[Federal Register: February 22, 2005 (Volume 70, Number 34)]
[Rules and Regulations]
[Page 8514]
From the Federal Register Online via GPO Access [wais.access.gpo.gov]
[DOCID:fr22fe05-8]
=======================================================================
-----------------------------------------------------------------------
DEPARTMENT OF HOMELAND SECURITY
Coast Guard
33 CFR Part 117
[CGD01-05-013]
Drawbridge Operation Regulations: Raritan River, NJ
AGENCY: Coast Guard, DHS.
ACTION: Notice of temporary deviation from regulations.
-----------------------------------------------------------------------
SUMMARY: The Commander, First Coast Guard District, has issued a
temporary deviation from the drawbridge operation regulations for the
New Jersey Transit Rail Operations (NJTRO) Bridge, at mile 0.5, across
the Raritan River, at Perth Amboy, New Jersey. Under this temporary
deviation the bridge may remain in the closed position beginning at 11
p.m. on Friday through 6 p.m. on Saturday for four weekends between
March 18 and May 14, 2005. This temporary deviation is necessary to
facilitate scheduled maintenance at the bridge.
DATES: This deviation is effective from March 18, 2005 through May 14,
2005.
FOR FURTHER INFORMATION CONTACT: Joe Arca, Project Officer, First Coast
Guard District, at (212) 668-7165.
SUPPLEMENTARY INFORMATION: The NJTRO Bridge has a vertical clearance in
the closed position of 8 feet at mean high water and 13 feet at mean
low water. The existing drawbridge operation regulations are listed at
33 CFR 117.747.
The bridge owner, New Jersey Transit Rail Operations (NJTRO),
requested a temporary deviation from the drawbridge operation
regulations to facilitate necessary scheduled bridge maintenance,
replacement of miter rails, at the bridge. The bridge must remain in
the closed position during the performance of these repairs.
Under this temporary deviation the NJTRO Bridge may remain in the
closed position beginning at 11 p.m. on Friday through 6 p.m. on
Saturday for four weekends as follows: March 18 through March 19; April
1 through April 2; April 15 through April 16; and April 29 through
April 30, 2005. Two alternate weekend closure dates, May 6 through May
7, and May 13 through May 14, 2005, have been authorized in the event
that inclement weather requires cancellation of any of the above dates.
This deviation from the operating regulations is authorized under
33 CFR 117.35, and will be performed with all due speed in order to
return the bridge to normal operation as soon as possible.
Dated: February 11, 2005.
Gary Kassof,
Bridge Program Manager, First Coast Guard District.
[FR Doc. 05-3255 Filed 2-18-05; 8:45 am]
BILLING CODE 4910-15-P