[Federal Register: May 17, 2005 (Volume 70, Number 94)]
[Notices]
[Page 28293-28294]
From the Federal Register Online via GPO Access [wais.access.gpo.gov]
[DOCID:fr17my05-52]
=======================================================================
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 2586]
Alabama Electric Cooperative, Inc.; Notice of Authorization for
Continued Project Operation
May 11, 2005.
On April 29, 2003, Alabama Electric Cooperative, Inc., licensee for
the Conecuh River Project No. 2586, filed an application for a new or
subsequent license pursuant to the Federal Power Act (FPA) and the
Commission's regulations. Project No. 2586 is located on the Conecuh
River in Covington County, Alabama.
The license for Project No. 2586 was issued for a period ending
April 30, 2005. Section 15(a)(1) of the FPA, 16 U.S.C. 808(a)(1),
requires the Commission, at the expiration of a license term, to issue
from year to year an annual license to the then licensee under the
terms and conditions of the prior license until a new license is
issued, or the project is otherwise disposed of as provided in section
15 or any other applicable section of the FPA. If the project's prior
license waived the applicability of section 15 of the FPA, then, based
on section 9(b) of the Administrative Procedure Act, 5 U.S.C. 558(c),
and as set forth at 18 CFR 16.21(a), if the licensee of such project
has filed an application for a subsequent license, the licensee may
continue to operate the project in accordance with the terms and
conditions of the license after the minor or minor part license
expires, until the Commission acts on its application. If the licensee
of such a project has not filed an application for a subsequent
license, then it may be required, pursuant to 18 CFR 16.21(b), to
continue project operations until the Commission issues someone else a
license for the project or otherwise orders disposition of the project.
[[Page 28294]]
If the project is subject to section 15 of the FPA, notice is
hereby given that an annual license for Project No. 2586 is issued to
Alabama Electric Cooperative, Inc. for a period effective May 1, 2005
through April 30, 2006, or until the issuance of a new license for the
project or other disposition under the FPA, whichever comes first. If
issuance of a new license (or other disposition) does not take place on
or before May 1, 2006, notice is hereby given that, pursuant to 18 CFR
16.18(c), an annual license under section 15(a)(1) of the FPA is
renewed automatically without further order or notice by the
Commission, unless the Commission orders otherwise.
If the project is not subject to section 15 of the FPA, notice is
hereby given that Alabama Electric Cooperative, Inc. is authorized to
continue operation of the Conecuh River Project No. 2586 until such
time as the Commission acts on its application for subsequent license.
Magalie R. Salas,
Secretary.
[FR Doc. E5-2473 Filed 5-16-05; 8:45 am]
BILLING CODE 6717-01-P