[Federal Register Volume 70, Number 19 (Monday, January 31, 2005)]
[Notices]
[Pages 4838-4839]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: E5-342]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket Nos. CP04-36-000, CP04-41-000]


Weaver's Cove Energy, L.L.C., Mill River Pipeline, L.L.C.; Notice 
of Limited Additional Period for Comment

January 19, 2005.
    On July 30, 2004, the Secretary of the Federal Energy Regulatory 
Commission (FERC or Commission) issued a Notice of Availability of the 
Draft Environmental Impact Statement (DEIS) and the Draft General 
Conformity Determination for the Proposed Weaver's Cove LNG Project, in 
the above-docketed proceedings. Comments on the draft EIS were due to 
the Secretary by September 20, 2004. As described below in this Notice, 
because it took the Commission time to process the requests described 
in the following paragraph, we will allow a limited opportunity for 
those who receive additional information to submit

[[Page 4839]]

supplemental comments based on that information. Responses will be 
included in the Final Environmental Impact Statement.
    The Commission has received numerous requests under its critical 
energy infrastructure information (CEII) regulation, 18 CFR 388.113, 
for several documents filed as CEII by Weaver's Cover Energy, L.L.C. 
(Weaver's Cove). The Commission and the Commission's CEII Coordinator 
are currently processing these requests. To the extent that a CEII 
request existing as of January 19, 2005 is granted, notice is given 
that any such requester is hereby given a period of thirty calendar 
days after the additional information is made available to the 
requester within which to submit any additional comments on the DEIS 
related to the information obtained as part of the CEII request.

Magalie R. Salas,
Secretary.
 [FR Doc. E5-342 Filed 1-28-05; 8:45 am]