[Federal Register: May 17, 2005 (Volume 70, Number 94)]
[Notices]               
[Page 28293-28294]
From the Federal Register Online via GPO Access [wais.access.gpo.gov]
[DOCID:fr17my05-52]                         

=======================================================================
-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 2586]

 
Alabama Electric Cooperative, Inc.; Notice of Authorization for 
Continued Project Operation

May 11, 2005.
    On April 29, 2003, Alabama Electric Cooperative, Inc., licensee for 
the Conecuh River Project No. 2586, filed an application for a new or 
subsequent license pursuant to the Federal Power Act (FPA) and the 
Commission's regulations. Project No. 2586 is located on the Conecuh 
River in Covington County, Alabama.
    The license for Project No. 2586 was issued for a period ending 
April 30, 2005. Section 15(a)(1) of the FPA, 16 U.S.C. 808(a)(1), 
requires the Commission, at the expiration of a license term, to issue 
from year to year an annual license to the then licensee under the 
terms and conditions of the prior license until a new license is 
issued, or the project is otherwise disposed of as provided in section 
15 or any other applicable section of the FPA. If the project's prior 
license waived the applicability of section 15 of the FPA, then, based 
on section 9(b) of the Administrative Procedure Act, 5 U.S.C. 558(c), 
and as set forth at 18 CFR 16.21(a), if the licensee of such project 
has filed an application for a subsequent license, the licensee may 
continue to operate the project in accordance with the terms and 
conditions of the license after the minor or minor part license 
expires, until the Commission acts on its application. If the licensee 
of such a project has not filed an application for a subsequent 
license, then it may be required, pursuant to 18 CFR 16.21(b), to 
continue project operations until the Commission issues someone else a 
license for the project or otherwise orders disposition of the project.

[[Page 28294]]

    If the project is subject to section 15 of the FPA, notice is 
hereby given that an annual license for Project No. 2586 is issued to 
Alabama Electric Cooperative, Inc. for a period effective May 1, 2005 
through April 30, 2006, or until the issuance of a new license for the 
project or other disposition under the FPA, whichever comes first. If 
issuance of a new license (or other disposition) does not take place on 
or before May 1, 2006, notice is hereby given that, pursuant to 18 CFR 
16.18(c), an annual license under section 15(a)(1) of the FPA is 
renewed automatically without further order or notice by the 
Commission, unless the Commission orders otherwise.
    If the project is not subject to section 15 of the FPA, notice is 
hereby given that Alabama Electric Cooperative, Inc. is authorized to 
continue operation of the Conecuh River Project No. 2586 until such 
time as the Commission acts on its application for subsequent license.

Magalie R. Salas,
Secretary.
[FR Doc. E5-2473 Filed 5-16-05; 8:45 am]

BILLING CODE 6717-01-P