DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 7321-018]
Erie Boulevard Hydropower, L.P.; Notice of Application Tendered
for Filing With the Commission, Soliciting Additional Study Requests,
and Establishing Procedural Schedule for Relicensing and a Deadline for
Submission of Final Amendments
December 3, 2004.
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection.
a. Type of Application: Subsequent License.
b. Project No.: 7321-018.
c. Date Filed: November 26, 2004.
d. Applicant: Erie Boulevard Hydropower, L.P.
e. Name of Project: Macomb Project.
f. Location: On the Salmon River in Franklin County, near Malone,
New York. The project does not occupy Federal lands.
g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791 (a)-825(r).
h. Applicant Contact: Jerry L. Sabattis, Erie Boulevard Hydropower,
L.P., 225 Greenfield Parkway, Suite 201, Liverpool, NY 13088, (315)
413-2787.
i. FERC Contact: John Smith, (202) 502-8972 or john.smith@ferc.gov.
j. Cooperating Agencies: We are asking Federal, State, local, and
tribal agencies with jurisdiction and/or special expertise with respect
to environmental issues to cooperate with us in the preparation of the
environmental document. Agencies who would like to request cooperating
status should follow the instructions for filing comments described in
item l below.
k. Pursuant to (4.32(b)(7) of 18 CFR of the Commission's
regulations, if any resource agency, Indian Tribe, or person believes
that an additional scientific study should be conducted in order to
form an adequate factual basis for a complete analysis of the
application on its merit, the resource agency, Indian Tribe, or person
must file a request for a study with the Commission not later than 60
days from the date of filing of the application, and serve a copy of
the request on the applicant.
l. Deadline for filing additional study requests and requests for
cooperating agency status: January 24, 2005.
All documents (original and eight copies) should be filed with:
Magalie R. Salas, Secretary, Federal Energy Regulatory Commission, 888
First Street, NE., Washington, DC 20426.
The Commission's Rules of Practice require all intervenors filing
documents with the Commission to serve a copy of that document on each
person on the official service list for the project. Further, if an
intervenor files comments or documents with the Commission relating to
the merits of an issue that may affect the responsibilities of a
particular resource agency, they must also serve a copy of the document
on that resource agency.
Additional study requests and requests for cooperating agency
status may be filed electronically via the Internet in lieu of paper.
The Commission strongly encourages electronic filings. See 18 CFR
385.2001(a)(1)(iii) and the instructions on the Commission's Web site
(http://www.ferc.gov) under the ``eFiling'' link.
m. This application is not ready for environmental analysis at this
time.
n. The existing Macomb Project consists of: (1) A 106-foot-long,
32-foot-high concrete gravity overflow-type dam having a spillway crest
elevation of 570.7 feet above mean sea level; (2) a 38-foot-long, 25-
foot-high intake structure along each bank; (3) a 6-foot-diameter, 60-
foot-long, riveted-steel, gated waste tube along each bank; (4) a 14-
acre reservoir with a net storage capacity of 14 acre-feet at the
spillway crest elevation; (5) a 6.5-foot-diameter, 60-foot-long,
riveted-steel, concrete-encased, gated pipeline along the left (south)
bank; (6) a powerhouse containing one 1,000-kilowatt horizontal Francis
turbine; (7) a 370-foot-long, 34.5-kilovolt transmission line; and (8)
appurtenant facilities. The applicant estimates that the total average
annual generation would be 5,660 megawatthours.
o. A copy of the application is available for review at the
Commission in the Public Reference Room or may be viewed on the
Commission's Web site at http://www.ferc.gov using the ``eLibrary''
link. Enter the docket number excluding the last three digits in the
docket number field to access the document. For assistance, contact
FERC Online Support at FERCOnlineSupport@ferc.gov or toll-free at 1-
866-208-3676, or for TTY, (202) 502-8659. A copy is also available for
inspection and reproduction at the address in item h above.
You may also register online at http://www.ferc.gov/docs-filing/esubscription.asp
to be notified via e-mail of new filings and
issuances related to this or other pending projects. For assistance,
contact FERC Online Support.
p. With this notice, we are initiating consultation with the New
York State
[[Page 75059]]
Historic Preservation Officer (SHPO), as required by Section 106,
National Historic Preservation Act, and the regulations of the Advisory
Council on Historic Preservation, 36 CFR 800.4.
q. Procedural schedule and final amendments: The application will
be processed according to the following Hydro Licensing Schedule.
Revisions to the schedule will be made as appropriate.
Issue Acceptance or Deficiency Letter--January 2005
Issue Scoping Document--February 2005
Notice of application is ready for environmental analysis--May 2005
Notice of the availability of the EA--November 2005
Ready for Commission's decision on the application--December 2005
Final amendments to the application must be filed with the
Commission no later than 30 days from the issuance date of the notice
of ready for environmental analysis.
Magalie R. Salas,
Secretary.
[FR Doc. E4-3665 Filed 12-14-04; 8:45 am]