[Federal Register: October 27, 2006 (Volume 71, Number 208)]
[Notices]
[Page 63006-63007]
From the Federal Register Online via GPO Access [wais.access.gpo.gov]
[DOCID:fr27oc06-51]
=======================================================================
-----------------------------------------------------------------------
ENVIRONMENTAL PROTECTION AGENCY
[ER-FRL-6680-6]
Environmental Impact Statements and Regulations; Availability of
EPA Comments
Availability of EPA comments prepared pursuant to the Environmental
Review Process (ERP), under section 309 of the Clean Air Act and
Section 102(2)(c) of the National Environmental Policy Act as amended.
Requests for copies of EPA comments can be directed to the Office of
Federal Activities at 202-564-7167.
An explanation of the ratings assigned to draft environmental
impact statements (EISs) was published in FR dated April 7, 2006 (71 FR
17845).
Draft EISs
EIS No. 20060305, ERP No. D-GSA-B81011-VT, New U.S. Border Station and
Commercial Port of Entry Route I-91 Derby Line, Design and
Construction, Vermont.
Summary: EPA does not object to the project as proposed, but
encourages GSA to consider additional measures to reduce air pollution
emissions. Rating LO.
EIS No. 20060316, ERP No. D-GSA-B40096-ME, Madawaska Border Station
Project, Replacement of Existing Border Station in Madawaska,
International Border between United States and Canada, Aroostook
County, ME.
Summary: EPA does not object to the project as proposed, but
encourages GSA to adopt measures to reduce air emissions. Rating LO.
EIS No. 20060328, ERP No. D-NRS-B36026-MA, Cape Cod Water Resources
Restoration Project, Restore Degraded Salt Marshes, Restore Anadromous
Fish Passages, and Improve Water Quality for Shellfishing Area, Cape
Cod, Barnstable County, MA.
Summary: EPA does not object to the project as proposed. Rating LO.
EIS No. 20060349, ERP No. D-DOE-E01016-FL, Orlando Gasification Project
(DOE/EIS-0383), To Provide Cost-Shared Funding for Construction and
Operation of Facilities at Orlando Utilities Commission's Station
Energy Center near Orlando, FL.
Summary: EPA expressed environmental concerns about the proposed
power plant's potential impacts on air quality, wetlands, hazardous
waste, and cumulative impacts. Evaluation of these impacts may require
various forms of modeling and risk assessments. Impacts to wetlands and
mitigation measures need to be discussed further in the FEIS. Rating
EC1.
Final EISs
EIS No. 20060326, ERP No. F-BOP-B81010-NH, Berlin, Coos County,
Proposed Federal Correctional Institution, Construction and Operation,
City of Berlin, Coos County, NH.
Summary: EPA does not object to the project as proposed, but
continues to encourage the BOP to investigate whether combined heat and
power
[[Page 63007]]
technologies could reduce energy usage at the facility.
EIS No. 20060120, ERP No. FB-FTA-L40210-WA, Central Link Light Rail
Transit Project (Sound Transit) Construction and Operation of the North
Link Light Rail Extension, from Downtown Seattle and Northgate, Updated
Information on Refined Design Concepts, Funding, Right-of-Way and U.S.
Army COE Section 404 Permits, King County, WA.
Summary: No formal comment letter was sent to the lead agency.
EIS No. 20060370, ERP No. FS-AFS-F65039-WI, McCaslin Project,
Vegetation Management Activities that are Consistent with Direction in
the Nicolet Forest Plan, New Information to Address Inadequate
Disclosure of the Cumulative Effect Analysis for Six Animal and Eight
Plant Species, Lakewood/Lasna District, Chequamegaon-Nicolet National
Forest, Oconto and Forest Counties, WI.
Summary: EPA's concerns about the cumulative impact analysis have
been resolved; therefore, EPA does not object to the proposed project.
Dated: October 24, 2006.
Robert W. Hargrove,
Director, NEPA Compliance Division, Office of Federal Activities.
[FR Doc. E6-18019 Filed 10-26-06; 8:45 am]
BILLING CODE 6560-50-P