[Federal Register: May 19, 2005 (Volume 70, Number 96)]
[Notices]               
[Page 28924-28926]
From the Federal Register Online via GPO Access [wais.access.gpo.gov]
[DOCID:fr19my05-56]                         

-----------------------------------------------------------------------

DEPARTMENT OF DEFENSE

Department of the Army; Corps of Engineers

 
Intent to Prepare a Draft Environmental Impact Statement (DEIS) 
for the Nourishment of 7.25 Miles of Beach, the Repositioning of the 
New River Inlet Channel, and the Implementation of an Inlet Management 
Plan, in North Topsail Beach, Onslow County, NC

AGENCY: Department of the Army, U.S. Army Corps of Engineers, DoD.

ACTION: Notice of intent.

-----------------------------------------------------------------------

SUMMARY: The U.S. Army Corps of Engineers (COE), Wilmington District, 
Wilmington Regulatory Field Office has received a request for 
Department of the Army authorization, pursuant to Section 404 of the 
Clean Water Act and Section 10 of the Rivers and Harbor Act, from the 
Town of North Topsail Beach to nourish approximately 7.25 miles of 
beachfront to protect residential homes and town infrastructures, and 
to implement an inlet management plan with the New River Inlet to 
control the positioning of the inlet channel. The new channel will be 
centrally located perpendicular to the adjacent shorelines of North 
Topsail Beach and Onslow Beach. The proposed source of the material for 
the nourishment will be dredged from offshore borrow area(s) and from 
the repositioning of the inlet. The placement of beach fill along the 
Town's shoreline would result in the initial widening of the beach by 
50 to 100 feet. The widened beach would be maintained through a program 
of undefined periodic beach nourishment events with the material 
extracted primarily from the New River Inlet.
    The ocean shoreline in the Town of North Topsail Beach encompasses 
approximately 11.1 miles along the northern end of Topsail Island. 
Currently, the U.S. Army Corps of Engineers is developing a Federal 
shoreline protection plan for parts of North Topsail Beach. This 
Federal plan will only cover 3.85 miles of the southern part of the 
beach. The remaining 7.25-miles of North Topsail Beach, with the 
exception of two small areas, is located within the Coastal Barrier 
Resource System (CBRS), which prohibits the expenditure of Federal 
funds that would encourage development. Therefore, the Town is pursuing 
to develop this non-Federal shoreline protection plan that will 
preserve existing development and infrastructure along the 7.25 miles 
of shoreline.
    The channel through New River Inlet has been maintained by the COE 
for commercial and recreational boating interest for over 55 years. The 
COE is authorized to maintain the channel in the inlet to a depth of 6 
feet mean low water (mlw) over a width of 90 feet.

DATES: A public scoping meeting for the Draft EIS will be held at Dixon 
High School located on Highway 17, on June 7, 2005 at 6 p.m. Written 
comments will be received until June 21, 2005.

ADDRESSES: Copies of comments and questions regarding scoping of the 
Draft EIS may be addressed to: U.S. Army Corps of Engineers, Wilmington 
District, Regulatory Division, ATTN: File Number 200500344, Post Office 
Box 1890, Wilmington, NC 28402-1890.

FOR FURTHER INFORMATION CONTACT: Questions about the proposed action 
and DEIS can be directed to Mr. Mickey Sugg, Wilmington Regulatory 
Field Office, telephone: (910) 251-4811.

SUPPLEMENTARY INFORMATION: 1. Project Description. The Town of North 
Topsail

[[Page 28925]]

