SUMMARY: EPA is approving a revision to the Missouri State
Implementation Plan (SIP) that will fulfill the condition of a
previously-published approval (July 11, 2006). The revision amends the
Construction Permits By Rule and requires a preconstruction review
period before sources may begin construction.
DATES: This direct final rule will be effective November 26, 2007,
without further notice, unless EPA receives adverse comment by October
26, 2007. If adverse comment is received, EPA will publish a timely
withdrawal of the direct final rule in the Federal Register informing
the public that the rule will not take effect.
ADDRESSES: Submit your comments, identified by Docket ID No. EPA-R07-
OAR-2007-0926, by one of the following methods:
1. http://www.regulations.gov. Follow the on-line instructions for
submitting comments.
2. E-mail: Algoe-Eakin.amy@epa.gov.
3. Mail: Amy Algoe-Eakin, Environmental Protection Agency, Air
Planning and Development Branch, 901 North 5th Street, Kansas City,
Kansas 66101.
4. Hand Delivery or Courier. Deliver your comments to Amy Algoe-
Eakin, Environmental Protection Agency, Air Planning and Development
Branch, 901 North 5th Street, Kansas City, Kansas 66101.
Instructions: Direct your comments to Docket ID No. EPA-R07-OAR-
2007-0926. EPA's policy is that all comments received will be included
in the public docket without change and may be made available online at
http://www.regulations.gov, including any personal information
provided, unless the comment includes information claimed to be
Confidential Business Information (CBI) or other information whose
disclosure is restricted by statute. Do not submit through http://www.regulations.gov
or e-mail information that you consider to be CBI
or otherwise protected. The http://www.regulations.gov Web site is an
``anonymous access'' system, which means EPA will not know your
identity or contact information unless you provide it in the body of
your comment. If you send an e-mail comment directly to EPA without
going through http://www.regulations.gov, your e-mail address will be
automatically captured and included as part of the comment that is
placed in the public docket and made available on the Internet. If you
submit an electronic comment, EPA recommends that you include your name
and other contact information in the body of your comment and with any
disk or CD-ROM you submit. If EPA cannot read your comment due to
technical difficulties and cannot contact you for clarification, EPA
may not be able to consider your comment. Electronic files should avoid
the use of special characters, any form of encryption, and be free of
any defects or viruses.
Docket: All documents in the electronic docket are listed in the
http://www.regulations.gov index. Although listed in the index, some
information is not publicly available, i.e., CBI or other information
whose disclosure is restricted by statute. Certain other material, such
as copyrighted material, is not placed on the Internet and will be
publicly available only in hard copy form. Publicly available docket
materials are available either electronically in http://www.regulations.gov
or in hard copy at the Environmental Protection
Agency, Air Planning and Development Branch, 901 North 5th Street,
Kansas City, Kansas 66101. The Regional Office's official hours of
business are Monday through Friday, 8 to 4:30 excluding Federal
holidays. The interested persons wanting to examine these documents
should make an appointment with the office at least 24 hours in
advance.
FOR FURTHER INFORMATION CONTACT: Amy Algoe-Eakin at (913) 551-7942, or
by e-mail at Algoe-Eakin.amy@epa.gov.
SUPPLEMENTARY INFORMATION: Throughout this document whenever ``we,''
``us,'' or ``our'' is used, we mean EPA. This section provides
additional information by addressing the following questions:
What is a SIP?
What is the Federal approval process for a SIP?
What does Federal approval of a state regulation mean to me?
What is being addressed in this document?
Have the requirements for approval of a SIP revision been met?
What action is EPA taking?
What is a SIP?
Section 110 of the Clean Air Act (CAA) requires states to develop
air pollution regulations and control strategies to ensure that state
air quality meets the national ambient air quality standards (NAAQS)
established by EPA. These ambient standards are established under
section 109 of the CAA, and they currently address six criteria
pollutants. These pollutants are: Carbon monoxide, nitrogen dioxide,
ozone, lead, particulate matter, and sulfur dioxide.
Each state must submit these regulations and control strategies to
us for approval and incorporation into the federally-enforceable SIP.
Each federally-approved SIP protects air quality primarily by
addressing air pollution at its point of origin. These SIPs can be
extensive, containing state regulations or other enforceable documents
and supporting information
[[Page 54563]]
such as emission inventories, monitoring networks, and modeling
demonstrations.
What is the Federal approval process for a SIP?
In order for state regulations to be incorporated into the
Federally-enforceable SIP, states must formally adopt the regulations
and control strategies consistent with state and Federal requirements.
