[Federal Register: May 13, 2004 (Volume 69, Number 93)]
[Notices]
[Page 26588-26589]
From the Federal Register Online via GPO Access [wais.access.gpo.gov]
[DOCID:fr13my04-99]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. ER04-782-000-341-002, et al.]
Vermont Electric Cooperative, Inc., et al.; Electric Rate and
Corporate Filings
May 6, 2004.
The following filings have been made with the Commission. The
filings are listed in ascending order within each docket
classification.
1. Vermont Electric Cooperative, Inc.
[Docket No. ER04- 341-002]
Take notice that on April 30, 2004, Vermont Electric Cooperative,
Inc. (VEC) submitted a compliance filing pursuant to the Commission's
order issued February 12, 2004 in Docket No. ER04-341-001, 106 FERC ]
61,131, (2004). VEC has requested an effective date of April 1, 2004.
Comment Date: May 21, 2004.
2. Midwest Independent Transmission System Operator, Inc.
[Docket No. ER04-782-000]
Take notice that on April 30, 2004, Midwest Independent
Transmission System Operator, Inc. (Midwest ISO), pursuant to section
205 of the Federal Power Act and section 35.12 of the Commission's
regulations, 18 CFR 35.12 (2003), submitted for filing an
Interconnection and Operating Agreement among Blue Sky Wind Farm LLC,
the Midwest ISO and American Transmission Company LLC. Midwest ISO has
requested an effective date of April 20, 2004.
Midwest ISO states that a copy of this filing was served on all
parties.
Comment Date: May 21, 2004.
3. Midwest Independent Transmission System Operator, Inc.
[Docket No. ER04-783-000]
Take notice that on April 30, 2004, Midwest Independent
Transmission System Operator, Inc. (Midwest ISO) pursuant to section
205 of the Federal Power Act and section 35.12 of the Commission's
regulations, 18 CFR 35.12 (2003), submitted for filing an
Interconnection and Operating Agreement among Green Field Wind Farm
LLC, the Midwest ISO and American Transmission Company LLC. Midwest ISO
has requested an effective date of April 20, 2004.
Midwest ISO states that a copy of this filing was served on all
parties.
Comment Date: May 21, 2004.
4. Tampa Electric Company
[Docket No. ER04-784-000]
Take notice that on April 30, 2004, Tampa Electric Company (Tampa
Electric) tendered for filing revised rate schedule sheets containing
updated rates for emergency interchange service and scheduled/short-
term firm interchange service under its interchange contracts with each
of 17 other utilities. Tampa Electric also tendered for filing revised
sheets for inclusion in its open access transmission tariff (OATT) that
contain an updated system average transmission loss percentage. Tampa
Electric requests that the revised rate schedule and tariff sheets be
made effective on May 1, 2004, and therefore requests waiver of the
Commission's notice requirement.
Tampa Electric states that a copy of the filing has been served
upon each of the parties to the affected interchange contracts and each
customer under its OATT, as well as the Florida and Georgia Public
Service Commissions.
Comment Date: May 21, 2004.
5. Commonwealth Edison Company
[Docket No. ER04-790-000]
Take notice that on April 30, 2004, Commonwealth Edison Company
(ComEd) tendered for filing an executed Standard Large Generator
Interconnection Agreement between ComEd and Power Partners Midwest,
LLC, for Power Partners' Kinnikinnik Wind Farm generating facility.
ComEd has requested an effective date of May 1, 2004.
Comment Date: May 21, 2004.
6. Tampa Electric Company
[Docket No. ER04-792-000]
Take notice that on April 30, 2004, Tampa Electric Company (Tampa
Electric) tendered for filing open access transmission tariff sheets
containing the Large Generator Interconnection Procedures and the Large
Generator Interconnection Agreement that the Commission adopted in
Order Nos. 2003 and 2003-A, Standardization of Generator
Interconnection Agreements and Procedures. Tampa Electric proposes that
the tariff sheets be made effective on April 30, 2004.
Tampa Electric states that copies of the filing have been served on
the customers under Tampa Electric's open access transmission tariff
and the Florida Public Service Commission.
