[Federal Register: April 9, 2007 (Volume 72, Number 67)]
[Notices]
[Page 17525-17526]
From the Federal Register Online via GPO Access [wais.access.gpo.gov]
[DOCID:fr09ap07-47]
[[Page 17525]]
-----------------------------------------------------------------------
DEPARTMENT OF DEFENSE
Department of the Army; Corps of Engineers
Intent To Prepare a Draft Environmental Impact Statement (DEIS)
for the Construction of Western Wake Regional Wastewater Management
Facilities, Regional Wastewater Pumping, Conveyance, Treatment, and
Discharge Facilities To Serve the Towns of Apex, Cary, Holly Springs
and Morrisville, as well as the Wake County Portion of Research
Triangle Park (Service Area), NC
AGENCY: Department of the Army, U.S. Army Corps of the Engineers, DoD.
ACTION: Notice of intent.
-----------------------------------------------------------------------
SUMMARY: The U.S. Army Corps of Engineers (COE), Wilmington District,
Wilmington Regulatory Division has received a request for Department of
the Army authorization, pursuant to Section 404 of the Clean Water Act,
from Western Wake Partners to construct Western Wake Regional
Wastewater Management Facilities. This project will be a regional
wastewater pumping, conveyance, treatment, and discharge project to
serve the Towns of Apex, Cary, Holly Springs and Morrisville, as well
as the Wake County portion of Research Triangle Park (service area),
NC.
The project is being proposed by the Western Wake Partners to
provide wastewater service for planned growth and development in the
project service area and to comply with two regulatory mandates. One
regulatory mandate has been issued by the North Carolina Environmental
Management Commission (EMC), and the second regulatory mandate has been
issued by the North Carolina Department of Environment and Natural
Resources (NC DENR). In accordance with the two regulatory mandates,
the proposed Project must be operational and discharging effluent to
the Cape Fear River Basin by January 1, 2011.
DATES: A public scoping meeting for the DEIS will be held at 6 p.m. at
the Town of Apex Town Hall, April 19, 2007. Written comments will be
received until April 30, 2007.
ADDRESSES: Copies of comments and questions regarding scoping of the
Draft EIS may be addressed to: U.S. Army Corps of Engineers, Wilmington
District, Regulatory Division. ATTN: File Number SAW-200520159-1, P.O.
Box 1890, Wilmington, NC 28402-1890.
FOR FURTHER INFORMATION CONTACT: Questions about the proposed action
and DEIS can be directed to Mr. Henry Wicker, Regulatory Division,
telephone: (910) 251-4930.
SUPPLEMENTARY INFORMATION: The proposed project consists of regional
wastewater pumping, conveyance, treatment, and discharge facilities to
serve the Towns of Apex, Cary, Holly Springs and Morrisville, as well
as the Wake County portion of Research Triangle Park (service area),
NC. The purpose of the project is to provide wastewater service for
planned growth and development in the project service area and to
comply with two regulatory mandates. One regulatory mandate has been
issued by the North Carolina Environmental Management Commission (EMC),
and the second regulatory mandate has been issued by the North Carolina
Department of Environment and Natural Resources (NC DENR). In
accordance with the two regulatory mandates, the proposed Project must
be operational and discharging effluent to the Cape January 1, 2011.
Regulatory Mandate No. 1--Interbasin Transfer: The Towns of Apex,
Cary, and Morrisville, as well as Research Triangle Park (RTP) South,
obtain their drinking water from Jordan Lake in the Cape Fear River
Basis and discharge treated effluent to locations in the Neuse River
Basin. Obtaining water from one basin and discharging it to another
river basin is referred to as an interbasin transfer (IBT), which
requires a permit from the EMC. In July 2001, the EMC granted the Towns
of Apex, Cary, and Morrisville, as well as Wake County (on behalf of
RTP South), an IBT certificate to withdraw water from the Cape Fear
River Basin and discharge the water to the Neuse River Basin. However,
as a condition of approval, the IBT certificate issued by the EMC
requires the local governments to return reclaimed water to the Cape
Fear River Basin by January 1, 2011. As a result, the local governments
have initiated activities to plan, permit, design, and construct
wastewater transmission, treatment, and disposal facilities in order to
comply with the terms and conditions of the IBT certificate issued by
the EMC. The facilities that will be described and evaluated in the
environmental impact statement (DEIS) are needed to comply with the IBT
certificate terms and conditions.
