[Federal Register: November 2, 2004 (Volume 69, Number 211)]
[Notices]
[Page 63514-63516]
From the Federal Register Online via GPO Access [wais.access.gpo.gov]
[DOCID:fr02no04-34]
=======================================================================
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
[Docket No. PP-89-1]
Notice of Intent To Prepare an Environmental Impact Statement and
To Conduct Public Scoping Meetings and Notice of Floodplain and
Wetlands Involvement; Bangor Hydro-Electric Company
AGENCY: Department of Energy (DOE).
ACTION: Notice of intent to prepare an environmental impact statement
and to conduct public scoping meetings, and notice of floodplain and
wetlands involvement.
-----------------------------------------------------------------------
SUMMARY: Bangor Hydro-Electric Company (BHE) has applied to DOE to
amend Presidential Permit PP-89, which authorizes BHE to construct a
single-circuit 345,000-volt (345-kV) electric transmission line across
the U.S. international border in the vicinity of Baileyville, Maine.
The proposed transmission line would originate at BHE's existing
Orrington Substation, located in Orrington, Maine, and extend eastward
approximately 85 miles to the international border between the United
States and Canada where it would connect with similar facilities to be
owned by New Brunswick Power Corporation (NB Power). DOE has determined
that amendment of the Presidential permit would constitute a major
Federal action that may have a significant impact upon the environment
within the meaning of the National Environmental Policy Act of 1969
(NEPA). For this reason, DOE intends to prepare an environmental impact
statement (EIS) entitled, ``The Northeast Reliability Interconnect''
(DOE/EIS-0372), to address potential environmental impacts from the
proposed action and the range of reasonable alternatives.
The purpose of this Notice of Intent is to inform the public about
the proposed action, announce plans to conduct three public scoping
meetings in the vicinity of the proposed transmission line, invite
public participation in the scoping process, and solicit public
comments for consideration in establishing the scope and content of the
EIS. Because the proposed project may involve an action in a floodplain
or wetland, the draft EIS will include a floodplain and wetlands
assessment and the final EIS or record of decision will include a
floodplain statement of findings in accordance with DOE regulations for
compliance with floodplain and wetlands environmental review
requirements (10 CFR part 1022).
DATES: DOE invites interested agencies, organizations, Native American
tribes, and members of the public to submit comments or suggestions to
assist in identifying significant environmental issues and in
determining the appropriate scope of the EIS. The public scoping period
starts with the publication of this notice in the Federal Register and
will continue until December 2, 2004. Written and oral comments will be
given equal weight, and DOE will consider all comments received or
postmarked by December 2, 2004, in defining the scope of this EIS.
Comments received or postmarked after that date will be considered to
the extent practicable.
Dates for the public scoping meetings are:
1. November 17, 2004; 7 p.m. to 9 p.m., Baileyville, Maine.
2. November 18, 2004; 1 p.m. to 3 p.m., South Lincoln, Maine.
3. November 18, 2004; 7 p.m. to 9 p.m., Brewer, Maine.
Requests to speak at a public scoping meeting(s) should be received
by Dr. Jerry Pell at the addresses indicated below on or before
November 10, 2004. Requests to speak may also be made at the scoping
meetings when registering for the meetings. However, persons who
submitted advance requests to speak will be given priority if time
should be limited during the meetings.
ADDRESSES: Written comments or suggestions on the scope of the EIS and
requests to speak at the scoping meeting(s) should be addressed to: Dr.
Jerry Pell, Office of Fossil Energy (FE-27), U.S. Department of Energy,
1000 Independence Avenue, SW., Washington DC 20585; facsimile: 202-318-
7761, or electronic mail at Jerry.Pell@hq.doe.gov.
Please note that regular postal mail to DOE tends to be delayed
because of anthrax screening. In order to avoid these delays, if you
wish to comment by mail, we suggest that your response be submitted
either by using overnight service, or that your letter first be sent to
us by fax or e-mail, and then followed by regular mailing of the
original documents.
The locations of the scoping meetings are:
1. Woodland Elementary School, 23 Fourth Avenue, Baileyville,
Maine.