Comment Date: May 21, 2004.
7. Fairless Energy, LLC
[Docket No. ER04-797-000]
Take notice that on April 30, 2004, Fairless Energy, LLC (Fairless)
tendered
[[Page 26589]]
for filing a revenue requirement and rate schedule pursuant to which
Fairless will provide Reactive Supply and Voltage Control from
Generation Sources Service pursuant to Schedule 2 of the PJM
Interconnection, L.L.C. (PJM) Open Access Transmission Tariff. The rate
schedule is Fairless Energy, LLC, Rate Schedule FERC No. 2. The Company
requests an effective date of the later of July 1, 2004 or the day
after the first block of facilities goes into commercial operation.
Fairless also tendered for filing a First Revised Rate Schedule FERC
No. 2 which adds charges for a second block of facilities and asks for
an effective date of the day after the second block of facilities goes
into commercial operation.
Fairless states that a copy of the filing was served on PJM, PECO
Energy Company and the relevant state utility commissions.
Comment Date: May 21, 2004.
8. Wabash Valley Power Association, Inc.
[Docket No. ER04-802-000]
Take notice that on April 30, 2004, Wabash Valley Power
Association, Inc. (Wabash Valley) tendered for filing its initial rate
filing. Wabash Valley states that it will become a FERC-jurisdictional
public utility on July 1, 2004, by virtue of its repurchase of its
outstanding U.S. Department of Agriculture Rural Utilities Service
debt. Therefore, in compliance with Section 205 of the Federal Power
Act (16 U.S.C. ( 824d), Wabash Valley is filing with the Commission all
of its rates, terms and conditions of service.
Wabash Valley state that copies of this filing were served upon
Wabash Valley's Members, Duke Vermillion, LLC, PSI Energy, Inc.,
Cinergy Corp., Indiana Municipal Power Agency, Northern Indiana Public
Service Company, Steel Dynamics, Inc. and the public utility
commissions in Illinois, Indiana, Michigan and Ohio.
Comment Date: May 21, 2004.
9. PJM Interconnection, L.L.C.
[Docket No. ER04-807-000]
Take notice that on April 30, 2004, PJM Interconnection, L.L.C.
(PJM) submitted for filing certain conforming changes to the PJM Open
Access Transmission Tariff and PJM Operating Agreement related to the
integration of Commonwealth Edison Company (including Commonwealth
Edison Company of Indiana, Inc.) (ComEd) into PJM on May 1, 2004, as
established by the Commission's April 27, 2004 order in Docket Nos.
ER04-521-002, et al., 107 FERC ] 61,087. PJM has requested an effective
date for these changes of May 1, 2004.
PJM states that copies of this filing have been served on all PJM
members and utility regulatory commissions in the PJM Region and on all
persons listed on the official service lists compiled by the Secretary
for these proceedings.
Comment Date: May 21, 2004.
Standard Paragraph
Any person desiring to intervene or to protest this filing should
file with the Federal Energy Regulatory Commission, 888 First Street,
NE., Washington, DC 20426, in accordance with Rules 211 and 214 of the
Commission's Rules of Practice and Procedure (18 CFR 385.211 and
385.214). Protests will be considered by the Commission in determining
the appropriate action to be taken, but will not serve to make
protestants parties to the proceeding. Any person wishing to become a
party must file a motion to intervene. All such motions or protests
should be filed on or before the comment date, and, to the extent
applicable, must be served on the applicant and on any other person
designated on the official service list. This filing is available for
review at the Commission or may be viewed on the Commission's Web site
at http://www.ferc.gov, using the ``FERRIS'' link. Enter the docket
number excluding the last three digits in the docket number filed to
access the document. For assistance, call (202) 502-8222 or TTY, (202)
502-8659. Protests and interventions may be filed electronically via
the Internet in lieu of paper; see 18 CFR 385.2001(a)(1)(iii) and the
instructions on the Commission's Web site under the ``e-Filing'' link.
The Commission strongly encourages electronic filings.
Magalie R. Salas,
Secretary.
[FR Doc. E4-1110 Filed 05-12-04; 8:45 am]
BILLING CODE 6717-01-P