DEPARTMENT OF DEFENSE
48 CFR Part 236
[DFARS Case 2003-D035]
Defense Federal Acquisition Regulation Supplement; Construction
and Architect-Engineer Services
AGENCY: Department of Defense (DoD).
ACTION: Final rule.
-----------------------------------------------------------------------
SUMMARY: DoD has issued a final rule amending the Defense Federal
Acquisition Regulation Supplement (DFARS) to update text pertaining to
selection of firms for architect-engineer contracts. This rule is a
result of a transformation initiative undertaken by DoD to dramatically
change the purpose and content of the DFARS.
EFFECTIVE DATE: December 15, 2004.
FOR FURTHER INFORMATION CONTACT: Mr. Euclides Barrera, Defense
Acquisition Regulations Council, OUSD(AT&L)DPAP(DAR), IMD 3C132, 3062
Defense Pentagon, Washington, DC 20301-3062. Telephone (703) 602-0296;
facsimile (703) 602-0350. Please cite DFARS Case 2003-D035.
SUPPLEMENTARY INFORMATION:
A. Background
DFARS Transformation is a major DoD initiative to dramatically
change the purpose and content of the DFARS. The objective is to
improve the efficiency and effectiveness of the acquisition process,
while allowing the acquisition workforce the flexibility to innovate.
The transformed DFARS will contain only requirements of law, DoD-wide
policies, delegations of FAR authorities, deviations from FAR
requirements, and policies/procedures that have a significant effect
beyond the internal operating procedures of DoD or a significant cost
or administrative impact on contractors or offerors. Additional
information on the DFARS Transformation initiative is available at
http://www.acq.osd.mil/dp/dars/transf.htm.
This final rule is a result of the DFARS Transformation initiative.
The changes in this rule--
Revise DFARS 236.602-1 to remove procedures for
establishment of evaluation criteria in the selection of firms for
architect-engineer contracts. This text has been relocated to the new
DFARS companion resource, Procedures, Guidance, and Information (PGI),
available at http://www.acq.osd.mil/dpap/dars/pgi.
Remove unnecessary text on preselection boards and
selection authorities at DFARS 236.602-2 and 236.602-4.
Amend DFARS 236.604 to reflect replacement of Standard
Form 254, Architect--Engineer and Related Services Questionnaire, with
Standard Form 330, Architect-Engineer Qualifications.
DoD published a proposed rule at 69 FR 35568 on June 25, 2004. DoD
received no comments on the proposed rule. Therefore, DoD has adopted
the proposed rule as a final rule without change.
This rule was not subject to Office of Management and Budget review
under Executive Order 12866, dated September 30, 1993.
B. Regulatory Flexibility Act
DoD certifies that this final rule will not have a significant
economic impact on a substantial number of small entities within the
meaning of the Regulatory Flexibility Act, 5 U.S.C. 601, et seq.,
because the changes in the rule represent no substantive change to
policy with regard to selection of firms for architect-engineer
contracts.
C. Paperwork Reduction Act
The Paperwork Reduction Act does not apply because the rule does
not impose any information collection requirements that require the
approval of the Office of Management and Budget under 44 U.S.C. 3501,
et seq.
List of Subjects in 48 CFR Part 236
Government procurement.
Michele P. Peterson,
Executive Editor, Defense Acquisition Regulations Council.
0
Therefore, 48 CFR Part 236 is amended as follows:
0
1. The authority citation for 48 CFR Part 236 continues to read as
follows:
Authority: 41 U.S.C. 421 and 48 CFR Chapter 1.
PART 236--CONSTRUCTION AND ARCHITECT-ENGINEER CONTRACTS
0
2. Section 236.602-1 is revised to read as follows:
236.602-1 Selection criteria.
(a) Establish the evaluation criteria before making the public
announcement required by FAR 5.205(c) and include the criteria and
their relative order of importance in the announcement. Follow the
procedures at PGI 236.602-1(a).
236.602-2 and 236.602-4 [Removed]
0
3. Sections 236.602-2 and 236.602-4 are removed.
0
4. Section 236.604 is amended by revising paragraph (c)(ii) to read as
follows:
236.604 Performance evaluation.
* * * * *
(c) * * *
(ii) File and use the DD Form 2631, Performance Evaluation
(Architect-Engineer), in a manner similar to the SF 330, Architect-
Engineer Qualifications, Part II.