LGIA captures the provisions of that Appendix elsewhere.

C. Other Significant Policy Issues

    674. A number of issues such as interconnection pricing policy, 
permitted variations in the terms of the Final Rule for independent 
transmission entities, and legal issues such as consequential damages 
and liquidated damages transcend individual sections in the Final Rule 
LGIP or articles in the Final Rule LGIA. Accordingly, they are 
addressed in the individual discussions that follow.
1. Interconnection Pricing Policy
    675. In the NOPR, the Commission proposed to adopt its existing 
interconnection pricing policy for a

[[Page 49901]]

Transmission Provider that is not independent of market participants, 
and invited comments on whether it should depart from this policy for a 
Transmission Provider that is independent.
    676. Since the NOPR was written to reflect the Commission's current 
pricing policy, NOPR LGIA Article 11 proposed that the Interconnection 
Customer be solely responsible for the costs of Interconnection 
Facilities, which are defined as all facilities and equipment between 
the Generating Facility and the Point of Interconnection with the 
Transmission System. Network Upgrades, which are defined as all 
facilities and equipment constructed at or beyond the Point of 
Interconnection for the purpose of accommodating the new Generating 
Facility,\108\ would be funded initially by the Interconnection 
Customer unless the Transmission Provider elects to fund them. The 
Interconnection Customer would then be entitled to a cash equivalent 
refund (i.e., credit) equal to the total amount paid for the Network 
Upgrades, including any tax gross-up or other tax-related payments. The 
refund would be paid to the Interconnection Customer on a dollar-for-
dollar basis, as credits against the Interconnection Customer's 
payments for transmission services, with the full amount to be 
refunded, with interest calculated in accordance with 18 CFR 
35.19a(a)(2)(ii), within five years of the date the Network Upgrades 
are placed in service, so long as the Transmission Provider continues 
to receive payments for transmission service with respect to the 
Generating Facility during this period. The NOPR proposed that the 
Interconnection Customer may assign its refund rights to any person.
---------------------------------------------------------------------------

    \108\ The proposed definition also states that the ``facilities 
and equipment are used by and benefit all users of the transmission 
grid, without distinction or regard as to the purpose of the upgrade 
(e.g., to relieve overloads, to remedy stability and short circuit 
problems, to maintain reliability, or to provide protection and 
service restoration) including the fact that these facilities and 
equipment are being replaced or upgraded to accommodate the 
interconnection request.''
---------------------------------------------------------------------------

    677. Also, in the NOPR, the Commission asked for comments on 
appropriate interconnection pricing consistent with the use of the 
locational marginal pricing methodology. This method was proposed in 
the Standard Market Design proceeding that the Commission had 
previously announced.\109\ The Commission noted that in a region that 
uses locational pricing, the RTO or ISO usually assigns to the 
Interconnection Customer the cost of any new network facilities that 
would not be in its transmission expansion plan but for the 
interconnecting Generating Facility. The Interconnection Customer then 
typically receives transmission rights in return for the capacity that 
is created. The Commission explained that this pricing method has been 
allowed only in regions where the Transmission Provider is independent 
of market participants, because certain aspects of this method can be 
subjective. These subjective aspects include the determination of 
congestion prices, rules for deciding which Interconnection Customer in 
the queue should be responsible for which facilities, the cost of the 
facilities, and the assumptions underlying the power flow analysis 
needed for system impact and facilities studies. The Commission noted 
that a Transmission Provider that is not an independent entity would 
have the ability and the incentive to exploit this subjectivity to its 
own or its affiliates advantage if it is able to allocate the costs of 
Network Upgrades between the Interconnection Customer and other 
transmission customers, where the Transmission Provider may be the 
principal other customer. The Commission invited comments on whether it 
should accept an approach that departs from the current Commission 
policy of providing transmission credits, and stated its willingness to 
consider alternative proposals as long as the cost causation 
determinations are made on an objective and non-discriminatory basis by 
an independent entity such as an RTO.
---------------------------------------------------------------------------

    \109\ Remedying Undue Discrimination Through Open Access 
Transmission Service and Standard Electricity Market Design, Notice 
of Proposed Rulemaking, 67 FR 55542 (Aug. 29, 2002), FERC Stats. & 
Regs. ] 32,563 (2002).
---------------------------------------------------------------------------

    678. The Commission has traditionally favored a ``rolled-in'' 
transmission pricing policy of the type that formed the basis for the 
pricing proposal in the Interconnection NOPR. However, such a policy 
may limit economic expansions that would remove congestion and allow 
customers to reach more distant power supplies. This may occur at least 
in part because state siting authorities may have little interest in 
siting a transmission facility that benefits mainly a particular 
Interconnection Customer or customers in another state if doing so 
would require the retail sales customers on the constructing public 
utility's system to pay for the new facilities.
    679. The Standard Market Design NOPR proposed that a policy of 
participant funding, where those who benefit from a particular project 
pay for it, may help to solve this problem. The Commission then 
reiterated its concern that certain functions that the Transmission 
Provider must perform to implement participant funding can be 
subjective. Also in this docket, the Commission encouraged the 
formation of Regional State Committees, which would allow states to 
work together to identify beneficiaries of expansion projects and make 
recommendations on pricing proposals and cost recovery that may include 
rolling in, assignment to beneficiaries, or some combination of the 
two.
    680. Finally, the Commission also addressed in the NOPR the 
question of the appropriate rate treatment for the cost of 
Interconnection Facilities that the Transmission Provider constructs 
for its own Generating Facilities. The Commission noted that, in 
Southern Company Services, Inc. (Southern), the company proposed to 
continue to treat the cost of Interconnection Facilities for its own 
Generating Facilities as part of the network while directly assigning 
the cost of the same type of facilities to its competitors' Generating 
Facilities. Southern raised the issue of how to ensure consistency 
between interconnection and transmission pricing. Recognizing the need 
to address this issue on a generic basis, the Commission made Southern 
subject to the outcome of this rulemaking. The Commission proposed in 
the NOPR to require all transmission rates to be designed in a manner 
that is consistent with whatever interconnection pricing policy is 
approved in the Final Rule. Thus, the Commission proposed that, to the 
extent its current interconnection pricing policy is adopted, each 
Transmission Provider must remove from its transmission rates the costs 
of all Interconnection Facilities, not just generator step-up 
transformers, constructed for the Transmission Provider's own 
Generating Facilities. The Commission proposed that the costs of these 
sole use facilities be directly assigned as generation-related costs. 
The Commission explained that this would be consistent with its current 
pricing of generator step-up transformers, and it would send a more 
accurate price signal by assigning the cost of Interconnection 
Facilities to the generation customers using them.
Comments
    681. A large number of commenters argue that the Commission's 
proposed crediting policy provides an undesirable subsidy to the 
Interconnection Customer and thereby creates incentives for the 
Interconnection Customer to make poor siting and investment decisions. 
Many commenters express concerns about the relationship between this 
policy and the Commission's Standard Market Design

[[Page 49902]]

proposal, and several provide recommendations on how the two rules 
could be made compatible. In addition, many commenters object to 
specific features of the proposed crediting policy. For example, 
several transmission owners cite problems (e.g., regulatory lag, retail 
rate freezes) related to their ability to recover in transmission rates 
the costs of interconnections, including the credits that they pay to 
an Interconnection Customer. Many commenters object to the five year 
``sunset'' date for refunding all amounts paid by the Interconnection 
Customer. They are concerned that transmission customers could be left 
with the financial burden and no offsetting benefits if the 
Interconnection Customer's Generating Facility ceases to operate. Some 
commenters argue that the Interconnection Customer's receipt of credits 
should not be limited to those occasions when the Interconnection 
Customer takes transmission service with respect to the output of the 
Generating Facility. Others argue that the payment of interest on 
unpaid credits is not appropriate or that the rate prescribed is either 
too high or too low.
    682. The following is a summary of the comments received, organized 
according to the issues addressed. After each issue summary, the 
Commission presents its conclusions for that issue.\110\
---------------------------------------------------------------------------

    \110\ Issues regarding the pricing of Network Resource 
Interconnection Service are addressed in part II.C.2 
(Interconnection Products and Scope of Service).
---------------------------------------------------------------------------