2. Mattanawcook Academy, 33 Reed Drive, Lincoln, Maine.
3. Jeff's Catering Banquet & Convention Center, East West
Industrial Park, 5 Coffin Avenue, Brewer, Maine.
FOR FURTHER INFORMATION CONTACT: For information on the proposed
project or to receive a copy of the Draft EIS when it is issued,
contact Dr. Pell by any of the means listed in the ADDRESSES section of
this notice. The main text of the BHE application is on the DOE Fossil
Energy Web site at http://fossil.energy.gov/programs/electricityregulation
, under Pending Proceedings and PP-89-1. The
complete BHE application, including associated maps and drawings, can
be obtained by contacting Dr. Jerry Pell as noted in the ADDRESSES
section above. Additional information and a description of the proposed
project may be found on the BHE project Web site at http://www.bhe.com/nri
.
For general information on the DOE NEPA review process, contact:
Carol M. Borgstrom, Director, Office of NEPA Policy and Compliance
(EH-42), U.S. Department of Energy, Washington, DC 20585; phone: 202-
586-4600 or leave a message at 800-472-2756; facsimile: 202-586-7031.
[[Page 63515]]
SUPPLEMENTARY INFORMATION:
Background and Need for Agency Action
Executive Order 10485, as amended by Executive Order 12038,
requires that a Presidential permit be issued by DOE before electric
transmission facilities may be constructed, operated, maintained, or
connected at the U.S. international border. The Executive Order
provides that a Presidential permit may be issued after a finding that
the proposed project is consistent with the public interest and after
concurrence by the Departments of State and Defense. In determining
consistency with the public interest, DOE considers the impacts of the
proposed project on the reliability of the U.S. electric power system
and on the environment. The regulations implementing the Executive
Order have been codified at 10 CFR 205.320-205.329. Issuance of the
permit indicates that there is no Federal objection to the project, but
does not mandate that the project be completed.
BHE originally applied to DOE for a Presidential permit on December
16, 1988. DOE published a notice of that application in the Federal
Register on January 19, 1989 (54 FR 2201), and a Notice of Intent to
Prepare an Environmental Impact Statement and to Conduct Public Scoping
Meetings in the Federal Register on May 22, 1989 (54 FR 22006). In
December 1993, DOE published the draft EIS titled, ``Construction and
Operation of the Proposed Bangor Hydro-Electric Company's Second 345-kV
Transmission Tie Line to New Brunswick.'' (DOE/EIS-0166). DOE issued a
final EIS in August 1995, and in a record of decision signed on January
18, 1996 (61 FR 2244), decided to grant Presidential Permit PP-89.
On January 22, 1996, DOE issued Presidential Permit PP-89
authorizing BHE to construct, operate, maintain, and connect a 345-kV
electric transmission line that would extend eastward approximately 85
miles from BHE's existing Orrington Substation to the U.S.-Canada
border near Baileyville, Maine. At the border, the proposed
transmission line was to connect to similar facilities to be built by
NB Power, a Crown corporation of Canada's Province of New Brunswick.
However, the authorized facilities have not been constructed.
On September 30, 2003, BHE applied to DOE to amend Presidential
Permit PP-89 to allow for the construction of the project along a
different route than those routes analyzed in the 1995 EIS. Since the
issuance of PP-89, a natural gas transmission line has been constructed
by Maritimes & Northeast Pipeline, L.L.C., in the same general vicinity
as the BHE project and in a corridor approved by the State of Maine
Department of Environmental Protection. The Board of Environmental
Protection, Maine's primary environmental review entity, now has
indicated its preference for BHE to consolidate the location of all
utility facilities in the area by constructing the proposed electric
transmission line along a route more closely aligned with the existing
pipeline corridor.