This process generally includes a public notice, public hearing, public
comment period, and a formal adoption by a state-authorized rulemaking
body.
Once a state rule, regulation, or control strategy is adopted, the
state submits it to us for inclusion into the SIP. We must provide
public notice and seek additional public comment regarding the proposed
Federal action on the state submission. If adverse comments are
received, they must be addressed prior to any final Federal action by
us.
All state regulations and supporting information approved by EPA
under section 110 of the CAA are incorporated into the Federally-
approved SIP. Records of such SIP actions are maintained in the Code of
Federal Regulations (CFR) at title 40, part 52, entitled ``Approval and
Promulgation of Implementation Plans.'' The actual state regulations
which are approved are not reproduced in their entirety in the CFR
outright but are ``incorporated by reference,'' which means that we
have approved a given state regulation with a specific effective date.
What does Federal approval of a state regulation mean to me?
Enforcement of the state regulation before and after it is
incorporated into the Federally-approved SIP is primarily a state
responsibility. However, after the regulation is Federally approved, we
are authorized to take enforcement action against violators. Citizens
are also offered legal recourse to address violations as described in
section 304 of the CAA.
What is being addressed in this document?
EPA is approving a SIP revision submitted by the state of Missouri
that will fulfill the condition of a previously-published approval
(July 11, 2006). Missouri adopted a rule in June 2003 (10 CSR 10-6.062)
to establish permits by rule for various source categories (e.g.,
printing operations, surface coating operations) which authorizes
sources in categories covered by the rule to operate under specified
conditions, instead of obtaining source-specific permits. The rule
applies only to the minor source program. The original rule (see 71 FR
38997 for a detailed description of the rule and specific action by EPA
on the rule) did not expressly include a mechanism for preconstruction
review of applications received from facilities that wanted to operate
under this rule. Section 110(a)(2)(C) of the CAA requires that each SIP
include a program to regulate construction and modification of sources
to ensure that the NAAQS are achieved. EPA's implementing regulation
provides that the plan must include procedures, ``by which the state .
. . will prevent such construction or modification'' where the source
or modification would violate a control strategy or interfere with
attainment or maintenance of the NAAQS (see 40 CFR 51.160(b)). Because
Missouri's rule that was adopted on June 26, 2003, appeared to
authorize construction to begin before any air quality review occurred,
and the rule only provided for revocation of a permit after the source
began construction or operation, EPA believed that Missouri's
preconstruction permit program was deficient with respect to sources
which may qualify for Permit By Rule.
To correct the deficiency, the Missouri Department of Natural
Resources was directed by the Missouri Air Conservation Commission via
resolution on December 8, 2005, to revise the Permit By Rule to
expressly include a preconstruction period of seven days before sources
could begin construction. The purpose of the preconstruction period is
to allow time for the state to review the application for the permit by
rule and determine whether additional air quality analyses should be
conducted for a particular project. The state must also approve the
application before construction may begin. This revision establishes
the seven day preconstruction period and fulfills the requirements of
the conditional approval.
Have the requirements for approval of a SIP revision been met?
The state submittal has met the public notice requirements for SIP
submissions in accordance with 40 CFR 51.102. The submittal also
satisfied the completeness criteria of 40 CFR part 51, appendix V. In
addition, as explained above and in more detail in the technical
support document which is part of this docket, the revision meets the
substantive SIP requirements of the CAA, including section 110 and
implementing regulations.
What action is EPA taking?
EPA is approving a revision to the Missouri SIP to fulfill the
condition of a previously-published approval (July 11, 2006). The
revision includes a mechanism for preconstruction review of
applications from facilities that want to operate under 10 CSR 10-
6.062, the permit by rule. We do not anticipate any adverse comments.
Please note that if EPA receives adverse comments on part of this rule,
and if that part can be severed from the remainder of the rule, EPA may
adopt as final those parts of the rule that are not the subject of an
adverse comment.
Statutory and Executive Order Reviews
Under Executive Order 12866 (58 FR 51735, October 4, 1993), this
action is not a ``significant regulatory action'' and therefore is not
subject to review by the Office of Management and Budget. For this
reason, this action is also not subject to Executive Order 13211,
``Actions Concerning Regulations That Significantly Affect Energy
Supply, Distribution, or Use'' (66 FR 28355, May 22, 2001). This action
merely approves state law as meeting Federal requirements and imposes
no additional requirements beyond those imposed by state law.