Concerns About the Fairness and Efficiency of the Commission's 
Crediting Policy
    683. Transmission Owners, such as Entergy, and others argue that 
the Commission's current crediting policy requires all transmission 
customers to subsidize the cost of facilities that would be unnecessary 
``but for'' a particular Interconnection Customer's Generating Facility 
and that provide no benefits to the other transmission customers on the 
Transmission System. They also argue that this policy encourages 
inefficient siting decisions because the Interconnection Customer has 
no incentive to consider the full impact of its decision regarding 
where to locate its Generating Facility on the Transmission System. 
They claim that, when selecting a site, an Interconnection Customer 
will pay more attention to fuel supply and water availability than to 
its impact on the Transmission System.
    684. The Alabama PSC argues that a pricing policy that spreads the 
costs of all interconnection-related facilities situated ``at and 
beyond'' the Point of Interconnection to all transmission customers 
results in a subsidy to the Interconnection Customer, causes 
inefficiencies in siting, and is inconsistent with longstanding cost 
causation principles. The Coalition for Pricing claims that the policy 
of assigning cost responsibility simply based on the physical location 
of the facilities (i.e., relative to the Point of Interconnection) is 
contrary to the Commission's ``system-wide benefit test'' and violates 
the Energy Policy Act of 1992. It argues that certain facilities 
installed at and beyond the Point of Interconnection may not provide a 
system-wide benefit and, as such, should be directly assigned to the 
Interconnection Customer. Entergy argues that grave consequences can be 
avoided through the interim use of the system-wide benefit test, and 
the assignment of costs to those who benefit, prior to the 
establishment of participant funded expansion regimes in RTOs.
    685. PSEG notes that in PJM the cost of any Network Upgrades that 
would not be required ``but for'' the interconnection of a Generating 
Facility to the Transmission System is assigned to the Interconnection 
Customer, and the Interconnection Customer receives financial 
transmission rights associated with the Network Upgrades that it pays 
for. PJM and others argue that an established RTO or ISO should be 
allowed to continue to use this policy, as the NOPR proposes. PJM 
states that its experience under its interconnection rules confirms 
that such pricing promotes economic efficiency including efficient use 
of the Transmission System. However, KeySpan cautions that the ``but 
for'' test can become meaningless if a fictitious transmission planning 
study can be used to identify the Transmission System needs required to 
meet load growth. It states that the independence of the Transmission 
Provider completing the study is the key to this process.
    686. The Maine PUC contends that the Commission's reasoning for 
refusing to socialize system expansion costs in the natural gas 
pipeline context applies with equal force in the generator 
interconnection context. It states that, just as subsidization of gas 
pipeline expansion costs could lead to non-optimal or unnecessary 
capacity expansion, so too will subsidization of Network Upgrades 
associated with new generation projects. The Maine PUC also states 
that, just as rolled-in pricing gives an existing gas pipeline an 
unfair economic advantage over potential new entrants, subsidization of 
Network Upgrades for Generating Facility interconnections could 
interfere with price signals for alternatives to traditional congestion 
solutions, such as load response from customers or merchant 
transmission.
    687. Many other commenters, including state commissions, are 
especially concerned about an Interconnection Customer that intends to 
sell its output off-system or out of state. These commenters claim that 
the current policy requires transmission customers of the local 
Transmission Provider to subsidize the cost of Network Upgrades that 
would, in the latter case, provide them with no benefits. NRECA-APPA 
recommends that, without a commitment by the Interconnection Customer 
to serve power customers within the Transmission Provider's footprint, 
the Commission should require the Interconnection Customer to pay for 
the Network Upgrades. Some commenters, such as the Midwest ISO, further 
claim that the law in some states may not allow Network Upgrade costs 
to be rolled into the base rates of the local customers that are not 
the beneficiaries of the upgrades.
    688. Other commenters, including EPSA, voice strong support for the 
crediting approach. EPSA states that the crediting mechanism works well 
at this time and should not be adjusted until the Commission has put in 
place a specific market design that would require such an adjustment. 
American Transmission and SoCal Edison also support the crediting 
approach. Indeed, American Transmission supports the crediting approach 
even if the Transmission Provider is an independent entity. American 
Transmission states that it discounts the argument advanced by critics 
of this policy that the Interconnection Customer must receive stronger 
price signals through direct assignment of the costs of Network 
Upgrades to bring about efficient location of new generation. It 
believes that requiring participant funding for Network Upgrades is 
akin to moving backward to the vertically integrated industry structure 
that existed prior to open access.
    689. Cleco supports participant funding that would eliminate the 
need for the costs of Network Upgrades being refunded through 
transmission crediting. In the absence of such an approach, Cleco 
recommends that an Interconnection Customer should be credited for only 
half of the transmission service it has subscribed to for the first 
five years. Under Cleco's

[[Page 49903]]

proposal, there would be no interest paid, and after five years no 
additional payment to the Interconnection Customer would be made. 
Western also recommends that the Commission adopt a method to recover 
the costs of the Network Upgrades from the benefitting entities. It 
believes that current transmission customers should be held harmless 
from the cost impact of Network Upgrades that is not mitigated by 
increased transmission usage and associated revenues.
    690. The North Carolina Commission recommends that the Commission 
modify its proposed rule to explicitly adopt the ``but for'' pricing 
policy for interconnection and transmission service in those states 
that have not yet unbundled retail electric service or implemented 
retail competition.
    691. Several commenters, including National Grid, propose that the 
pricing issue can be resolved by analogy to the process of cost 
allocation for public roads. According to this analogy, the 
Interconnection Customer will have virtually sole use of the leads to 
the substation, just like the homeowner has sole use of his or her 
driveway. Thus, the cost of Interconnection Facilities, which are for 
the sole use of the Interconnection Customer, should be the 
responsibility of the Interconnection Customer. Next, the substation 
facilities needed to connect the sole-use facilities of the 
Interconnection Customer to the general delivery system are shared-use 
facilities, much like a local street. National Grid states that the 
cost of such facilities could be allocated partially to load and 
partially to the new Interconnection Customer. It explains that Network 
Upgrades that are remote from the Generating Facility typically allow 
movement of aggregate generation to aggregate load. National Grid 
contends that the benefits and use of such Network Upgrades are spread 
much more broadly and, like the highway system, could be rolled in and 
allocated to aggregate load within the market, or throughout an RTO if 
one exists. Finally, it argues that it may be appropriate to maintain 
an incremental charge for market-to-market transactions, but only where 
Network Upgrades in one market are needed by another market.
    692. Peabody asserts that the NOPR contains certain provisions that 
are unjust and unreasonable as applied to large-scale base-load 
generation projects, especially coal-based projects. It urges the 
Commission to modify its interconnection pricing policy in such cases 
to require the Transmission Provider to roll the costs of Network 
Upgrades into its transmission rate base without requiring the 
Interconnection Customer to fund the costs in advance.
Commission Conclusion
    693. For Transmission Providers that are not independent entities, 
the Commission will continue to apply its current interconnection 
pricing policy, with certain revisions that are discussed below.
    694. The Commission recognizes that its policy of requiring refunds 
to be paid to an Interconnection Customer for the cost of Network 
Upgrades constructed on its behalf is a controversial one. However, the 
Commission instituted this policy to achieve a number of important 
goals. First, consistent with the Commission's long-held policy of 
prohibiting ``and'' pricing \111\ for transmission service, the 
crediting policy ensures that the Interconnection Customer will not be 
charged twice for the use of the Transmission System. The Commission 
determined that it is appropriate for the Interconnection Customer to 
pay initially the full cost of Interconnection Facilities and Network 
Upgrades that would not be needed but for the interconnection, but once 
the Generating Facility commences operation and delivery service 
begins, it must receive transmission service credits for the cost of 
the Network Upgrades. This ensures that the Interconnection Customer 
will not ultimately have to pay both incremental costs and an average 
embedded cost rate for the use of the Transmission System. Second, the 
Commission's crediting policy helps to ensure that the Interconnection 
Customer's interconnection is treated comparably to the 
interconnections that a non-independent Transmission Provider completes 
for its own Generating Facilities. The Transmission Provider has 
traditionally rolled into its transmission rates the cost of Network 
Upgrades required for its own interconnections, and the Commission's 
crediting policy ensures that Network Upgrades constructed for others 
are treated the same way. Finally, the policy is intended to enhance 
competition in bulk power markets by promoting the construction of new 
generation, particularly in areas where entry barriers due to unduly 
discriminatory transmission practices may still be significant. The 
policy is therefore consistent with the Commission's long-held view 
that competitive wholesale markets provide the best means by which to 
meet its statutory responsibility to assure adequate and reliable 
supplies of electric energy at just and reasonable prices.\112\
---------------------------------------------------------------------------

    \111\ When a Transmission Provider must construct Network 
Upgrades to provide new or expanded transmission service, the 
Commission generally allows the Transmission Provider to charge the 
higher of the embedded costs of the Transmission System with 
expansion costs rolled in, or incremental expansion costs, but not 
the sum of the two. Hence, ``and'' pricing is not permitted.
    \112\ The Commission's crediting policy has also withstood 
judicial review. In an opinion issued February 18, 2003, the DC 
Circuit Court of Appeals affirmed Commission orders requiring a 
Transmission Provider to provide credits to Interconnection 
Customers for the cost of short-circuit and stability Network 
Upgrades. Entergy Services, Inc. v. FERC, 319 F.3d 536 (DC Cir. 
2003). The court stated that ``[t]he Commission's rationale for 
crediting network upgrades, based on a less cramped view of what 
constitutes a 'benefit,' reflects its policy determination that a 
competitive transmission system, with barriers to entry removed or 
reduced, is in the public interest.'' Id. at 543-44. The court 
concluded that ``the Commission has reasonably explained that its 
crediting pricing policy avoids both gold plating and less favorable 
price signals such that the enlarged transmission system, which it 
views as a public good, can function reliably and continue to 
expand.'' Id. at 544.
---------------------------------------------------------------------------

    695. While the Commission still finds these to be appropriate goals 
for an interconnection pricing policy, the commenters that object to 
the Commission's crediting policy make a number of valid points. Most 
importantly, as many point out, providing transmission service credits 
to an Interconnection Customer for the cost of Network Upgrades that 
would not be needed but for the interconnection of the new Generating 
Facility mutes somewhat the Interconnection Customer's incentive to 
make an efficient siting decision that takes new transmission costs 
into account, and it provides the Interconnection Customer with what 
many view as an improper subsidy, particularly when the Interconnection 
Customer chooses to sell its output off-system. In this regard, the 
Commission believes that, under the right circumstances, a well-
designed and independently administered participant funding policy for 
Network Upgrades offers the potential to provide more efficient price 
signals and a more equitable allocation of costs than the crediting 
approach. The Commission notes that the transmission pricing policies 
that the Commission has permitted for an RTO or ISO with locational 
pricing, in which the Interconnection Customer bears the cost of all 
facilities and upgrades that would not be needed but for the 
interconnection of the new Generating Facility and receives valuable 
transmission rights in return, are acceptable forms of participant 
funding.
    696. However, the Commission remains concerned that, when the 
Transmission Provider is not