The international transmission line now proposed by BHE is
identical in design to the line originally analyzed in the 1995 EIS and
authorized in Presidential Permit PP-89. It would be a single-circuit
345-kV alternating current transmission line consisting of two overhead
shield wires and three phases with two conductors per phase. The
transmission line is proposed to have a thermal capacity of at least
1,000 megawatts. The line would originate at BHE's existing Orrington
Substation and extend eastward approximately 85 miles, crossing the
U.S.-Canada border near Baileyville, Maine. In Canada, the BHE
facilities would interconnect with similar facilities to be owned by NB
Power and continue approximately 60 miles to the switchyard at the
Point Lepreau Nuclear Generating Station. Canada's National Energy
Board authorized construction of the Canadian portion of the facilities
in May 2003. The proposed transmission line project that will be the
subject of this EIS differs from the original project only in the
proposed routes between the Orrington Substation and the international
border crossing near Baileyville, Maine.
BHE has identified four alternative routes for constructing the
proposed transmission line: (1) The Consolidated Corridors route; (2)
the Previously Permitted route; (3) the Maine Electric Power Company
(MEPCO) South route; and (4) BHE's Preferred route. BHE states that it
has identified its preferred alternative by working with
representatives of large landowners, operators of nearby electric and
pipeline utility facilities, state and Federal agencies, local tribes,
and interest groups to develop a matrix of environmental factors to
consider for route selection. BHE also states that it considered
stakeholder and public input it received through outreach efforts, mail
communications, and electronically via the BHE project Web site. BHE
states that the environmental factors it considered in selecting its
preferred alternative included land use, wetlands and water bodies,
flora, fauna, fisheries, recreational and visual considerations, and
cultural resources.
All alternative routes originate at the Orrington Substation and
generally parallel an existing MEPCO transmission line and Maritimes &
Northeast Pipeline for approximately 12 miles until they reach
Blackman's Stream.
Consolidated Corridors route: From Blackman's Stream, this route
continues northward paralleling the existing MEPCO transmission line
and the Maritimes & Northeast Pipeline for an additional 8 miles until
reaching Stud Mill Road. At Stud Mill Road, this route turns eastward
generally paralleling Stud Mill Road and the Maritimes & Northeast
Pipeline right-of-way for a distance of approximately 65 miles. The
line would cross the international border at Baileyville, Maine, at the
location previously permitted in PP-89.
Previously Permitted Route: From Blackman's Stream, this route
turns eastward for approximately 3.5 miles before turning northward
until it meets Stud Mill Road. This route then generally follows Stud
Mill Road, but deviates from it in several locations before it crosses
the international border at Baileyville, Maine.
MEPCO South Route: From Blackman's Stream, this route continues
north to Chester along the MEPCO line. The route then heads east
roughly paralleling State Route 6 before crossing the international
border at Baileyville, Maine.
BHE's Preferred route: This route incorporates a majority of the
Consolidated Corridors route but deviates from it in two locations
based on input received from various stakeholders. BHE's preferred
route follows the three other alternative routes from Orrington
Substation until it reaches Blackman's Stream. From Blackman's Stream,
this route follows the Previously Permitted route until Stud Mill Road,
at which point it then follows the Consolidated Corridors route until
the vicinity of the Maritimes & Northeast Pipeline Baileyville
Compressor Station. Near the compressor station, the line deviates to
the north of the Consolidated Corridors route to maintain approximately
3600 feet of separation between the transmission line and the
Baileyville Compressor Station.
All four alternative routes would cross primarily commercial forest
in regrowth. All four alternative routes also would cross 100-year
floodplains and wetlands, including some waterfowl and wading bird
habitat. The MEPCO South Route would cross the Penobscot River. All
alternatives would cross both
[[Page 63516]]
perennial and intermittent streams, and may cross the Machias, East
Machias and Narraguagus Rivers or associated tributaries, depending on
the alternative. Project activities would include clearing rights-of-
way and access roads, digging tower footings, setting transmission
towers, seeding/mulching and other erosion control work, and hanging
transmission wires.
The EIS will consider the environmental impacts of constructing the
proposed transmission line along these alternative routes and the No
Action alternative. Under the No Action alternative, the EIS will
analyze the impacts associated with ``no action.'' Because the proposed
action is the amendment of Presidential Permit PP-89 to allow
construction of the proposed transmission line over a different route
from that authorized by the permit, ``no action'' means that the permit
would not be amended and that the original permit would remain in
effect. This would mean that the proposed transmission line could be
constructed only over the Previously Permitted route.
