ENVIRONMENTAL PROTECTION AGENCY
[Petition IV-2003-1; FRL-7842-2]
Clean Air Act Operating Permit Program; Petition for Objection to
State Operating Permit for Hercules, Inc.; Brunswick (Glynn County), GA
AGENCY: Environmental Protection Agency (EPA).
ACTION: Notice of final order on petition to object to a state
operating permit.
-----------------------------------------------------------------------
SUMMARY: Pursuant to section 505(b)(2) of the Clean Air Act (the Act)
and 40 CFR 70.8(d), the EPA Administrator signed an order, dated
November 10, 2004, denying a petition to object to a state operating
permit issued by the Georgia Environmental Protection Division (EPD) to
Hercules, Inc. (Hercules) located in Brunswick, Glynn County, Georgia.
This order constitutes final action on the petition submitted by the
Glynn Environmental Coalition and the Center for a Sustainable Coast
(Petitioners). Pursuant to section 505(b)(2) of the Act, any person may
seek judicial review in the United States Court of Appeals for the
appropriate circuit within 60 days of this notice under section 307 of
the Act.
ADDRESSES: Copies of the final order, the petition, and all pertinent
information relating thereto are on file at the following location: EPA
Region 4, Air, Pesticides and Toxics Management Division, 61 Forsyth
Street SW., Atlanta, Georgia 30303-8960. The final order is also
available electronically at the following address: http://www.epa.gov/region7/programs/artd/air/title5/petitiondb/petitions/
hercules--
decision2003.pdf.
FOR FURTHER INFORMATION CONTACT: Art Hofmeister, Air Permits Section,
EPA Region 4, at (404) 562-9115 or hofmeister.art@epa.gov.
SUPPLEMENTARY INFORMATION: The Act affords EPA a 45-day period to
review and, as appropriate, to object to operating permits proposed by
state permitting authorities under title V of the Act, 42 U.S.C. 7661-
7661f. Section 505(b)(2) of the Act and 40 CFR 70.8(d) authorize any
person to petition the EPA Administrator to object to a title V
operating permit within 60 days after the expiration of EPA's 45-day
review period if EPA has not objected on its own initiative. Petitions
must be based only on objections to the permit that were raised with
reasonable specificity during the public comment period provided by the
state, unless the petitioner demonstrates that it was impracticable to
raise these issues during the comment period or the grounds for the
issues arose after this period.
On January 23, 2003, the Administrator received a petition
requesting that EPA object to a state title V operating permit issued
by EPD to Hercules. The Petitioners maintain that the Hercules permit
is inconsistent with the Act because: (1) The permit fails to include
all applicable requirements, specifically Georgia Rule 391-3-
1-.02(2)(a)1. and (2) the permit fails to assure compliance with said
rule.
On November 10, 2004, the Administrator issued an order denying
this petition. The order explains the reasons behind EPA's conclusion
that the Petitioners failed to demonstrate that the Hercules permit is
not in compliance with the requirements of the Act on the grounds
raised.
Dated: November 18, 2004.
J.I. Palmer, Jr.,
Regional Administrator, Region 4.
[FR Doc. 04-26080 Filed 11-23-04; 8:45 am]
BILLING CODE 6560-50-P