[[Page 49904]]

independent and has an interest in frustrating rival generators, the 
implementation of participant funding, including the ``but for'' 
pricing approach, creates opportunities for undue discrimination. As 
the Commission stated in the NOPR, a number of aspects of the ``but 
for'' approach are subjective, and a Transmission Provider that is not 
an independent entity has the ability and the incentive to exploit this 
subjectivity to its own advantage. For example, such a Transmission 
Provider has an incentive to find that a disproportionate share of the 
costs of expansions needed to serve its own power customers is 
attributable to competing Interconnection Customers. The Commission 
would find any policy that creates opportunities for such 
discriminatory behavior to be unacceptable. Furthermore, none of the 
commenters in this proceeding has convinced the Commission that, in the 
absence of independence, it is possible to implement a ``but for'' 
pricing approach that avoids this inherent subjectivity. Therefore, the 
Commission continues in this Final Rule its current policy, as modified 
below, of requiring a Transmission Provider that is not an independent 
entity to provide transmission credits for the cost of Network Upgrades 
needed for a Generating Facility interconnection.
    697. The Commission notes, however, that the current pricing policy 
does not explicitly address instances where the Generating Facility 
interconnects with a Transmission Provider's jurisdictional 
distribution facility and, as a result, upgrades are needed on the 
Distribution System to accommodate the interconnection. The Commission 
clarifies here that, if any such interconnection is jurisdictional, the 
cost of such upgrades must be directly assigned to the Interconnection 
Customer. This is because an upgrade to the Distribution System 
generally does not benefit all transmission customers. Distribution 
facilities typically deliver electricity to particular localities, and 
do not serve a bulk delivery service for the entire system as is the 
case for transmission facilities. Accordingly, it is not appropriate 
that all transmission customers share the cost of Distribution 
Upgrades.
    698. For a Transmission Provider, such as an RTO or ISO, that is an 
independent entity, the Commission continues to allow flexibility 
regarding the interconnection pricing policy that each independent 
entity chooses to adopt, subject to Commission approval. We invite a 
Regional State Committee to establish criteria that an independent 
entity would use to determine which Transmission System upgrades, 
including those required for generator interconnections, should be 
participant funded and which should not.
    699. The Commission will permit, for a period of transition to the 
start of RTO or ISO operations, not to exceed a year, participant 
funding to be used for Network Upgrades for generator interconnections 
as soon as an independent administrator has been approved by the 
Commission and the affected states. Allowing participant funding, i.e., 
direct assignment of the cost of Network Upgrades is reasonable, if an 
independent administrator performs transmission planning and related 
cost allocation, as a transitional approach that may be used in 
anticipation of an RTO or ISO assuming operational control of the 
regional transmission grid within a year.\113\ Based on the comments in 
this interconnection rulemaking, we find this approach to be 
appropriate here. Therefore, the Commission adopts this policy in this 
Final Rule.
---------------------------------------------------------------------------

    \113\ See Cleco Power LLC, et al., 103 FERC ] 61,272 (2003); 
Southern Company Services, Inc., 103 FERC ] 61,279 (2003), reh'g 
pending.
---------------------------------------------------------------------------

    700. However, the Commission wishes to emphasize that, by allowing 
an independent Transmission Provider to adopt a pricing policy, such as 
the ``but for'' approach, that differs from the crediting approach that 
the Commission is requiring for non-independent entities, the 
Commission is not abandoning the goals that the Commission has 
established for interconnection pricing, as described above. First, 
even though the ``but for'' approach allows the cost of certain Network 
Upgrades to be assigned to the Interconnection Customer, it is not 
``and'' pricing if, for example, the Interconnection Customer is 
allowed to receive well-defined capacity rights that are created by the 
upgrades. For example, PJM, which uses locational pricing, gives Firm 
Transmission Rights (FTRs) and Capacity Interconnection Rights (CIRs) 
to the Interconnection Customer in exchange for a ``but for'' cost 
payment. These are rights that are created by the Network Upgrades for 
which the Interconnection Customer pays, and they are well-defined, 
long-term and tradeable. Moreover, the Commission concludes that, even 
if the Interconnection Customer (or its power sales customer) is also 
required to pay an embedded cost-based charge for transmission service, 
this is not ``and'' pricing. This is because the Interconnection 
Customer pays separate charges for separate services. It pays an access 
charge for transmission service that may involve an obligation to pay 
congestion charges, and in exchange for its ``but for'' payment, it 
receives these well-defined capacity rights, which provide some 
protection from having to actually pay the congestion charges.
    701. Second, when the Transmission Provider is an independent 
entity, the Commission is much less concerned that all generation 
owners will not be treated comparably because independence ensures that 
the Transmission Provider has no incentive to treat Interconnection 
Customers differently.
    702. Third, in this context, ``but for'' pricing is consistent with 
the Commission's policy of promoting competitive wholesale markets 
because it causes the Interconnection Customer to face the same 
marginal cost price signal that it would face in an efficient, 
competitive market. This means that, in a competitive market 
environment, market forces could act freely to achieve the desirable 
level of entry of new generating capacity.
    703. Finally, participant funding of transmission upgrades may 
provide the pricing framework needed to overcome the reluctance of 
incumbent Transmission Owners in many parts of the country to build 
transmission, with the result that badly needed transmission 
infrastructure could be put in place quickly.
Interconnection Pricing and the Transition to Standard Market Design
    704. Several commenters assert that certain proposed Standard 
Market Design policies, such as locational marginal pricing, congestion 
revenue rights, transmission expansion pricing, and transmission 
planning, could affect interconnection pricing, but that the full 
effect cannot be determined until the Standard Market Design Final Rule 
is issued. Nevertheless, many of these commenters propose that, until 
Standard Market Design is implemented, the Commission should continue 
to require the Interconnection Customer to pay for Network Upgrades in 
exchange for future transmission service credits. Duke Energy proposes 
that after Standard Market Design is implemented, the crediting policy 
could be replaced with one that provides the Interconnection Customer 
with financial transmission rights in exchange for funding Network 
Upgrades.
    705. Exelon and Sithe recommend that, for the Transmission Provider 
that is not yet part of an RTO, and for an RTO that has not yet 
implemented LMP-based congestion pricing, the Commission continue its 
current policy

[[Page 49905]]

of requiring the Transmission Provider to provide an Interconnection 
Customer that funds Network Upgrades with credits against future 
transmission service. As a transition plan, Exelon and Sithe recommend 
that an Interconnection Customer that is receiving credits when 
Standard Market Design is implemented be awarded financial transmission 
rights in an amount based on the Interconnection Customer's remaining 
credits as a proportion of its total credits. Some commenters, such as 
Cleco Power and Monongahela Power, emphasize that a Transmission 
Provider should not be required to provide both transmission credits 
and congestion rights to the same Interconnection Customer. Mirant 
believes that the two practices can coexist and that the 
Interconnection Customer should have the option to elect either 
transmission credits or the equivalent firm transmission rights as 
comparable compensation for Network Upgrades.
    706. Other commenters believe that attempting to resolve pricing 
issues in this rulemaking presents significant problems. New York 
Transmission Owners declares that the ``Commission's [Standard Market 
Design and LMP] policies and this NOPR are regulatory ships traveling 
in the night on a collision course, each completely unaware of the 
other's existence.'' They propose that the Commission limit the 
interconnection rulemaking to non-price issues. EPSA proposes that the 
Commission need not resolve in this proceeding what, if any, changes in 
the crediting mechanism might be necessary to implement Standard Market 
Design and the formation of RTOs. Calpine submits that the transmission 
credit policy should not be abandoned in the transition to Standard 
Market Design. It states that relying on recovery of the costs of 
Network Upgrades solely through assignment of FTRs under Standard 
Market Design would ignore the network access aspect of Standard Market 
Design and would not provide a practical means of recovering all costs 
of Network Upgrades. Although a change in policy may be appropriate 
after the Standard Market Design is in place, Calpine recommends that 
such a change not be made in this proceeding.
Commission Conclusion
    707. The timing and content of any Final Rule in the Standard 
Market Design proceeding will not be determined in this proceeding. In 
the meantime, it is important to include interconnection pricing rules 
in this Final Rule, based on the record of this proceeding.
The Inability of a Transmission Owner To Recover the Costs of Network 
Upgrades
    708. A number of Transmission Owners express concern that they may 
not be able to recover in a timely fashion the costs that they will 
incur under the proposed pricing policy. Monongahela Power states that 
a Transmission Owner faces three problems in this regard. First, it 
notes that a Transmission Owner faces the expense, delay, and 
uncertainty of a full transmission rate case before the Commission to 
roll in the costs of system upgrades associated with new generation 
projects. Second, it claims that even if the Commission grants full 
cost recovery, costs may be ``trapped'' by an inability to pass them 
through to the majority of customers due to a state retail rate freeze. 
Third, a Transmission Owner may face lost revenues associated with a 
new generating project once transmission service begins because of the 
requirement to provide a financial credit to the Interconnection 
Customer. Monongahela Power asks that the Commission permit a 
Transmission Owner to make a limited Section 205 filing for the 
immediate roll in of these costs, and that it work with the States to 
accommodate the flow-through of these costs to retail customers. At a 
minimum, both Monongahela Power and Dominion Resources ask that the 
Commission provide for deferred accounting treatment with assurances of 
future cost recovery when the Transmission Owner must record a 
transmission revenue credit with no income to offset it.
Commission Conclusion
    709. The Commission concludes that it is not necessary to provide 
for the Transmission Provider to make a limited Section 205 filing as 
proposed by Monongahela Power for the immediate roll in of the costs it 
will incur under the crediting policy. In the ordinary course of 
business, a public utility frequently incurs costs for which it has no 
immediate revenue offset, just as it routinely experiences revenue 
increases that are not accompanied by commensurate increases in costs. 
When a public utility believes that its revenues are not adequate, it 
is permitted by Section 205 of the FPA to make a rate filing. The 
commenters have provided no evidence to convince the Commission that 
the burden created by its crediting policy is so great that the 
Commission should change its regulations to permit a limited Section 
205 transmission rate filing that addresses only credit-related cost 
increases, or deferred accounting treatment for transmission credits, 
as sought by Monongahela Power and Dominion Resources.
Responsibility for Line Outage Costs Resulting From Interconnection
    710. The NOPR did not address the allocation of costs that may be 
incurred when a transmission line must be taken off-line in order to 
complete an interconnection. In an order issued November 20, 2001,\114\ 
however, the Commission stated that it would consider in this 
rulemaking the question of who should bear these costs.
---------------------------------------------------------------------------

    \114\ American Electric Power Service Corporation, 97 FERC ] 
61,200 (2001) (AEP).
---------------------------------------------------------------------------

