[Federal Register: May 10, 2005 (Volume 70, Number 89)]
[Notices]
[Page 24567]
From the Federal Register Online via GPO Access [wais.access.gpo.gov]
[DOCID:fr10my05-73]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. EL05-71-000]
Mystic Development, LLC, Complainant v. Boston Edison Company and
NSTAR Electric & Gas Corporation, Respondents; Notice of Institution of
Investigation and Refund Effective Date
May 3, 2005.
On April 29, 2005, the Commission issued an order that initiated an
investigation and a trial-type evidentiary hearing under section 206 of
the Federal Power Act (FPA). Mystic Development, LLC v. Boston Edison
Company and NSTAR Electric & Gas Corporation, 111 FERC ] 61,133 (2005).
The refund effective date in Docket No. EL05-71-000, established
pursuant to section 206(b) of the FPA, is May 1, 2005.
Magalie R. Salas,
Secretary.
[FR Doc. E5-2247 Filed 5-9-05; 8:45 am]
BILLING CODE 6717-01-P