[Federal Register: April 8, 2005 (Volume 70, Number 67)]
[Notices]
[Page 17986]
From the Federal Register Online via GPO Access [wais.access.gpo.gov]
[DOCID:fr08ap05-38]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. EL05-72-000]
Dynegy Midwest Generation, Inc.; Notice of Institution of
Proceeding and Refund Effective Date
April 1, 2005.
On March 25, 2005, the Commission issued an order initiating a
proceeding in Docket No. EL05-72-000 under section 206 of the Federal
Power Act concerning the continued justness and reasonableness of
Dynegy Midwest Generation, Inc.'s previously-accepted rate schedule for
reactive power services. Dynegy Midwest Generation, Inc. 110 FERC ]
61,358 (2005).
The refund effective date in Docket No. EL05-72-000, established
pursuant to section 206 of the Federal Power Act, will be 60 days
following publication of this notice in the Federal Register.
Magalie R. Salas,
Secretary.
[FR Doc. E5-1628 Filed 4-7-05; 8:45 am]
BILLING CODE 6717-01-P