Accordingly, the Administrator certifies that this action will not have
a significant economic impact on a substantial number of small entities
under the Regulatory Flexibility Act (5 U.S.C. 601 et seq.). Because
this action approves pre-existing requirements under state law and does
not impose any additional enforceable duty beyond that required by
state law, it does not contain any unfunded mandate or significantly or
uniquely affect small governments, as described in the Unfunded
Mandates Reform Act of 1995 (Pub. L. 104-4).
This action also does not have tribal implications because it will
not have a substantial direct effect on one or more Indian tribes, on
the relationship between the Federal Government and Indian tribes, or
on the distribution of power and responsibilities between the Federal
Government and Indian tribes, as specified by Executive Order 13175 (65
FR 67249, November 9, 2000). This action also does not have Federalism
implications because it does not have substantial direct effects on the
States, on the relationship between the national government and the
States, or on the distribution of power and responsibilities among the
various levels of government, as specified in Executive Order 13132 (64
FR 43255, August 10, 1999). This action merely approves a state rule
implementing a
[[Page 54564]]
Federal standard, and does not alter the relationship or the
distribution of power and responsibilities established in the CAA. This
action also is not subject to Executive Order 13045, ``Protection of
Children from Environmental Health Risks and Safety Risks'' (62 FR
19885, April 23, 1997), because it approves a state rule implementing a
Federal standard.
In reviewing state submissions, EPA's role is to approve state
choices, provided that they meet the criteria of the CAA. In this
context, in the absence of a prior existing requirement for the State
to use voluntary consensus standards (VCS), EPA has no authority to
disapprove a state submission for failure to use VCS. It would thus be
inconsistent with applicable law for EPA, when it reviews a state
submission, to use VCS in place of a state submission that otherwise
satisfies the provisions of the CAA. Thus, the requirements of section
12(d) of the National Technology Transfer and Advancement Act of 1995
(15 U.S.C. 272 note) do not apply. This action does not impose an
information collection burden under the provisions of the Paperwork
Reduction Act of 1995 (44 U.S.C. 3501 et seq.).
The Congressional Review Act, 5 U.S.C. 801 et seq., as added by the
Small Business Regulatory Enforcement Fairness Act of 1996, generally
provides that before a rule may take effect, the agency promulgating
the rule must submit a rule report, which includes a copy of the rule,
to each House of the Congress and to the Comptroller General of the
United States. EPA will submit a report containing this rule and other
required information to the U.S. Senate, the U.S. House of
Representatives, and the Comptroller General of the United States prior
to publication of the rule in the Federal Register. A major rule cannot
take effect until 60 days after it is published in the Federal
Register. This action is not a ``major rule'' as defined by 5 U.S.C.
804(2).
Under section 307(b)(1) of the CAA, petitions for judicial review
of this action must be filed in the United States Court of Appeals for
the appropriate circuit by November 26, 2007. Filing a petition for
reconsideration by the Administrator of this final rule does not affect
the finality of this rule for the purposes of judicial review nor does
it extend the time within which a petition for judicial review may be
filed, and shall not postpone the effectiveness of such rule or action.
This action may not be challenged later in proceedings to enforce its
requirements. (See section 307(b)(2).)
List of Subjects in 40 CFR Part 52
Environmental protection, Air pollution control, Carbon monoxide,
Incorporation by reference, Intergovernmental relations, Lead, Nitrogen
dioxide, Ozone, Particulate matter, Reporting and recordkeeping
requirements, Sulfur oxides, Volatile organic compounds.
Dated: September 13, 2007.
John B. Askew,
Regional Administrator, Region 7.
0
Chapter I, title 40 of the Code of Federal Regulations is amended as
follows:
PART 52--[AMENDED]
0
1. The authority citation for part 52 continues to read as follows:
Authority: 42 U.S.C. 7401 et seq.
Subpart AA--Missouri
0
2. In Sec. 52.1320 the table in paragraph (c) is amended by revising
the entry for 10-6.062 to read as follows:
Sec. 52.1320 Identification of plan.
* * * * *
(c) * * *
EPA-Approved Missouri Regulations
--------------------------------------------------------------------------------------------------------------------------------------------------------
State
Missouri citation Title effective EPA approval date Explanation
date
--------------------------------------------------------------------------------------------------------------------------------------------------------
Missouri Department of Natural Resources
--------------------------------------------------------------------------------------------------------------------------------------------------------
* * * * * * *
Chapter 6 Air Quality Standards, Definitions, Sampling and Reference Methods, and Air Pollution Control Regulations for the State of Missouri
--------------------------------------------------------------------------------------------------------------------------------------------------------
* * * * * * *
10-6.062............................ Construction Permits By 5/30/07 9/26/07 [insert FR page number where the Section (3)(B)4 is not