Regulatory Mandate No. 2--Nutrient Enrichment for Harris Lake: The
Town of Holly Springs currently has a wastewater treatment plant (WWTP)
that discharges to Utley Creek, which is a tributary to Harris Lake in
the Cape Fear River Basin. Representatives from NCDENR have directed
the Town of Holly Springs to remove the Town's wastewater discharge
from Utley Creek due to nutrient enrichment issues in Utley Creek and
downstream in Harris Lake. In addition, NCDENR has encouraged Holly
Springs to participate with Apex, Cary and Morrisville on a regional
wastewater management program that will allow Holly Springs to remove
the Town's discharge from Utley Creek by January 1, 2011. Thus, Holly
Springs is participating with Apex, Cary and Morrisville in the
planning, permitting, design and construction of regional effluent
disposal facilities in order to comply with the mandate issued by
NCDENR to remove its discharge from Utley Creek. The regional effluent
disposal facilities that will be described and evaluated in the DEIS
are needed to comply with the NCDENR mandate.
The proposed project will need to be reviewed to address a number
of issues which includes an alternative analyses, direct environmental
impacts, secondary and cumulative environmental impacts, environmental
justice concerns, endangered species, and potential project costs.
Alternative Analysis: The purpose of the alternative analyses is to
present a discussion of the environmental impacts associated with a
reasonable number of alternatives. The proposed Project and a
reasonable number of alternatives will be evaluated and compared in the
DEIS. The factors to be considered will be similar for each of the
alternatives. Impacts are expected to differ primarily in the degree to
which specific factors may be affected.
The alternative analysis will evaluate alternative wastewater
management options. Presently eight wastewater management options have
been identified to be evaluated in the DEIS. These eight wastewater
management alternatives include the following:
(1) No Action;
(2) Regional System with Cape Fear River Discharge;
(3) Regional System with Jordan Lake Discharge;
(4) Independent Systems;
(5) Purchasing Capacity from Other Systems;
(6) Optimum Operation of Existing Facilities;
(7) Regional Land Application System;
(8) Water Reuse System.
Alternative Discharge Locations: Four alternative discharge
locations have been identified to be evaluated in the DEIS. These four
alternative discharge locations include the following:
(1) Cape Fear River below Buckhorn Dam;
[[Page 17526]]
(2) New Hope Arm of Jordan Lake (above Jordan Lake Dam and below US
64);
(3) Cape Fear River/Haw River above Buckhorn Dam;
(4) Harris Lake/Utley Creek.
Alternative Water Reclamation Facility Sites: Preliminary
investigations identified 30 potential locations for the Water
Reclamation Facility (WRF). The DEIS will analyze all 30 potential
locations to identify the impacts and use the information to make an
appropriate site selection.
Alternative Raw Wastewater Pumping and Conveyance; Alternative raw
wastewater pump station sites and force main routes will be evaluated
in the DEIS for the preferred WRF site and discharge location.
Alternative Effluent Pumping and Conveyance: The effluent pump
station will be located at the WRF site; therefore, selection of an
effluent pump station site is inherent in the WRF site selection
process. Alternative effluent force main routes will be evaluated in
the DEIS for the preferred WRF site and discharge location.
Alternative Outfall Configurations at Cape Fear River: The DEIS
will include evaluation of two configuration for the outfall structure.
The alternatives to be evaluated include (a) bank discharge structure,
and (b) instream diffuser.
