[Federal Register: January 28, 2005 (Volume 70, Number 18)]
[Rules and Regulations]               
[Page 4014]
From the Federal Register Online via GPO Access [wais.access.gpo.gov]
[DOCID:fr28ja05-8]                         

-----------------------------------------------------------------------

DEPARTMENT OF HOMELAND SECURITY

Coast Guard

33 CFR Part 117

[CGD01-04-157]

 
Drawbridge Operation Regulations: Newtown Creek, Dutch Kills, 
English Kills, and Their Tributaries, NY

AGENCY: Coast Guard, DHS.

ACTION: Notice of temporary deviation from regulations.

-----------------------------------------------------------------------

SUMMARY: The Commander, First Coast Guard District, has issued a 
temporary deviation from the drawbridge operation regulations for the 
Metropolitan Avenue Bridge, mile 3.4, across English Kills at New York 
City, New York. Under this temporary deviation the bridge may remain 
closed from 6 a.m. to midnight on the following days: January 19 
through January 21; January 26 through January 28; and January 31 
through February 5, 2005. This temporary deviation is necessary to 
facilitate bridge maintenance.

DATES: This deviation is effective from January 19, 2005 through 
February 5, 2005.

FOR FURTHER INFORMATION CONTACT: Judy Leung-Yee, Project Officer, First 
Coast Guard District, at (212) 668-7195.

SUPPLEMENTARY INFORMATION: The Metropolitan Avenue Bridge has a 
vertical clearance in the closed position of 10 feet at mean high water 
and 15 feet at mean low water. The existing drawbridge operation 
regulations are listed at 33 CFR 117.801(e).
    The owner of the bridge, New York City Department of Transportation 
(NYCDOT), requested a temporary deviation from the drawbridge operation 
regulations to facilitate rehabilitation repairs at the bridge. The 
bridge must remain in the closed position to perform these repairs.
    Under this temporary deviation the NYCDOT Metropolitan Avenue 
Bridge may remain in the closed position from 6 a.m. through midnight 
on the following days: January 19 through January 21; January 26 
through January 28; and from January 31 through February 5, 2005.
    This deviation from the operating regulations is authorized under 
33 CFR 117.35, and will be performed with all due speed in order to 
return the bridge to normal operation as soon as possible.

    Dated: January 12, 2005.
Gary Kassof,
Bridge Program Manager, First Coast Guard District.
[FR Doc. 05-1561 Filed 1-27-05; 8:45 am]

BILLING CODE 4910-15-P