    711. Commenters express a variety of views on this issue. The 
Coalition for Pricing states that these costs should be a component of 
the costs paid by generators for interconnection service under the 
Final Rule IA. It asserts that any other policy would result in all 
transmission customers unfairly subsidizing Generating Facility 
interconnections. The Coalition for Pricing proposes that the Parties 
to individual interconnection agreements be allowed to agree on the 
specific line outage costs for which the Interconnection Customer 
should be responsible. The Coalition for Pricing argues that, since the 
Parties' agreement would necessarily be filed with the Commission, it 
would retain its regulatory control over line outage cost allocations. 
However, Reliant states that the Commission has had a policy of not 
requiring that the Interconnection Customer pay for outage-related 
costs, and argues that the Coalition for Pricing has provided no 
justification for departing from this policy. Reliant recommends 
rejecting the modifications that the Coalition for Pricing proposes.
    712. AEP recommends that the Interconnection Customer be required 
to reimburse all affected generation owners for outage-related costs 
that they incur, whether or not such generation owners are affiliated 
with the Transmission Provider. AEP believes that this can be done in a 
manner that properly identifies the costs, minimizes the Transmission 
Provider's discretion, and allows for adequate regulatory scrutiny. It 
recommends a method of compensation that it claims avoids the exercise 
of discretion. That is, the Interconnection Customer should replace the 
energy that would otherwise have been generated by the affected 
Generating Facility. AEP states that if the Interconnection Customer is 
unwilling to replace the lost energy, it would be up to the affected 
generation

[[Page 49906]]

owner to file with the Commission a proposal to recover its costs. 
Further, AEP believes that the Interconnection Customer, the existing 
generation owner and the Transmission Provider should be obligated to 
use Reasonable Efforts to minimize the impact of any outage.
    713. ATC states that dividing the costs between the Interconnection 
Customer and the Transmission Provider may provide the most equitable 
results. It believes that a reasonable approach might be to allocate up 
to the full costs of the line outage to the Interconnection Customer so 
long as the timing is primarily under the Interconnection Customer's 
control. However, if the Transmission Provider has substantial 
influence over the timing and engineering aspects of the outage, ATC 
recommends that all or a large percentage of the new facility costs may 
be appropriate for rolling into transmission rates.
Commission Conclusion
    714. The Final Rule does not permit the Transmission Provider to 
allocate interconnection-related outage costs to the Interconnection 
Customer. The Commission recognizes that the Transmission Provider and 
the owners of other generators may incur costs as a result of having to 
take a transmission line out of service in order to complete an 
interconnection. Such costs may include generator shut-down and restart 
costs, redispatch and purchased power costs, lost opportunity costs on 
sales not made, costs of power to compensate for additional line 
losses, and possibly other costs. In prior orders,\115\ the Commission 
has generally rejected, without prejudice, proposals by a Transmission 
Provider to allocate these costs to the Interconnection Customer. Among 
other things, the Commission has found that the proposals are vague, 
leave too much discretion to the Transmission Provider, and do not 
provide for adequate regulatory oversight by the Commission. For 
example, in NSTAR, the Commission stated that ``determining how much 
cost responsibility to assign to an interconnecting generator, when 
other factors also may contribute to the need to redispatch 
contemporaneously, would be unacceptably arbitrary: for example, higher 
redispatch costs may be the result of a planned or unplanned outage, 
maintenance that requires a line to be taken out of service 
temporarily, or an unexpected shift in load.'' \116\ Furthermore, while 
the Transmission Provider may be able to propose an objective method 
for determining its own outage-related costs, estimating the outage-
related costs of unaffiliated generation owners could pose a 
significant problem. The Commission does not believe that AEP's 
proposal to have the Interconnection Customer replace the energy that 
would otherwise have been generated by the affected Generating Facility 
solves this problem in part because the value of the replacement energy 
may bear no relationship to the actual outage-related costs.
---------------------------------------------------------------------------

    \115\ See, e.g., id.; ISO New England, Inc., 91 FERC ] 61,311 
(2000).
    \116\ Cambridge Electric Light Co., et al., (NSTAR), 95 FERC ] 
61,339 (2001).
---------------------------------------------------------------------------

    715. As the Commission concluded above, when the Transmission 
Provider asks the Interconnection Customer to reschedule a planned 
maintenance outage of the Generating Facility (per Article 9.7--
Outages, Interruptions, and Disconnection), the Interconnection 
Customer should be compensated for only the direct costs that the 
Interconnection Customer incurs. It should not be compensated, for 
example, for lost opportunity costs. One reason is that outages of 
transmission and generation facilities for maintenance and other 
purposes are a routine part of electric system operations and, in 
fairness, these costs also should be considered a normal part of doing 
business. Moreover, the determination of the appropriate level of costs 
to be allocated involves a process that is inevitably arbitrary and 
contentious, particularly when the determination is made by a 
Transmission Provider that is not an independent entity. Therefore, in 
the Final Rule we are codifying our policy of not allowing 
interconnection-related outage costs to be allocated to the 
Interconnection Customer.
Issues Concerning the Five Year Refund Period and the Payment of 
Interest
    716. Many commenters object to the proposal to require the 
Interconnection Customer to be reimbursed for the costs of Network 
Upgrades within a five year period. Several also object to the payment 
of interest on outstanding balances or to the formula for determining 
the rate of interest.
    717. Duke Energy generally supports the provisions as proposed but, 
to be consistent with the Commission's policy of allowing the 
Transmission Provider to collect the higher of incremental or embedded 
costs for transmission service, it recommends elimination of the five 
year ``sunset'' provision in Section 11.4.1 of the NOPR LGIA. Cleco is 
concerned that a Transmission Provider may be liable for payment of 
refunds after a five year period has elapsed because the 
Interconnection Customer has not taken enough transmission service to 
be credited the full amount for upgrades originally paid for. 
Westconnect RTO submits that arbitrarily setting a five year term is 
unjustified and unreasonable. It proposes that a more appropriate 
approach would be to allow unused transmission credits to expire after 
a set term. However, Mirant argues that once the Network Upgrades are 
placed in service, every network customer receives some benefit from 
those facilities. Therefore, it sees no reason to limit the refund to 
the requirement in proposed LGIA Article 11.4.1 that the Transmission 
Provider continue to receive payment for transmission service from the 
Generating Facility.
    718. Western states that if it has to return monies to an 
Interconnection Customer in less time than the service life of an 
upgrade, rates may have to be increased to ensure the timely repayment 
of other federal investments. It believes such a rate increase would be 
inequitable to existing customers. BPA states that the Interconnection 
Customer should not be entitled to a refund over an arbitrary five year 
period and argues that other customers should not have to bear the risk 
that the Interconnection Customer will cease taking transmission 
service. LADWP states that the five year requirement imposes an undue 
burden on public power customers. It requests that, if the Commission's 
generation interconnection pricing policy is applied to a non-
jurisdictional transmission owner, that owner should have the 
flexibility to provide such refunds over the same period that it would 
use to amortize such facilities if constructed for the benefit of its 
own customers. WEPCO states that the Commission should recognize that 
sometimes both the Interconnection Customer and the Transmission 
Provider may desire a payback period of less than five years. 
Accordingly, it recommends that the Commission revise Article 11.4.1 of 
the NOPR LGIA to provide for repayment at such earlier time as the 
Parties may agree.
    719. Mirant argues that, at a minimum, the Commission should 
require that interest on any Network Upgrades be calculated using the 
Transmission Provider's most recent Commission-approved rate of return 
in the Transmission Provider's OATT. For a non-public utility that does 
not have a rate of return, Mirant proposes that the Commission use the 
rate of return set forth in the most recent Commission order as a proxy 
for such entity. Peabody recommends that the Commission modify the 
proposed LGIA

[[Page 49907]]

to provide for a more flexible, incentive-based rate of interest for 
transmission credits. Also, if a Transmission Provider files for 
incentive pricing for transmission service, Peabody recommends that it 
be required to file simultaneously to amend the interest rate in LGIA 
Article 11.4.1 to match such incentive mechanism. Progress Energy 
disagrees with the requirement to pay an Interconnection Customer 
interest, arguing that the Transmission Provider cannot use the funds 
advanced by the Interconnection Customer for purposes other than 
constructing the Network Upgrades and that it should not be put in the 
position of being a bank for the Interconnection Customer. If interest 
must be paid, Progress Energy proposes using the Federal Fund 
Commercial Rate or a similar rate to ensure that the payment of 
interest is not a source of profit for the Interconnection Customer.
Commission Conclusion
    720. Regarding the specific rules for the payment of credits, the 
Commission clarifies that the Interconnection Customer is entitled to a 
full refund of the payments it makes toward the cost of Network 
Upgrades within five years after the Commercial Operation Date, as long 
as the Generating Facility remains in operation through the five year 
period.\117\ During the five year period, credits must be awarded on a 
dollar-for-dollar basis as payments are made for transmission services. 
However, the Commission is also permitting the payments to be made on 
any other basis that is mutually agreeable to the Interconnection 
Customer and the Transmission Provider. For example, if the Parties 
agree to a stream of uniform monthly payments designed to fully 
reimburse the Interconnection Customer over the five year period, that 
would be acceptable. In addition, as stated in Article 11.3 of the 
Final Rule LGIA, the Transmission Provider may elect to fund the 
Network Upgrades itself, with no advance payment by the Interconnection 
Customer, and thus no need for subsequent credits.
---------------------------------------------------------------------------

    \117\ Although Article 11.4.1 of the NOPR LGIA proposed to begin 
the five year period on the date that the Network Upgrades are 
placed in service, as the Commission explains below, the Commission 
concludes that the Interconnection Customer should not be entitled 
to receive a refund unless the Generating Facility achieves 
commercial operation. Therefore, the Commission is modifying Article 
11.4.1 to specify that the five year period begins with the 
Generating Facility's Commercial Operation Date.
---------------------------------------------------------------------------