Direct Environmental Impacts: The DEIS will identify and discuss
the direct impacts of the proposed Project and feasible alternatives on
topography, floodplains, soils, land use, wetlands, prime farmlands,
public lands, historic and archaeological resources, air quality,
noise, water resources, forest resources, shellfish and fish, wildlife
and natural vegetation, the introduction of toxic substances, shore
erosion and accretion, energy needs, safety, food and fiber production,
mineral needs, and property ownership. Geographic Information System
(GIS) data and mapping will be used to evaluate direct environmental
impacts of the proposed Project and alternatives.
Secondary and Cumulative Environmental Impacts: The Western Wake
Partners have developed Secondary and Cumulative Impacts Master
Mitigation Plans to address secondary and cumulative impacts that are
expected to result from the Western Wake Regional Wastewater Management
Facilities project as well as other infrastructure projects that will
be implemented in the Partners' jurisdictions in the future. Additional
secondary and cumulative impacts will be addressed in the DEIS as
recommended by the United States Army Corps of Engineers (USACE). GIS
data and mapping will be used to evaluate and quantify secondary and
cumulative impacts of the proposed Project to stream and wetland
resources.
Environmental Justice: In accordance with Executive Order 12898,
the DEIS will include an evaluation of the proposed Project's impact on
minority and low-income populations. US Census Bureau data and GIS
mapping will be used to determine the existence of all minority and
low-income populations in the Projects service area and in the affected
area for the preferred WRF site.
Endangered Species: A biological assessment will be included as an
appendix to the document for the preferred alternative in accordance
with the Endangered Species Act.
Project Costs: Project costs will be evaluated based on a 20 year
present-worth costs and Phase 1 capital costs. 20-year present-worth
costs allow for a direct comparison of long-term cost-effectiveness,
and Phase 1 capital costs allow for a direct comparison of short-term
capital requirements which have an immediate impact on sewer rates,
fees, and charges. Mitigation costs for direct impacts to streams and
wetlands will be estimated based on the Ecosystem Enhancement Program's
schedule of fees.
NEPA/SEPA Preparation and Permitting: Because the proposed Western
Wake Regional Wastewater Management Facilities Project requires
approvals from federal and state agencies under both the National
Environmental Policy Act (NEPA) and the State Environmental Policy Act
(SEPA), a joint Federal and State Environmental Document will be
prepared. The US Army Corps of Engineers will serve as the lead agency
for the Federal process.
Based on the size and complexity of the proposed Project, the
applicant has been encouraged by US Army Corps of Engineers and NCDENR
staff to identify and address the environmental impacts of the proposed
Project through the DEIS process. Within the DEIS, the applicant will
conduct a thorough environmental review, including an evaluation of
reasonable, feasible, and financially responsible alternatives. After
review of the DEIS and final EIS, a Record of Decision (ROD) will be
issued for the EIS document. The ROD will document the completion of
the EIS and serve as a basis for further permitting decisions by
federal and state agencies.
Scoping Process: A public scoping meeting (see DATES) will be held
to receive public comment and assess public concerns regarding the
appropriate scope and preparation of the DEIS. Participation in the
public meeting by federal, state, and local agencies and other
interested organizations and persons is encouraged. The Corps will also
be consulting with the U.S. Fish and Wildlife Service under the
Endangered Species Act and the Fish and Wildlife coordination Act.
Additionally, the DEIS will assess the potential water quality impacts
pursuant to Section 401 of the Clean Water Act. The corps will work
closely with the NC DENR to ensure the process complies with all State
Environmental Policy Act (SEPA) requirements. It is the Corps and
NCDENR's intentions to consolidate both NEPA and SEPA processes to
eliminate duplications.
Availability of the DEIS: The DEIS is expected to be published and
circulated sometime in early 2008, and a public hearing will be held
after the publication of the DEIS.
Patrick E. Tilque,
LTC U.S. Army, Deputy District Commander.
[FR Doc. 07-1741 Filed 4-6-07; 8:45 am]
BILLING CODE 3710-GN-M