[Federal Register: September 18, 2003 (Volume 68, Number 181)]
[Notices]               
[Page 54727]
From the Federal Register Online via GPO Access [wais.access.gpo.gov]
[DOCID:fr18se03-50]                         

-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

 
Notice of Application for Extension of Time to Commence and 
Complete Construction and Soliciting Comments, Motions To Intervene, 
and Protests

September 11, 2003.
    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection:
    a. Application Type: Extension of Time to Commence and Complete 
Construction.
    b. Project No: 11214-010.
    c. Date Filed: August 19, 2003.
    d. Applicant: Southwestern Electric Cooperative, Inc. (Applicant or 
Southwestern).
    e. Name and Location of Project: The Carlyle Hydroelectric Project 
is to be located at the U.S. Army Corps of Engineers' Carlyle Dam on 
the Kaskaskia River near the City of Carlyle in Clinton County, 
Illinois.
    f. Filed Pursuant to: Public Law 108-12.
    g. Applicant Contacts: For Southwestern: Michael Postar, Duncan, 
Weinberg, Genzer & Pembroke, P.C., 1615 M Street NW., Suite 800, 
Washington, DC 20036, (202) 467-6370. For the City of Carlyle: Donald 
H. Clarke, Law Offices of GKRSE, 1500 K St. NW., Suite 330, Washington, 
DC 20005, (202) 408-5400.
    h. FERC Contact: James Hunter, (202) 502-6086.
    i. Deadline for filing comments, protests, and motions to 
intervene: October 10, 2003.
    All documents (original and eight copies) should be filed with: 
Magalie R. Salas, Secretary, Federal Energy Regulatory Commission, 888 
First Street NE., Washington, DC 20426. Comments, protests, and 
interventions may be filed electronically via the Internet in lieu of 
paper; see 18 CFR 385.2001(a)(1)(iii) and the instructions on the 
Commission's Web site under the ``e-Filing'' link. The Commission 
strongly encourages electronic filings. Please include the project 
number (P-11214-010) on any comments or motions filed.
    The Commission's Rules of Practice and Procedure require all 
interveners filing a document with the Commission to serve a copy of 
that document on each person in the official service list for the 
project. Further, if an intervener files comments or documents with the 
Commission relating to the merits of an issue that may affect the 
responsibilities of a particular resource agency, they must also serve 
a copy of the documents on that resource agency.
    j. Description of Application: Public Law 108-12 authorizes the 
Commission to reinstate the license for the Carlyle Project as of June 
24, 2000, and to extend the time during which the licensee is required 
to commence the construction of the project for three consecutive 2-
year periods beyond June 26, 2001. The Applicant accordingly requests 
that the deadline for commencement of project construction be extended 
to July 26, 2005, and that the deadline for completion of construction 
also be extended. Southwestern and the City of Carlyle, Illinois, have 
reached an agreement whereby they will cooperate in seeking 
reinstatement of the license, extension of the construction schedule, 
and transfer of the license from Southwestern to Carlyle. Public notice 
of the joint application for approval of transfer of the license, also 
filed on August 19, 2003, will be issued at such time as the license is 
reinstated.
    k. This filing is available for review at the Commission in the 
Public Reference Room or may be viewed on the Commission's Web site at 
http://www.ferc.gov using the ``eLibrary'' link. Enter the docket 
number excluding the last three digits in the docket number field to 
access the document. For assistance, call toll-free 1-866-208-3676 or 
e-mail FERCOnlineSupport@ferc.gov . For TTY, call (202) 502-8659. A 
copy is also available for inspection and reproduction at the address 
in item h. above.
    l. Individuals desiring to be included on the Commission's mailing 
list should so indicate by writing to the Secretary of the Commission.
    m. Comments, Protests, or Motions to Intervene--Anyone may submit 
comments, a protest, or a motion to intervene in accordance with the 
requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, 
.214. In determining the appropriate action to take, the Commission 
will consider all protests or other comments filed, but only those who 
file a motion to intervene in accordance with the Commission's Rules 
may become a party to the proceeding. Any comments, protests, or 
motions to intervene must be received on or before the specified 
comment date for the particular application.
    n. Filing and Service of Responsive Documents--Any filings must 
bear in all capital letters the title ``COMMENTS'', ``PROTEST'', OR 
``MOTION TO INTERVENE'', as applicable, and the Project Number of the 
particular application to which the filing refers. Any of the above-
named documents must be filed by providing the original and the number 
of copies provided by the Commission's regulations to: The Secretary, 
Federal Energy Regulatory Commission, 888 First Street NE., Washington, 
DC 20426. A copy of any motion to intervene must also be served upon 
each representative of the Applicant specified in the particular 
application.
    o. Agency Comments: Federal, State, and local agencies are invited 
to file comments on the described application. A copy of the 
application may be obtained by agencies directly from the Applicant. If 
an agency does not file comments within the time specified for filing 
comments, it will be presumed to have no comments. One copy of an 
agency's comments must also be sent to the Applicant's representatives.

Magalie R. Salas,
Secretary.
[FR Doc. 03-23807 Filed 9-17-03; 8:45 am]

BILLING CODE 6717-01-P