    721. With regard to Cleco's concern about the Transmission 
Provider's liability at the end of the five year crediting period, the 
Commission clarifies that the Transmission Provider must make a lump-
sum payment to the Interconnection Customer for any balance owed to the 
Interconnection Customer five years after the Interconnection Customer 
has begun commercial operation.
    722. The Commission recognizes that the choice of the length of the 
repayment period is somewhat arbitrary. However, specifying five years 
as the maximum repayment period will promote the development of new 
generation by reducing the Interconnection Customer's risk, thereby 
facilitating project financing. Contrary to the views of LADWP and 
others, it would not be appropriate to extend repayment over a period 
that corresponds to the Transmission Provider's amortization period for 
similar facilities. As explained above, the Commission's policy for a 
non-independent Transmission Provider is to roll the costs of 
interconnection-related Network Upgrades into the Transmission 
Provider's transmission rate base. However, rather than require 
immediate roll-in, we have chosen a five year repayment period, in part 
to provide the Interconnection Customer with an incentive to make good 
faith requests for Network Upgrades.
    723. With regard to the payment of interest on unpaid credits, the 
Commission adopts the policy proposed in the NOPR. The Commission 
continues to believe that the Interconnection Customer is entitled to a 
refund for all of the costs of the Network Upgrades for which it has 
paid, including a reasonable estimate of the carrying costs that it 
incurs in making the advance payments. The determination of an interest 
rate that accurately reflects this carrying cost cannot be reduced to a 
completely objective calculation. Interest calculated in accordance 
with 18 CFR Sec.  35.19a(a)(2)(ii) provides a reasonable proxy for this 
carrying cost, and because it offers an objective calculation, the 
Commission retains this provision in Article 11.4.1 of the Final Rule 
LGIA.
Rules Governing the Payment of Credits
    724. With regard to the payment of credits, Interconnection 
Customers generally are in favor of a flexible policy that allows 
credits to be paid under a wide range of circumstances, while 
Transmission Providers advocate a policy that places strict limits on 
when and how an Interconnection Customer may receive credits.
    725. For example, Dynegy states that the Final Rule must ensure 
that the credits do not limit the Interconnection Customer to 
purchasing the delivery component of transmission service on the 
Transmission Provider's system with the Interconnection Customer's 
Generating Facility as the Point of Receipt. Instead, Dynegy believes 
that the credits should apply to transmission at any location on the 
Transmission Provider's system. Duke Energy believes that an 
Interconnection Customer's flexibility in obtaining refunds should be 
similar to the flexibility a Transmission Customer has to reassign 
transmission service under the OATT. Accordingly, it proposes to allow 
credits not only for the charges for transmitting power from the 
Generating Facility, but also for the charges for transmitting power 
from an Affiliated Generating Facility. Similarly, Peabody states that 
the Interconnection Customer should be allowed to receive credits for 
any transmission service that it purchases on the Transmission 
Provider's Transmission System. Both Calpine and EPSA offer modified 
language for Article 11 of the NOPR LGIA that would implement these 
recommendations. Cal Cogen and the Energy Producers and Users Coalition 
claims that a term-based credit mechanism (i.e., one where the credits 
are paid out according to a fixed schedule) is preferable to the NOPR's 
proposed transmission-based mechanism.
    726. Edison Mission states that Articles 2 and 11 of the NOPR LGIA 
should be modified so that if an Interconnection Customer pays for 
Network Upgrades but the interconnection agreement is then terminated 
or the Generating Facility not constructed, the Interconnection 
Customer nonetheless receives payments for the upgrades it paid for, 
with the payments coming from other users of the Transmission System.
    727. Other commenters propose limiting the availability of credits. 
Dominion Resources argues that, if Network Upgrades funded by the 
Interconnection Customer are not used for output from the Generating 
Facility, a refund for such upgrades is inappropriate. Similarly, the 
Coalition for Pricing claims that proposed LGIP Section 11.4.2 can be 
read to suggest that the Interconnection Customer has some right to 
transmission credits as transmission service is taken anywhere on the 
Transmission Provider's system. It asks the Commission to clarify that 
this is not the case. The Alabama PSC argues that providing 
transmission credits only when transmission service is taken from an 
Interconnection Customer's Generating Facility would prevent the 
socialization of upgrade costs that do not benefit the network.

[[Page 49908]]

    728. Westconnect RTO and others argue that the Transmission 
Provider should credit the Interconnection Customer only for the 
``demand'' or ``return'' component of the otherwise applicable 
transmission charges, and not apply the credit to such costs as 
operations and maintenance, administrative and general, taxes, line 
losses, etc. Also, Westconnect RTO and BPA oppose the proposal in 
Section 12.3 of the NOPR LGIP that the Interconnection Customer receive 
transmission credits for expediting costs associated with constructing 
Network Upgrades out of sequence. TAPS states that the Interconnection 
Customer should receive a credit against its network transmission 
service bill based on the capacity of the Generating Facility, not the 
energy output of the unit. It argues that an energy output-based method 
of calculating the credit unfairly penalizes network customers and 
sends the wrong price signal, discouraging the construction of peaking 
units and the designation of such units as Network Resources.
    729. WEPCO states that the Commission must continue to mandate, as 
proposed in Article 11.4 of the NOPR LGIA, that rights to receive 
credits are fully assignable. It believes that this is crucial because 
in many instances the Interconnection Customer is not the transmission 
customer.
Commission Conclusion
    730. The Commission agrees with Dynegy and others that the 
Interconnection Customer should receive credits for transmission 
(delivery) service taken anywhere on the Transmission Provider's 
Transmission System and that credits should not be limited to service 
taken with respect to the Generating Facility at the point of receipt, 
as long as certain conditions are met. That is, as long as the 
Generating Facility has achieved commercial operation, continues to 
operate and there are unpaid credits outstanding, the Interconnection 
Customer should receive credits for all of the transmission charges 
that it pays, including charges for ``through'' transmission service. 
This is appropriate because it provides an additional vehicle by which 
the Transmission Provider can meet the requirement that the 
Interconnection Customer must receive a full refund of all amounts due 
within five years of the Commercial Operation Date. Accordingly, the 
Commission is removing from Article 11.4.1 of the Final Rule LGIA the 
following language: ``so long as Transmission Provider continues to 
receive payments for transmission service with respect to the 
Generating Facility during such period.''
    731. Edison Mission asks that Articles 2 and 11 of the NOPR LGIA be 
modified to allow the Interconnection Customer to receive credits for 
Network Upgrades that it has paid for if the interconnection agreement 
is terminated or the Generating Facility is not constructed. The 
Commission disagrees. In order to achieve an appropriate balance 
between the Interconnection Customer's risks and incentives, the 
Commission believes that the Interconnection Customer should receive a 
refund of the costs of Network Upgrades only if the Generating Facility 
has achieved commercial operation. Allowing the Interconnection 
Customer to avoid any responsibility for the cost of Network Upgrades 
needed for a Generating Facility that is never completed would 
improperly shift all risk of cost recovery to the Transmission Provider 
and its other customers. In addition, it would greatly reduce the 
Interconnection Customer's incentives to make good faith requests for 
Network Upgrades. Therefore, the Commission concludes that the 
Transmission Provider must provide a refund to the Interconnection 
Customer only after commercial operation of the Generating Facility has 
been demonstrated. However, if the Generating Facility fails to achieve 
commercial operation, but it or another Generating Facility is later 
constructed and makes use of the Network Upgrades, the Interconnection 
Customer would at that time be entitled to a refund of the investment 
that it made in the Network Upgrades.
    732. Westconnect RTO and others argue that the Transmission 
Provider should credit the Interconnection Customer only for the non-
usage sensitive ``demand'' or ``return'' component of the applicable 
transmission charges, presumably on the basis that this is the 
component that relates most directly to the cost of the investment for 
which the Interconnection Customer is to receive credits. The 
Commission clarifies that the Transmission Provider may decline to 
award credits for those transmission charges that are designed to 
recover out-of-pocket costs, such as the cost of line losses, 
associated with the delivery of the Generating Facility's output. The 
Commission notes, however, that all amounts paid by the Interconnection 
Customer toward Network Upgrades must be refunded within five years of 
the Commercial Operation Date. Thus, any reduction in the level of 
credit payments will only increase the cost of interest and the 
magnitude of the final cash payment that may be required.
    733. Westconnect RTO and BPA oppose the proposal in Section 12.3 of 
the NOPR LGIP that would provide the Interconnection Customer with a 
refund of the costs of expediting construction of Network Upgrades so 
that they can be placed in service out of sequence. The Commission is 
not changing this provision in the Final Rule LGIP. The sequence in 
which Network Upgrades would normally be constructed is based on the 
order in which requests are received. Although changing the order may 
increase or decrease the level of costs, the new level of costs is no 
less legitimate than the first. Thus, the Transmission Provider must 
refund to the Interconnection Customer the cost of constructing Network 
Upgrades regardless of the construction sequence.
    734. In response to WEPCO's concern about the assignability of 
refund rights, the Commission confirms that Final Rule LGIA Article 
11.4 provides that refund rights are fully assignable.
    735. Finally, the Commission clarifies how the crediting policy 
will work when the Interconnection Customer elects to build and retain 
ownership of Stand-Alone Network Upgrades. In such case, the 
Interconnection Customer is not entitled to a refund of its investment 
in any facilities in which it elects to retain ownership. If the 
Interconnection Customer constructs Stand-Alone Network Upgrades, and 
chooses not to transfer ownership to the Transmission Provider, it will 
not receive a refund but may enter into a cost-based lease agreement 
with the Transmission Provider that places the upgrades under the 
Transmission Provider's operation and control. The rates, terms and 
conditions of any such lease agreement are subject to the approval of 
the Commission.
Responsibility for the Costs Incurred by Affected Systems
    736. A number of commenters argue that the Final Rule should 
address directly the assignment of costs that may be incurred by 
Affected Systems when an Interconnection Customer obtains an 
interconnection.\118\ Entergy contends that, even if the Final Rule 
LGIA could bind an Affected System, the Commission's current 
interconnection pricing policies fail to establish the allocation of 
the costs of Network Upgrades among the Interconnection Customer, the 
interconnecting Transmission Provider, and the Affected System. 
Dominion