Beach, located along the north-northeast 11.1 miles of Topsail Island, 
North Carolina, is proposing to nourish approximately 7.25 miles of 
beach and reposition New River Inlet channel as a means to address a 
severe erosion problem that is threatening development and town 
infrastructure. The entire stretch of the Town's shoreline has 
experienced a considerable amount of erosion over the last 20 years due 
primarily to the impact of numerous tropical storms and hurricane 
during the mid to late 1990's and due to impacts of the uncontrolled 
movement of the main ebb channel in New River Inlet. The Town has 
stated that the shoreline erosion and residual effects of the storms 
have left North Topsail Beach in an extremely vulnerable position with 
regard to its ocean front development and infrastructure. They have 
estimated that over $250 million in property tax value as well as 
roads, water and sewer lines, and other utilities are at risk.
    The project area is divided into the North Section and the Central 
Section
    (Note: The South Section is part of the Federal shoreline 
protection plan). The North Section is further divided into two parts. 
One comprises approximately 5,800 linear feet, or 1.1 mile, of the 
project and is located along the northern end of the island. This area 
will receive material solely from the dredging of the New River Inlet 
when the channel is repositioned and realigned through the ebb tide 
delta. The new channel is expected to result in widening of the north 
of the Town's shoreline as the shoreline responds to the ebb tide delta 
configuration that would accompany the relocated channel. In addition 
to the placement of the material in the North Section, a portion of the 
inlet material will be deposited on the southern end of Onslow Beach as 
part of the comprehensive inlet management plan in order to maintain 
the existing sediment budget on Onslow Beach. The second part of the 
North Section is approximately 14,200 linear feet along the shoreline 
and will receive sand from the offshore borrow site(s). The Central 
Section is located both north and south of NC Hwy 210/55 Bridge and is 
approximately 16,500 linear feet. Material used to widened this section 
of the beach will also be obtained from the offshore borrow area(s).
    2. Proposed Action. The scope of activities for the formulation of 
the shoreline protection and inlet management plans for the Town of 
North Topsail Beach includes: (a) Detailed geotechnical investigations 
to define potential offshore borrow site(s); (b) evaluation and design 
of a new channel for New River Inlet and the development of an inlet 
management plan; (c) design and evaluation of beach fill sections 
including an assessment of the potential impacts of the offshore borrow 
area(s) on sediment transport; (d) near shore and inlet habitat 
mapping; and (e) hard bottom investigations. All geospatial data 
collected for the North Topsail Beach project will be included in a GIS 
database developed for the project.
    Potential offshore borrow areas, previously identified by work 
conducted by the Wilmington District Corps of Engineers, will be 
evaluated in detail using jet probes; seismic, sidescan, and 
magnetometer surveys; as well as vibracores. Samples of the offshore 
material collected form the jet probes and vibracores will be used to 
define the preliminary boundaries of the offshore borrow area(s) and 
make a preliminary determination of the compatibility of the borrow 
material to the native beach material. The boundaries of the potential 
borrow area(s) will take into consideration the location and extent of 
hard bottom resources identified by the sidescan and seismic surveys, 
as well as in-waters surveys. The boundaries of the proposed offshore 
borrow site(s) will also be refined to avoid historically significant 
archaeological artifacts located by the magnetometer surveys and 
verified through field investigations. Once the boundaries of the 
potential borrow area(s) are finalized, a final sediment compatibility 
analysis will be conducted.
    The beach fill designs presented in the feasibility study will be 
refined by analyzing existing profiles to determine potential erosion 
and storm impacts on back beach features such as vegetation, 
structures, and infrastructure. Specific designs will be developed for 
up to five characteristic profiles for the Central and North Sections. 
Design variations will be considered at discrete beach sections where 
unique upland features require special accommodation. The composite 
nature of the final beach and inlet design will require a more complex 
sequencing in construction operations than normally required for 
renourishment projects. The method and order of operations will be 
determined in order to optimize constructability and reduce costs.
    Beach planform performance will be evaluated based on the numerical 
modeling for the proposed projects. The GENESIS numerical model will be 
used in conjunction with a wave transformation model (STWAVE) to 
evaluate shoreline positions in time. The wave transformation model 
will be used to determine changes in wave patterns associated with the 
near shore borrow area(s). The state-of-the-art GENESIS version will be 
used so that the project area may be incorporated into a single 
simulation domain. The historical changes of the project area shoreline 
will be used to calibrate and verify the model, using an error 
minimization approach. Adjustments to the wave data used as input 
within the models will be made as required to replicate observed 
performance. The GENESIS model will be used to identify optimum 
alongshore fill placement.
    A detailed geomorphic study of New River Inlet was accomplished 
during the feasibility phase of the project development. The geomorphic 
study used aerial photographs to evaluate changes in New River Inlet 
from 1962 and 2003 and develop relationships between the configuration 
of the New River Inlet ebb tide delta and the behavior of the 
shorelines on the north end of the North Topsail Beach and the south 
end of Onslow Beach. The geomorphic study concluded that the most 
desirable location and orientation of the channel through the ebb tide 
delta, in terms of impacts on the adjacent islands, is one located 
closer to North Topsail Beach and oriented essentially perpendicular to 
the general alignment of the adjacent shorelines. The feasibility phase 
of the project development also included a preliminary numerical model 
evaluation of the impact of the relocated channel of flows and flow 
distributions in the New River Inlet complex.
    The next phase of the channel design will include additional 
numerical model evaluations of a wider range of channel alternatives 
(channel depths, widths, and locations) and will incorporate 
modifications in the configuration of the ebb tide delta expected to 
occur in response to the new channel. The reconfigured ebb tide delta 
will also be used to determine the potential changes in wave patterns 
north and south of New River Inlet and the impacts these changes could 
have on longshore sediment transport and shoreline behavior.
    The potential shoaling characteristics of the new channel will be 
evaluated using empirical shoaling algorithms developed for inlets in 
North Carolina. The propensity of the new channel to migrate to the 
north and/or south and possible future changes in the channel alignment 
will be based on observed changes in New River Inlet as documented by 
the geomorphic analysis. The potential changes in longshore sediment 
transport patterns on North Topsail Beach and Onslow

