[Federal Register: January 6, 2004 (Volume 69, Number 3)]
[Rules and Regulations]               
[Page 533-534]
From the Federal Register Online via GPO Access [wais.access.gpo.gov]
[DOCID:fr06ja04-23]                         

-----------------------------------------------------------------------

DEPARTMENT OF HOMELAND SECURITY

Coast Guard

46 CFR Parts 401 and 404

[USCG-2002-11288]
RIN 2115-AG30

 
Rates for Pilotage on the Great Lakes

AGENCY: Coast Guard, DHS.

ACTION: Correction to interim rule.

-----------------------------------------------------------------------

SUMMARY: This document contains corrections to the interim rule [USCG-
2002-11288], which was published in the Federal Register on December 
12, 2003 (68 FR 69564). The interim rule provides a partial rate 
adjustment for pilotage on the Great Lakes. A review of this interim 
rule after publication identified an omission of a figure in a table 
and two erroneous tables.

DATES: Effective on January 6, 2004.

FOR FURTHER INFORMATION CONTACT: For questions on this correction 
notice, call or e-mail Paul Wasserman, Director, Office of Great Lakes 
Pilotage (G-MW-1), U.S. Coast Guard, at telephone 202-267-2856, or 

SUPPLEMENTARY INFORMATION:

Need for Correction

    The interim rule, as published, contained an erroneous figure for 
the total of District One's Projected Return on Investment. This was 
due to the omission of a number in the column designated as ``Total 
District One.'' There were also two incorrect tables placed in Step 6a. 
The tables should have been ``Table B.--District Two--Projected Return 
on Investment'' and Table C.--District Three--Projected Return on 
Investment.''

Correction of Publication

0
Accordingly, the publication on December 12, 2003, of the interim rule 
[USCG-2002-11288], FR Doc. 03-30711, is corrected as follows:
0
1. On page 69574, in Table A.--District One Step 10, change the figure 
under Total District One from $10,000 to $100,000.
0
2. On page 69574, remove ``Table B.--District Two--Adjustment 
Determination'' and ``Table C.--District Three--Adjustment 
Determination'' and, in their place, add the following tables.

                             Table B.--District Two--Projected Return on Investment
----------------------------------------------------------------------------------------------------------------
                                                                                                  Total District
                             Step                                   Area 4           Area 5             2
----------------------------------------------------------------------------------------------------------------
1............................................................        $705,015       $1,461,069       $2,166,084
2............................................................        (365,292)        (446,468)        (811,760)
3............................................................        (477,218)        (930,701)      (1,407,919)
4............................................................        (137,495)          83,900          (53,595)
5............................................................               0                0                0
6............................................................        (137,495)          83,900          (53,595)
7............................................................               0                0                0

[[Page 534]]


8............................................................        (137,495)          83,900          (53,595)
9............................................................        (137,495)          83,900          (53,595)
10...........................................................          89,734          140,353          230,087
11...........................................................          (1.593)           0.559           (0.280)
----------------------------------------------------------------------------------------------------------------


                            Table C.--District Three--Projected Return on Investment
----------------------------------------------------------------------------------------------------------------
                                                                                                  Total District
                    Step                           Area 6           Area 7           Area 8             1
----------------------------------------------------------------------------------------------------------------
1...........................................      $1,540,306       $1,119,819       $1,030,693       $3,690,818
2...........................................        (739,550)        (292,739)        (508,441)      (1,540,730)
3...........................................      (1,099,676)        (625,315)        (715,827)      (2,440,818)
4...........................................        (298,920)         201,765         (193,575)        (290,730)
5...........................................               0                0                0                0
6...........................................        (298,920)         201,765         (193,575)        (290,730)
7...........................................               0                0                0                0
8...........................................        (298,920)         201,765         (193,575)        (290,730)
9...........................................        (298,920)         201,765         (193,575)        (290,730)
10..........................................         111,668           83,752           83,752          279,172
11..........................................          (2.677)           2.409           (2.311)          (1.041)
----------------------------------------------------------------------------------------------------------------


    Dated: December 30, 2003.
Joseph J. Angelo,
Acting Assistant Commandant for Marine Safety, Security and 
Environmental Protection.
[FR Doc. 04-226 Filed 1-5-04; 8:45 am]