[[Page 49909]]

Resources recommends that Section 3.5 of the NOPR LGIP require the 
Interconnection Customer to be responsible for all costs incurred by 
the Transmission Provider in coordinating the interconnection request 
with the affected party, including all study costs. Reliant states that 
there is presently no mechanism that provides the Interconnection 
Customer with transmission credits for a contribution to the 
construction of Network Upgrades on third party systems. Reliant 
recommends that the Commission add to Section 3.5 of the NOPR LGIP 
language proposed by EPSA that addresses this omission. Mirant 
recommends that the Commission require the Transmission Provider to 
coordinate the provision of transmission credits associated with 
funding Network Upgrades on affected third party systems.
---------------------------------------------------------------------------

    \118\ As discussed above, an Affected System is a system other 
than that of the Transmission Provider that may be affected by the 
proposed interconnection.
---------------------------------------------------------------------------

    737. LADWP is concerned that the NOPR did not address how the 
Commission intends the financing and crediting to be implemented if the 
Interconnection Customer does not purchase transmission service on the 
Affected System.
Commission Conclusion
    738. The NOPR LGIP and NOPR LGIA included no pricing provisions 
that specifically address situations where Network Upgrades must be 
constructed on Affected Systems to protect the reliability of those 
systems. However, the Commission concurs with the commenters that state 
that the NOPR LGIA should be modified to expressly allow for refunds to 
be provided to the Interconnection Customer when such Network Upgrades 
must be constructed and the Interconnection Customer is required to pay 
for them. Therefore, the Commission modifies Article 11.4 of the Final 
Rule LGIA to make it applicable to all jurisdictional Affected System 
Operators on whose systems Network Upgrades are constructed to 
accommodate the Interconnection Customer's Interconnection Request. 
This means that, prior to the Commercial Operation Date, an Affected 
System Operator may require the Interconnection Customer to pay for all 
Interconnection Facilities and Network Upgrades constructed to 
accommodate the Interconnection Customer's Interconnection Request. 
Then, upon commencement of commercial operation, any Affected System 
Operator that has received payments from the Interconnection Customer 
must begin to refund to the Interconnection Customer the costs of 
Network Upgrades that the Interconnection Customer has paid. 
Furthermore, refunds are to be provided without regard to whether the 
Interconnection Customer has contracted for delivery service on the 
Affected System Operator's Transmission System. If the Interconnection 
Customer has not contracted for delivery service, and in the absence of 
another mutually agreeable payment schedule, refunds shall be provided 
by means of a uniform stream of monthly payments designed to fully 
reimburse the Interconnection Customer, with interest, over a five year 
period commencing with the Generating Facility's Commercial Operation 
Date.
    739. When the Interconnection Customer is required to pay for 
Network Upgrades on an Affected System, it must enter into an agreement 
with the Affected System Operator unless the payments are incorporated 
in the interconnection agreement that the Interconnection Customer 
signs with the Transmission Provider. Any agreement with an Affected 
System Operator must specify the terms governing payments to be made by 
the Interconnection Customer as well as the payment of refunds by the 
Affected System Operator. The Commission is revising proposed Article 
11.4.1 to incorporate this new requirement.
Policies Regarding Previously Approved Cost Allocations and Pricing 
Arrangements
    740. A number of commenters express their views regarding the 
NOPR's proposal to require that all Transmission Providers remove from 
their transmission rates the costs of Interconnection Facilities 
constructed for the Transmission Provider's own Generating Facilities, 
and to treat them as directly assigned, generation-related costs. 
Commenters also address the possible retroactive application of the 
pricing policy adopted in the Final Rule. Calpine and Mirant request 
that the Commission require that all Transmission Owners make 
compliance filings to remove the costs of Interconnection Facilities 
from existing transmission rates. The Arkansas PSC states that it does 
not object in principle to the proposal to remove such costs from 
transmission rates, but notes that this could shift additional costs 
onto the retail customers of regulated generation-owning utilities. It 
proposes that, if the cost-shifting burden is judged to be significant, 
a phase-in or modification may be appropriate. PSNM believes that the 
Commission's proposal to require all Transmission Providers to remove 
sole use facilities from their transmission rates currently in place 
resolves the lack of pricing comparability alleged by Interconnection 
Customers.
    741. PJMTO generally agrees with the NOPR's proposal to assign to 
the generator the costs of Interconnection Facilities, but requests 
that the Commission clarify that, to the extent this policy alters 
existing practices, it will apply prospectively and only affect 
interconnections that post-date the Final Rule. PJMTO states that, 
historically, transmission providers have used a variety of approaches 
to assign cost responsibility for Interconnection Facilities, claiming 
that some have rolled these costs into transmission rates while others 
have directly assigned the costs to the Interconnection Customer. PJMTO 
urges the Commission not to undercut the business assumptions of 
existing project sponsors or to require the Transmission Provider to 
refile transmission rates to remove any non-network costs that have 
been rolled in, and invoice Interconnection Customers for such removed 
costs. Exelon and Sithe express similar views and state that, since 
Order No. 888, numerous vertically integrated utilities have spun off 
their Generation Facilities to non-affiliated third parties. Exelon and 
Sithe believe that those parties would likely claim that their 
interconnection arrangements have been effectively grandfathered and 
that no interconnection costs that may have been rolled into base 
transmission rates are now recoverable from them. Exelon and Sithe 
argue this could lead to costly and time-consuming litigation.
    742. Calpine requests that the Commission find here that any policy 
that requires the Interconnection Customer to pay for Network Upgrades 
is unjust and unreasonable, and unless otherwise barred by explicit 
contract language, any Interconnection Customer should be permitted to 
have the facility cost allocation provisions of any existing agreement 
modified pursuant to Section 206 of the FPA to reflect the current 
interconnection pricing policies. However, Exelon and Sithe, using 
arguments similar to those above, recommend that any historical 
allocation of the costs of Network Upgrades that was agreed to by the 
parties and accepted by the Commission should not be disturbed now. 
Exelon and Sithe recommend that those costs be rolled into the 
transmission rate base only for new Interconnection Requests.
Commission Conclusion
    743. The Commission believes that, to ensure fully comparable 
treatment of all Generating Facilities, transmission rates should not 
include the costs of Interconnection Facilities. As stated in the NOPR, 
this policy is consistent with the Commission's current treatment of

[[Page 49910]]

generation step-up transformers, appropriately assigns the costs of 
Interconnection Facilities to the generation customers using them, and 
ensures that the Transmission Provider's own Generating Facilities and 
those of its competitors are treated comparably.
    744. However, the Commission is sympathetic to the concern of PJMTO 
and Exelon and Sithe that the Transmission Provider may have difficulty 
recovering the costs associated with Generating Facilities that it does 
not own, including those that it once owned but has since divested. 
Also, the Commission is concerned that the Transmission Provider may 
have difficulty identifying the interconnection-related costs of older 
Generating Facilities given that, historically, the Transmission 
Provider may have had no reason to segregate these costs from other 
transmission costs in its books of account. Therefore, the Commission 
is not adopting the NOPR's proposal to require the Transmission 
Provider to remove from its existing transmission rates the costs of 
all Interconnection Facilities constructed for its own Generating 
Facilities and to directly assign them as generation-related costs. 
Rather, the Commission here is imposing a more limited requirement. The 
Commission is requiring that the Transmission Provider remove from 
transmission rates only the costs of Interconnection Facilities 
constructed by the Transmission Provider after a certain date to 
interconnect Generating Facilities owned by the Transmission Provider 
on the effective date of this Final Rule. That date certain is March 
15, 2000, the date on which the Commission issued its order in 
Tennessee clarifying that interconnection is a separate component of 
transmission service, and that an Interconnection Customer may request 
interconnection separately from the delivery component of transmission 
service. That order effectively placed Transmission Providers on notice 
that the costs of Interconnection Facilities cannot be recovered in 
rates for transmission service. Thus, the Commission presumes that 
after March 15, 2000, any Interconnection Agreement signed by the 
Transmission Provider provides for the direct assignment of 
Interconnection Facility costs to the Interconnection Customer. The 
Commission also presumes that the Transmission Provider can identify 
the costs of any Interconnection Facilities constructed for its own 
Generating Facilities after March 15, 2000. In this Final Rule, the 
Commission is requiring the Transmission Provider, in its next filed 
transmission rate case, to remove such costs from transmission rates.
    745. With regard to the Arkansas PSC's concern about the impact of 
any cost shifting that may result from the reallocation of 
Interconnection Facility costs, we do not believe that the impact will 
be so great as to warrant a phase-in. Because the requirement that we 
are adopting here applies only to costs incurred after March 15, 2000, 
we expect the cost impact, if any, to be small. Furthermore, any cost 
impact will not occur until the Transmission Provider's next filed rate 
case.
    746. Finally, in response to Calpine, the Commission is not 
requiring in this Final Rule any changes to previously accepted 
interconnection agreements.
Miscellaneous Pricing Issues
    747. Dynegy argues that Article 4.6 of the NOPR LGIA should be 
clarified to include a more comprehensive listing of the possible 
services that the Interconnection Customer might be called upon to 
provide to the Transmission Provider under the express provisions of 
the LGIA. Dynegy submits that the Interconnection Customer would be 
required to have a Tariff on file with the Commission pursuant to 
Section 205 of the Federal Power Act for any service for which it seeks 
to charge the Transmission Provider. In the alternative, it recommends 
that the Commission clarify that this provision does not require the 
Interconnection Customer to forego the right to seek compensation for 
any services beyond the two listed.
    748. ACEEE states that it agrees with the Commission's general 
proposal on pricing, but identifies pricing issues faced by the 
Interconnection Customer that it believes can pose major barriers to 
interconnection. It claims that excessive standby charges, backup power 
rates, and insurance requirements have frequently been used to try to 
block an Interconnection Customer from interconnecting a new Generating 
Facility and competing on a comparable basis. It states that the 
Commission and others must address these pricing issues if electricity 
markets are to be fully accessible.
Commission Conclusion
    749. In response to Dynegy, the Commission clarifies that, while 
Articles 4.6 and 11.6 of the Final Rule LGIA provide that the 
Transmission Provider must compensate the Interconnection Customer for 
certain specific services that the latter provides, no provision of the 
Final Rule LGIA limits the right of the Interconnection Customer to 
seek compensation for any other services that the Transmission Provider 
may from time to time request from the Interconnection Customer.
    750. With regard to ACEEE's concerns about the rates for standby 
charges and backup power rates provided by the Transmission Provider to 
the Interconnection Customer, the rates for these services are a state 
jurisdictional retail rate issue. The Commission discusses insurance 
requirements in part II.C.8.a of this Preamble.
2. Interconnection Products and Scope of Service
    751. Scope of service, including in particular the definition and 
study requirements for the two Interconnection Service products 
proposed to be made available to Interconnection Customers, was perhaps 
the most heavily debated topic during the ANOPR phase of this 
proceeding. In addition, the controversial nature of this topic is 
reflected in the many pages that commenters devoted to it. These 
comments are addressed below.
Definition of Interconnection Products
    752. The LGIA NOPR provided for two Interconnection Service 
products from which the Interconnection Customer would have to choose: 
Energy Resource Interconnection Service, which is a basic or minimal 
interconnection service, and Network Resource Interconnection Service, 
which is a more flexible and comprehensive interconnection 
service.\119\ Neither is a transmission delivery service. Article 4 
(Scope of Service) of the NOPR LGIA defines these products and sets 
forth specific Interconnection Study requirements for each. This 
article also describes the relationship between delivery service and 
the Interconnection Services, as well as the rights and 
responsibilities that each Interconnection Service entails. In 
addition, Section 3.2 of the NOPR LGIP sets forth the procedure that 
the Interconnection Customer must use to select an Interconnection 
Service.
---------------------------------------------------------------------------

