[Federal Register: December 7, 2007 (Volume 72, Number 235)]
[Notices]
[Page 69206-69207]
From the Federal Register Online via GPO Access [wais.access.gpo.gov]
[DOCID:fr07de07-46]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 12925-000]
FFP Project 39, LLC; Notice of Application Accepted for Filing
and Soliciting Motions To Intervene, Protests, and Comments
November 30, 2007.
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection:
a. Type of Application: Preliminary Permit.
b. Project No.: 12925-000.
c. Date filed: August 6, 2007.
d. Applicant: FFP Project 39, LLC.
e. Name of Project: Malone Field Light Project.
f. Location: The project would be located in a section of the
Mississippi River in Bolivar County, Mississippi and Desha County,
Arkansas. The project uses no dam or impoundment.
g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)--825(r).
h. Applicant Contacts: Mr. Daniel Irvin, FFP Project 39, LLC, 69
Bridge Street, Manchester, MA 01944, phone (978) 232-3536, and Ms.
Maureen Winters, Project Manager, Devine Tarbell & Associates, 970
Baxter Boulevard, Portland, ME 04103, phone (207) 775-4495.
i. FERC Contact: Kelly Houff, (202) 502-6393.
j. Deadline for filing comments, protests, and motions to
intervene: 60 days from the issuance date of this notice.
All documents (original and eight copies) should be filed with:
Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888
First Street, NE., Washington, DC 20426. Comments, protests, and
interventions may be filed electronically via the Internet in lieu of
paper; see 18 CFR 385.2001(a)(1)(iii) and the instructions on the
Commission's Web site under the ``e-Filing'' link. The Commission
strongly encourages electronic filings. Please include the project
number (P-12925-000) on any comments or motions filed.
The Commission's Rules of Practice and Procedure require all
intervenors filing documents with the Commission to serve a copy of
that document on each person in the official service list for the
project. Further, if an intervenor files comments or documents with the
Commission relating to the merits of an issue that may affect the
responsibilities of a particular resource agency, they must also serve
a copy of the document on that resource agency.
k. Description of Project: The proposed project consists of: (1)
4,400 proposed 20 kilowatt Free Flow generating units having a total
installed capacity of 88 megawatts, (2) a proposed transmission line,
(3) a mooring system comprised of either free standing pilings or
existing infrastructure which will anchor the units, and (4)
appurtenant facilities. The FFP Project 39, LLC, project would have an
average annual generation of 385.440 gigawatt-hours and be sold to a
local utility.
l. Locations of Applications: A copy of the application is
available for inspection and reproduction at the Commission in the
Public Reference Room, located at 888 First Street NE., Room 2A,
Washington DC 20426, or by calling (202) 502-8371. This filing may also
be viewed on the Commission's Web site at http://www.ferc.gov using the
``eLibrary'' link. Enter the docket number excluding the last three
digits in the docket number field to access the document. For
assistance, call toll-free 1-866-208-3676 or e-mail
FERCOnlineSupport@ferc.gov. For TTY, call (202) 502-8659. A copy is
also available for inspection and reproduction at the address in item h
above.
m. Individuals desiring to be included on the Commission's mailing
list should so indicate by writing to the Secretary of the Commission.
n. Competing Preliminary Permit--Anyone desiring to file a
competing application for preliminary permit for a proposed project
must submit the competing application itself, or a notice of intent to
file such an application, to the Commission on or before the specified
comment date for the particular application (see 18 CFR 4.36).
Submission of a timely notice of intent allows an interested person to
file the competing preliminary permit application no later than 30 days
after the specified comment date for the particular application. A
competing preliminary permit application must conform with 18 CFR 4.30
and 4.36.
o. Competing Development Application--Any qualified development
applicant desiring to file a competing development application must
submit to the Commission, on or before a specified comment date for the
particular application, either a competing development application or a
notice of intent to file such an application. Submission of a timely
notice of intent to file a development application allows an interested
person to file the competing application no later than 120 days after
the specified comment date for the particular application. A competing
license application must conform with 18 CFR 4.30 and 4.36.
p. Notice of Intent--A notice of intent must specify the exact
name, business address, and telephone number of the prospective
applicant, and must include an unequivocal statement of intent to
submit, if such an application may be filed, either a preliminary
permit application or a development application (specify which type of
[[Page 69207]]
application). A notice of intent must be served on the applicant(s)
named in this public notice.
q. Proposed Scope of Studies under Permit--A preliminary permit, if
issued, does not authorize construction. The term of the proposed
preliminary permit would be 36 months. The work proposed under the
preliminary permit would include economic analysis, preparation of
preliminary engineering plans, and a study of environmental impacts.
Based on the results of these studies, the Applicant would decide
whether to proceed with the preparation of a development application to
construct and operate the project.
r. Comments, Protests, or Motions to Intervene--Anyone may submit
comments, a protest, or a motion to intervene in accordance with the
requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211,
.214. In determining the appropriate action to take, the Commission
will consider all protests or other comments filed, but only those who
file a motion to intervene in accordance with the Commission's Rules
may become a party to the proceeding. Any comments, protests, or
motions to intervene must be received on or before the specified
comment date for the particular application.
Comments, protests and interventions may be filed electronically
via the Internet in lieu of paper; See 18 CFR 385.2001 (a)(1)(iii) and
the instructions on the Commission's Web site under ``e-filing'' link.
The Commission strongly encourages electronic filing.
s. Filing and Service of Responsive Documents--Any filings must
bear in all capital letters the title ``COMMENTS'', ``RECOMMENDATIONS
FOR TERMS AND CONDITIONS'', ``PROTEST'', ``COMPETING APPLICATION'' OR
``MOTION TO INTERVENE'', as applicable, and the Project Number of the
particular application to which the filing refers. Any of the above-
named documents must be filed by providing the original and the number
of copies provided by the Commission's regulations to: The Secretary,
Federal Energy Regulatory Commission, 888 First Street, NE.,
Washington, DC 20426. A copy of any motion to intervene must also be
served upon each representative of the Applicant specified in the
particular application.
t. Agency Comments--Federal, State, and local agencies are invited
to file comments on the described application. A copy of the
application may be obtained by agencies directly from the Applicant. If
an agency does not file comments within the time specified for filing
comments, it will be presumed to have no comments. One copy of an
agency's comments must also be sent to the Applicant's representatives.
Kimberly D. Bose,
Secretary.
[FR Doc. E7-23778 Filed 12-6-07; 8:45 am]
BILLING CODE 6717-01-P