[Federal Register: August 8, 2005 (Volume 70, Number 151)]
[Rules and Regulations]
[Page 45534]
From the Federal Register Online via GPO Access [wais.access.gpo.gov]
[DOCID:fr08au05-9]
-----------------------------------------------------------------------
DEPARTMENT OF HOMELAND SECURITY
Coast Guard
33 CFR Part 117
[CGD01-05-080]
Drawbridge Operation Regulations: Long Island, New York Inland
Waterway From East Rockaway Inlet to Shinnecock Canal, NY
AGENCY: Coast Guard, DHS.
ACTION: Notice of temporary deviation from regulations and request for
comment.
-----------------------------------------------------------------------
SUMMARY: The Commander, First Coast Guard District, has issued a
temporary deviation from the drawbridge operation regulations to test
an alternate drawbridge operation regulation for the Wantagh State
Parkway Bridge, at mile 16.1, across Goose Creek, New York. Under this
temporary 90-day deviation the bridge will open on signal once an hour,
on the half hour, between 7:30 a.m. and 8:30 p.m. on Saturday, Sunday,
and Federal holidays after a 30-minute advance notice is given. At all
other times the bridge will open on signal after a 30-minute advance
notice is given by calling the number posted at the bridge.
DATES: This deviation is effective from August 15, 2005 through
November 12, 2005. Comments must reach the Coast Guard on or before
November 30, 2005.
ADDRESSES: You may mail comments to Commander (obr), First Coast Guard
District Bridge Branch, One South Street, Battery Park Building, New
York, New York, 10004, or deliver them to the same address between 7
a.m. and 3 p.m., Monday through Friday, except, Federal holidays. The
telephone number is (212) 668-7165. The First Coast Guard District,
Bridge Branch, maintains the public docket for this rulemaking.
Comments and material received from the public, as well as documents
indicated in this preamble as being available in the docket, will
become part of this docket and will be available for inspection or
copying at the First Coast Guard District, Bridge Branch, 7 a.m. to 3
p.m., Monday through Friday, except Federal holidays.
Request for Comments
We encourage you to participate in this rulemaking by submitting
comments or related material. If you do so, please include your name
and address, identify the docket number for this rulemaking (CGD01-05-
080), indicate the specific section of this document to which each
comment applies, and give the reason for each comment. Please submit
all comments and related material in an unbound format, no larger than
8 \1/2\ by 11 inches, suitable for copying. If you would like to know
if they reached us, please enclose a stamped, self-addressed postcard
or envelope. We will consider all comments and material received during
the comment period. We may change this rule in view of them.
FOR FURTHER INFORMATION CONTACT: Judy Leung-Yee, Project Officer, First
Coast Guard District, at (212) 668-7195.
SUPPLEMENTARY INFORMATION: The Wantagh State Parkway Bridge has a
vertical clearance in the closed position of 16 feet at mean high water
and 19 feet at mean low water. The existing drawbridge operation
regulations are listed at 33 CFR 117.799(i).
The bridge owner, Jones Beach State Park requested a temporary
deviation from the drawbridge operation regulations to test an
alternate drawbridge operation schedule to help better balance the
needs between vehicular land traffic and marine vessel traffic.
Under this 90-day temporary deviation, in effect from August 15,
2005 through November 12, 2005, the Wantagh State Parkway Bridge at
mile 16.1, across Goose Creek, shall operate as follows:
The bridge shall open on signal once an hour, on the half hour,
between 7:30 a.m. and 8:30 p.m. on Saturday, Sunday, and Federal
holidays after a 30-minute advance notice is given by calling the
number posted at the bridge.
At all other times the bridge shall open on signal after a 30-
minute advance notice is given by calling the number posted at the
bridge.
This deviation from the operating regulations is authorized under
33 CFR 117.43.
Dated: July 28, 2005.
Gary Kassof,
Bridge Program Manager, First Coast Guard District.
[FR Doc. 05-15564 Filed 8-5-05; 8:45 am]
BILLING CODE 4910-15-P