    \119\ During the ANOPR negotiating sessions EPSA and other 
Interconnection Customers negotiated to secure these two forms of 
service.
---------------------------------------------------------------------------

    753. As proposed, Energy Resource Interconnection Service would 
allow the Interconnection Customer to connect its Generating Facility 
to the Transmission System and be eligible to deliver its output using 
the existing firm or non-firm capacity of the Transmission System on an 
``as available'' basis. In an area with a bid-based energy market 
(e.g., ISO New

[[Page 49911]]

England, NYISO, or PJM), Energy Resource Interconnection Service would 
allow the Interconnection Customer to place a bid to sell into the 
market and the Generating Facility would be dispatched if the bid is 
accepted. In all other areas, no transmission delivery service would be 
assured, but the Interconnection Customer may obtain point-to-point 
transmission service or gain access to secondary network transmission 
service, pursuant to the Transmission Provider's Tariff. The 
Interconnection Studies to be performed for Energy Resource 
Interconnection Service would identify the Interconnection Facilities 
required as well as the Network Upgrades needed to allow the proposed 
Generating Facility to operate at full output. In addition, the 
Interconnection Studies would identify the maximum allowed output of 
the Generating Facility without Network Upgrades.
    754. In contrast, Network Resource Interconnection Service would 
require the Transmission Provider to undertake the Interconnection 
Studies and Network Upgrades needed to integrate the Generating 
Facility into the Transmission System in a manner comparable to that in 
which the Transmission Provider integrates its own generators to serve 
native load customers. If the Transmission Provider is an RTO or ISO 
with market-based congestion management, it would have to integrate the 
Generating Facility in the same manner as all other Network Resources.
    755. The Transmission Provider would study the Transmission System 
at peak load, under a variety of severely stressed conditions, to 
determine whether, with the Generating Facility at full output, the 
aggregate of generation in the local area can be delivered to the 
aggregate of load, consistent with the Transmission Provider's 
reliability criteria and procedures. Under this approach, the 
Transmission Provider would assume that some portion of the capacity of 
existing Network Resources is displaced by the output of the new 
Generating Facility.
    756. Network Resource Interconnection Service provides for all of 
the Network Upgrades that would be needed to allow the Interconnection 
Customer to designate its Generating Facility as a Network Resource and 
obtain Network Integration Transmission Service. Thus, once an 
Interconnection Customer has obtained Network Resource Interconnection 
Service, any future transmission service request for delivery from the 
Generating Facility would not require additional studies or Network 
Upgrades. However, Network Resource Interconnection Service itself does 
not convey any delivery service and the Interconnection Customer would 
not be required to identify a specific buyer (or sink). If the 
Interconnection Customer wishes to obtain the delivery component of 
transmission service, it would have to do so pursuant to the 
Transmission Provider's Tariff.
    757. Requests for long-term transmission service for deliveries 
outside the Transmission Provider's system may require additional 
Interconnection Studies and Network Upgrades. Network Resource 
Interconnection Service would allow the Generating Facility to be used 
to provide Ancillary Services and, should the Transmission System 
become congested, the Generating Facility would be subject to the same 
congestion management procedures that apply to all other Network 
Resources. Article 4.1.2.3 of the NOPR LGIA states that ``[d]epending 
on how the cost allocation issue is resolved, the [Interconnection 
Customer] may be allocated congestion rights based on the construction 
of upgrades.''
    758. Proposed LGIA Article 4.3 also provides for generator 
balancing service arrangements and refers to other articles that 
address payment for certain services provided by the Interconnection 
Customer.
Comments
    759. Several commenters, primarily Transmission Providers, object 
to the proposed requirement that Interconnection Customers be allowed 
to request Network Resource Interconnection Service. NRECA-APPA and 
others argue that, contrary to the Commission's assertion, Network 
Resource Interconnection Service would convey transmission delivery 
rights to the Interconnection Customer in the form of a permanent right 
to the future use of the Transmission System's delivery capacity. APS 
contends that Network Resource Interconnection Service would provide 
delivery service rights that are greater than any available under Order 
No. 888, and claims that Network Resource Interconnection Service may 
require a Transmission Provider to expand transmission capacity beyond 
any foreseeable needs of network load and to hold that capacity 
indefinitely. LG&E Energy believes that Network Resource 
Interconnection Service could result in substantial overbuilding of the 
Transmission System as a result of the requirement that transmission be 
upgraded to accommodate any Interconnection Customer taking Network 
Resource Interconnection Service to serve any load on the system. 
However, TAPS is concerned that Network Resource Interconnection 
Service does not provide for the capacity expansions that may be needed 
to allow network customers to access their Network Resources without 
congestion. It claims that the NOPR's treatment of Network Resource 
designation and network service is inconsistent with the OATT Network 
Integration Transmission Service, which requires a demonstration of 
load-specific deliverability from designated Network Resources. TAPS 
states that Network Resource Interconnection Service lacks such a 
deliverability test and, as a result, would be a service under which 
the Network Resource designation is meaningless from a load serving 
entity's point of view. It claims that while Network Resource 
Interconnection Service would grant some rights to the Interconnection 
Customer, it leaves the load serving entity to bear all the risk of 
congestion between its Network Resources and its load.
    760. PSNM notes that for an Interconnection Customer to secure 
delivery rights using Network Integration Transmission Service under 
the OATT, the Generating Facility must be designated as a Network 
Resource. The Interconnection Customer also must pay separately for 
point-to-point service when not providing service as a Network 
Resource. PSNM claims that the language in the NOPR LGIA would undo 
that requirement. Western objects to the fact that Network Resource 
Interconnection Service would impose no obligation on an 
Interconnection Customer to serve network load or to meet network 
operating obligations, such as providing Ancillary Services, and would 
not require an Interconnection Customer to participate in regional 
planning processes. Dairyland Power states that Article 4.1.2 of the 
NOPR LGIA seems to presuppose that Network Resource Interconnection 
Service may be used only in conjunction with Network Integration 
Transmission Service under the OATT, but the LGIA is not explicit. It 
asks the Commission to clarify the purpose of Network Resource 
Interconnection Service and how it may actually be used.
    761. Central Maine claims that the exact products or services 
required to be offered are not clearly defined. Industrial Energy 
asserts that the acknowledgment of potential congestion in the Network 
Resource Interconnection Service description seems to contradict the 
further

[[Page 49912]]