However, the EIS will consider any additional reasonable
alternatives that result from comments received in response to the
scoping process described in this notice. One alternative already
identified by DOE is the rescission of Presidential Permit PP-89.
Rescission of the permit would mean that the permitted transmission
line could not be constructed. This alternative will address the
environmental impacts that are reasonably foreseeable to occur if
Presidential Permit PP-89 is rescinded but no new permit is issued.
However, this would not necessarily result in maintenance of the status
quo or no environmental impacts. It is possible that BHE and/or NB
Power may take other actions to achieve the purpose of this project if
the permitted or proposed transmission line is not built.
Identification of Environmental Issues
The purpose of this notice is to solicit comments and suggestions
for consideration in the preparation of the EIS. As background for
public comment, this notice contains a list of potential environmental
issues that DOE has tentatively identified for analysis. This list is
not intended to be all-inclusive or to imply any predetermination of
impacts. Following is a preliminary list of issues that may be analyzed
in the EIS:
(1) Socioeconomic and recreational impacts of development of the
land tracts and their subsequent uses;
(2) Impacts on protected, threatened, endangered, or sensitive
species of animals or plants or their critical habitats, including the
bald eagle, Atlantic salmon, and shortnose sturgeon;
(3) Impacts on floodplains and wetlands;
(4) Impacts on archaeological, cultural, or historic resources;
(5) Impacts on human health and safety;
(6) Impacts on existing and future land uses;
(7) Visual impacts; and
(8) Disproportionately high and adverse impacts on minority and
low-income populations, also known as environmental justice
considerations.
Scoping Process
Interested parties are invited to participate in the scoping
process, both to refine the preliminary alternatives and environmental
issues to be analyzed in depth, and to eliminate from detailed study
those alternatives and environmental issues that are not feasible or
pertinent. The scoping process is intended to involve all interested
agencies (Federal, state, county, and local), public interest groups,
Native American tribes, businesses, and members of the public.
Potential cooperating agencies may include but may not be limited to
the U.S. Department of the Interior's Fish and Wildlife Service and
Bureau of Indian Affairs, the National Marine Fisheries Service, the
State of Maine Department of Environmental Protection, and the U.S.
Army Corps of Engineers. Public scoping meetings will be held at the
locations, dates, and times indicated above under the DATES and
ADDRESSES sections. These scoping meetings will be informal. The
presiding officer will establish only those procedures needed to ensure
that everyone who wishes to speak has a chance to do so and that DOE
understands all issues and comments. Speakers will be allocated
approximately 5 minutes for their oral statements. Depending upon the
number of persons wishing to speak, the presiding officer may allow
longer times for representatives of organizations. Consequently,
persons wishing to speak on behalf of an organization should identify
that organization in their request to speak. Persons who have not
submitted a request to speak in advance may register to speak at the
scoping meeting(s), but advance requests are encouraged. Meetings will
begin at the times specified and will continue until all those present
who wish to participate have had an opportunity to do so. Should any
speaker desire to provide for the record further information that
cannot be presented within the designated time, such additional
information may be submitted in writing by the date listed in the DATES
section. Oral, written, and electronic (i.e., by facsimile or by e-
mail) comments will be impartially considered and given equal weight by
DOE.
Draft EIS Schedule and Availability
The Draft EIS is scheduled to be issued in June 2005, at which time
its availability will be announced in the Federal Register and local
media and public comments again will be solicited. The Draft EIS will
be made available for public inspection at several public libraries and
reading rooms in Maine, and notice of these locations will be provided
in the Federal Register and local media at a later date. However,
readers are cautioned that many considerations enter into the
preparation of the Draft EIS and the actual issuance date may differ
from the above.
People who do not wish to submit comments or suggestions at this
time but who would like to receive a copy of the Draft EIS for review
and comment when it is issued should notify Dr. Pell as provided in the
ADDRESSES section above.
Issued in Washington, DC, on October 27, 2004.
Steven V. Cary,
Acting Assistant Secretary, Office of Environment, Safety and Health.
[FR Doc. 04-24404 Filed 11-1-04; 8:45 am]
BILLING CODE 6450-01-P