[[Page 28926]]

Beach associated changes in wave patterns together with the channel 
shoaling analysis will be used to develop a with-project sediment 
budget. The with-project sediment budget will be compared to the 
existing sediment budget to determine sand bypassing requirements that 
would be needed to maintain the existing sediment budget of the 
adjacent islands.
    3. Issues. There are several potential environmental issues that 
will be addressed to the FIS. Additional issues may be identified 
during the scoping process. Issues initially identified as potentially 
significant include:
    a. Potential impact to marine biological resources (benthic 
organisms, passageway for fish and other marine life) and Essential 
Fish Habitat, particularly Hard Bottoms.
    b. Potential impact to threatened and endangered marine mammals, 
birds, fish, and plants.
    c. Potential impacts to water quality.
    d. Potential increase in erosion rates to adjacent Onslow Beach.
    e. Potential effects on military training on U.S. Marine Corps Camp 
Lejeune Base.
    f. Potential impacts to Navigation, commercial and recreational.
    g. Potential impacts to the long-term management of New River 
Inlet.
    h. Potential impacts to private and public property.
    i. Cumulative impacts of Inlet and Inlet channel relocations 
throughout North Carolina.
    j. Cumulative impacts for using inlets as sand source in 
nourishment projects.
    k. Potential impacts on public health and safety.
    l. Potential impacts to recreational and commercial fishing.
    m. The compatibility of the material for nourishment.
    n. Potential economic impacts.
    4. Alternatives. Several alternative borrow areas are being 
considered for the proposed project. These alternatives will be further 
formulated and developed during the scoping process and an appropriate 
range of alternatives, including the no federal action alternative, 
will be considered in the EIS.
    5. Scoping Process. A public scoping meeting (see DATES will be 
held to receive public comment and assess public concerns regarding the 
appropriate scope and preparation of the Draft EIS. Participation in 
the public meeting by federal, state, and local agencies and other 
interested organizations and persons is encouraged.
    The COE will also be consulting with the U.S. Fish and Wildlife 
Service under the Endangered Species Act and the Fish and Wildlife 
Coordination Act, and with the National Marine Fisheries Service under 
the Magnuson-Stevens Act and Endangered Species Act. Additionally, the 
EIS will assess the potential water quality impacts pursuant to Section 
401 of the Clean Water Act, and will be coordinated with the North 
Carolina Division of Coastal Management (DCM) to determine the projects 
consistency with the Coastal Zone Management Act. The COE will closely 
work with DCM through the EIS to ensure the process complies with all 
State Environmental Policy Act (SEPA) requirements. It is the COE and 
DCM's intentions to consolidate both NEPA and SEPA processes to 
eliminate duplications.
    6. Availability of the Draft EIS. The Draft EIS is expected to be 
published and circulated sometime in early 2006, and a public hearing 
will be held after the publication of the Draft EIS.

    Dated: May 12, 2005.
George T. Burch,
Chief of Staff.
[FR Doc. 05-9995 Filed 5-18-05; 8:45 am]