specifications in proposed LGIA Article 4.1.2.3, which appears to 
contemplate delivery from the Generating Facility within the 
Transmission Provider's Transmission System of any amount of capacity 
and/or energy up to the amount initially studied without additional 
studies or Network Upgrades. TANC recommends that the Commission 
replace the study provision requiring displacement of existing 
generation (NOPR LGIA Article 4.1.2.2) with appropriate technical 
guidelines and procedures for identifying resource displacement.
    762. LG&E Energy claims that the proposal is inconsistent with the 
Commission's proposed approach to Standard Market Design. It notes that 
the market designs of certain ISOs permit customers to designate any 
resource as a Network Resource, but do not require the Transmission 
System to be upgraded to ensure physical delivery of all generation 
resources to all loads. Rather, according to LG&E Energy, the effect of 
transmission congestion is reflected in locational energy prices. Also, 
the Midwest ISO states that it is not clear how Network Resource 
Interconnection Service would evolve as Standard Market Design is 
implemented. It believes that Network Resource Interconnection Service 
is more appropriate for an Interconnection Customer that wishes to 
designate its Generating Facility as a capacity resource in a market 
design where there is a capacity market. If there is not such a market, 
the Midwest ISO would support Energy Resource Interconnection Service 
alone as sufficient to provide for reliable interconnections, and allow 
for market-based mechanisms to support expansion of the Transmission 
System beyond minimum reliability needs. Both the Wisconsin PSC and 
American Wind Energy advise the Commission to defer consideration of 
Network Resource Interconnection Service until it can be evaluated in 
the context of Standard Market Design. Dairyland Power states that it 
is not clear how Network Resource Interconnection Service would fit 
with the new Network Access Service contemplated in the Commission's 
Standard Market Design rulemaking.
    763. Some commenters argue that there should be only one 
interconnection product and that product should define a minimum level 
of service. For example, ISO New England believes that its Minimum 
Interconnection Standard has resulted in equal treatment of new and 
incumbent generation owners and has resulted in a substantial number of 
new generators being interconnected onto the bulk power Transmission 
System in New England. It also states that the Minimum Interconnection 
Standard allows every generator owner, new and incumbent alike, the 
opportunity to participate in all markets.
    764. PG&E notes that, while Network Resource Interconnection 
Service requires the Transmission Provider to interconnect new plants 
in a manner comparable with that of other Network Resources, in 
California there are no Network Resources. PG&E asks the Commission to 
explain how this Interconnection Service would apply in areas where no 
network transmission service is available. Central Maine argues that 
the definition of products and services should be left to regional 
practices.
    765. Xcel states that the description of Network Resource 
Interconnection Service appears to assume the Transmission Provider's 
system is the same as its Control Area. However, with the development 
of large transmission networks subject to an RTO's OATT, it may not be 
possible to actually deliver the capacity and energy of any individual 
generator to a network load on a huge regional network. The Midwest ISO 
recommends that, if Network Resource Interconnection Service is 
retained as part of the Final Rule, an Interconnection Customer within 
a large footprint RTO like the Midwest ISO should be allowed to select 
specific zones (or Control Areas) in which it would be eligible to be a 
designated Network Resource.
Commission Conclusion
    766. Article 4 of the NOPR LGIA did not adequately convey the 
Commission's intent, particularly with regard to the characteristics 
that distinguish the two proposed interconnection products and the 
rights and responsibilities that each entails. Many of the commenters' 
concerns can be addressed by improving the clarity and accuracy in the 
Final Rule provisions concerning scope of services and interconnection 
products. Therefore, as described below, the Commission modifies the 
text of proposed LGIA Article 4 and provides the following 
clarifications.
    767. Both Energy Resource Interconnection Service and Network 
Resource Interconnection Service provide for the construction of 
Network Upgrades that would allow the Interconnection Customer to flow 
the output of its Generating Facility onto the Transmission Provider's 
Transmission System in a safe and reliable manner. However, contrary to 
the assertions of several commenters, neither Energy Resource 
Interconnection Service nor Network Resource Interconnection Service in 
and of itself conveys the right to do so. Moreover, neither type of 
Interconnection Service constitutes a reservation of transmission 
capacity. The Interconnection Customer, load or other market 
participant would have to request either point-to-point or Network 
Integration Transmission Service under the Transmission Provider's OATT 
in order to receive the delivery service that is a prerequisite to 
flowing power onto the system. When an Interconnection Customer that 
has chosen either Energy Resource Interconnection Service or Network 
Resource Interconnection Service later requests firm point-to-point 
delivery service, additional Network Upgrades may be required, 
depending on the availability of transmission capacity to deliver power 
to the delivery point.
    768. Network Resource Interconnection Service is intended to 
provide the Interconnection Customer with an interconnection of 
sufficient quality to allow the Generating Facility to qualify as a 
designated Network Resource on the Transmission Provider's system 
without additional Network Upgrades. This means that Network Resource 
Interconnection Service entitles the Generating Facility to be treated 
in the same manner as the Transmission Provider's own resources for 
purposes of assessing whether aggregate supply is sufficient to meet 
aggregate load within the Transmission Provider's Control Area, or 
other area customarily used for generation capacity planning. Thus, 
with Network Resource Interconnection Service, the Interconnection 
Customer would be eligible to obtain Network Service under the 
Transmission Provider's OATT, or network access service under the 
Tariff of an RTO or ISO, without the need for additional Network 
Upgrades.
    769. However, contrary to the views of some commenters, Network 
Resource Interconnection Service does not necessarily provide the 
Interconnection Customer with the capability to physically deliver the 
output of its Generating Facility to any particular load on the system 
without incurring congestion costs. Depending on the location of the 
load for which the Generating Facility serves as a designated Network 
Resource, it may be required to participate in a redispatch procedure, 
or other non-discriminatory congestion management process, such as 
locational marginal pricing. Network Upgrades required under Network 
Resource Interconnection Service integrate the Generating Facility into 
the

[[Page 49913]]

Transmission System in a manner that ensures that aggregate generation 
can meet aggregate load while satisfying regional reliability criteria 
and generation capacity planning requirements. However, these upgrades 
do not necessarily eliminate congestion.
    770. In response to ISO New England and the Midwest ISO, the 
Commission is not limiting the Interconnection Customer's 
interconnection alternatives to a single option that meets only a 
minimum interconnection standard. In general, such a policy would not 
provide an interconnection that meets the standard that the 
Transmission Provider uses to interconnect its own generators. The 
Commission notes, however, that in regions where the Transmission 
System is operated by an independent entity, the Commission allows 
flexibility, as discussed in part II.C.1 (Interconnection Pricing 
Policy). For example, an independent entity may determine, subject to 
Commission approval, that the designation of Network Resources is not 
necessary (which, PG&E points out, is the case in California).
    771. The Commission recognizes that the Transmission Provider's 
Transmission System may not comprise a single Control Area, as several 
commenters point out. If the Transmission Provider operates more than 
one Control Area, it may limit the network service that is available to 
an Interconnection Customer taking Network Resource Interconnection 
Service to the Control Area where the Generating Facility is located. 
If the Interconnection Customer wishes to serve load in another Control 
Area, it must submit a separate request for transmission service to 
that other area, and it would be subject to the pricing provisions of 
the Transmission Provider's OATT for that service.
    772. The Commission further clarifies that, if the Generating 
Facility of an Interconnection Customer taking Network Resource 
Interconnection Service is selected by a load as a designated Network 
Resource, it will be required to meet all network operating obligations 
that the OATT imposes upon Network Resources generally. If an 
Interconnection Customer's Generating Facility has not been designated 
as a Network Resource by any load, it cannot be required to provide 
Ancillary Services except to the extent such requirements extend to all 
generators that are similarly situated.
    773. Finally, in response to Dairyland Power and others, the 
Commission notes that an RTO or ISO may propose in its tariff filing to 
modify the definition and scope of the available interconnection 
products to accommodate its market.
Pricing of Network Resource Interconnection Service
    774. Some commenters express concern over the application of the 
proposed interconnection pricing policy to Network Resource 
Interconnection Service. For example, Progress Energy and the Alabama 
PSC believe that an Interconnection Customer taking Network Resource 
Interconnection Service should pay a reservation charge for reserved 
but unused transmission capacity on the Transmission Provider's 
Transmission System. Progress Energy believes that such an approach 
would properly allocate the cost of the transmission capacity being 
reserved for the Interconnection Customer until a customer actually 
begins paying for transmission service for output from the 
Interconnection Customer's Generating Facility.
    775. Entergy states that the requirement that a Transmission 
Provider offer Network Resource Interconnection Service should not be 
included in the Final Rule until the Commission has thoroughly analyzed 
the effects of providing such service. If this service is required, 
however, Entergy recommends that a Transmission Provider be compensated 
by any Interconnection Customer electing this service, as the service 
prevents a Transmission Provider from achieving the maximum use of its 
Transmission System due to the standing transmission reservation that 
it claims is granted to an Interconnection Customer under this service. 
The Coalition for Pricing recommends that the Interconnection Customer 
be required to commit to pay for Network Resource Interconnection 
Service for a specific term long enough to protect other customers from 
economic harm. It further recommends that, if the Interconnection 
Customer is not required to commit to a specific term of Network 
Resource Interconnection Service, it should at a minimum be required to 
pay some amount up front to cover ongoing expenses associated with the 
upgrades constructed if service is cancelled after a short time.
    776. NRECA-APPA states that coupling Network Resource 
Interconnection Service with the Commission's current interconnection 
pricing policy will cause customers to bear much of the cost of Network 
Upgrades while having no right to use the resulting transmission 
delivery capability.
    777. However, American Transmission opposes any special charges for 
Network Resource Interconnection Service and believes that commenters' 
criticisms that this service confers too great an advantage on the new 
Interconnection Customer are overstated. It believes the provision 
should be designed to put the independent generation owner on a 
competitive footing equal to that of incumbent owners. If the 
Commission is persuaded that the proposed policy provides an undue 
advantage to the new Interconnection Customer, the solution lies in 
adjusting the service description, not in imposing a surcharge.
Commission Conclusion
    778. The Commission is not requiring the Interconnection Customer 
to pay a reservation fee for the delivery component of transmission 
service as a condition for receiving Network Resource Interconnection 
Service. As explained above, Network Resource Interconnection Service 
does not convey to the Interconnection Customer a reservation of 
transmission capacity or the right to begin taking firm or non-firm 
transmission service on the Transmission Provider's system. Rather, its 
purpose, as stated in proposed LGIA Article 4.1.2.1, is to provide the 
Network Upgrades needed to integrate the Interconnection Customer's 
Generating Facility into the Transmission System in a manner that is 
comparable to that in which the Transmission Provider integrates its 
own resources or other Network Resources. When the Interconnection 
Customer does take transmission service, it (or its power sales 
customer) will be required to pay appropriate rates, subject to the 
crediting provisions of Article 11.4 of the Final Rule LGIA. To charge 
the Interconnection Customer an additional reservation fee, as several 
commenters propose, would violate the Commission's prohibition against 
``and'' pricing. Nevertheless, Network Resource Interconnection Service 
does not guarantee that the Interconnection Customer can physically 
deliver its output to any load. This means that, depending on the 
location of its power sales customer, the Interconnection Customer may 
be required to pay congestion or redispatch costs.
    779. Finally, in response to NRECA-APPA, the Commission emphasizes 
that any capacity created by the Network Upgrades constructed on the 
Interconnection Customer's behalf is available for use by all customers 
on an equal basis. The Final Rule only requires that, once the 
Interconnection Customer has paid for the Network Upgrades needed to 
integrate its Generating Facility, it cannot be charged

[[Page 49914]]

again for any additional upgrades that may be needed to continue to 
qualify as a Network Resource.
Study Requirements for Network Resource Interconnection Service
    780. Article 4.1.2.2 of the NOPR LGIA described the