DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP08-33-000]
Dominion Transmission, Inc.; Notice of Application
December 20, 2007.
Take notice that on December 10, 2007, Dominion Transmission, Inc.
(DTI), 120 Tredegar Street, Richmond, Virginia 23219, filed an
abbreviated application pursuant to section 7(c) of the Natural Gas Act
(NGA) and Part 157 of the Commission's regulations, for a certificate
of public convenience and necessity to construct, install, own,
operate, and maintain a new 4,740 horsepower compressor station and two
miles of 20-inch diameter pipeline in Westmoreland County, Pennsylvania
(Dominion Hub I Project) for the purpose of transporting up to 200,000
Dth per day of new gas supplies received from proposed Rockies Express
Pipeline LLC facilities to a new interconnection with Texas Eastern
Transmission Company LP. DTI proposes to charge a discounted, fixed
reservation charge for transportation from primary receipt points to
the primary delivery point and requests a predetermination that rolled-
in rate treatment for the project is appropriate.
This filing is available for review at the Commission in the Public
Reference Room or may be viewed on the Commission's Web site at http://www.ferc.gov
using the ``eLibrary'' link. Enter the docket number
excluding the last three digits in the docket number field to access
the document. For assistance, please contact FERC Online Support at
FERCOnlineSupport@ferc.gov or toll free at (866) 208-3676, or for TTY,
contact (202) 502-8659.
Any questions regarding the application are to be directed to
Matthew R. Bley, Manager, Gas Transmission Certificates, Dominion
Transmission, Inc., 120 Tredegar Street, Richmond, Virginia 23219,
telephone no. (804) 819-2877, facsimile no. (804) 819-2064 and e-mail:
Matthew.R.Bley@dom.com.
Pursuant to section 157.9 of the Commission's rules, 18 CFR 157.9,
within 90 days of this Notice the Commission staff will either:
complete its environmental assessment (EA) and place it into the
Commission's public record (eLibrary) for this proceeding, or issue a
Notice of Schedule for Environmental Review. If a Notice of Schedule
for Environmental Review is issued, it will indicate, among other
milestones, the anticipated date for the Commission staff's issuance of
the final environmental impact statement (FEIS) or EA for this
proposal. The filing of the EA in the Commission's public record for
this proceeding or the issuance of a Notice of Schedule for
Environmental Review will serve to notify federal and state agencies of
the timing for the completion of all necessary reviews, and the
subsequent need to complete all federal authorizations within 90 days
of the date of issuance of the Commission staff's FEIS or EA.
Any person desiring to intervene or to protest this filing must
file in accordance with Rules 211 and 214 of the Commission's Rules of
Practice and Procedure (18 CFR 385.211 and 385.214). Protests will be
considered by the Commission in determining the appropriate action to
be taken, but will not serve to make protestants parties to the
proceeding. Any person wishing to become a party must file a notice of
[[Page 74277]]
intervention or motion to intervene, as appropriate. Such notices,
motions, or protests must be filed on or before the comment date.
Anyone filing a motion to intervene or protest must serve a copy of
that document on the Applicant. On or before the comment date, it is
not necessary to serve motions to intervene or protests on persons
other than the Applicant.
However, a person does not have to intervene in order to have
comments considered. The second way to participate is by filing with
the Secretary of the Commission, as soon as possible, an original and
two copies of comments in support of or in opposition to this project.
The Commission will consider these comments in determining the
appropriate action to be taken, but the filing of a comment alone will
not serve to make the filer a party to the proceeding. The Commission's
rules require that persons filing comments in opposition to the project
provide copies of their protests only to the party or parties directly
involved in the protest.
Persons who wish to comment only on the environmental review of
this project should submit an original and two copies of their comments
to the Secretary of the Commission. Environmental commenters will be
placed on the Commission's environmental mailing list, will receive
copies of the environmental documents, and will be notified of meetings
associated with the Commission's environmental review process.
Environmental commenters will not be required to serve copies of filed
documents on all other parties. However, the non-party commenters will
not receive copies of all documents filed by other parties or issued by
the Commission (except for the mailing of environmental documents
issued by the Commission) and will not have the right to seek court
review of the Commission's final order.
The Commission encourages electronic submission of protests and
interventions in lieu of paper using the ``eFiling'' link at http://www.ferc.gov.
Persons unable to file electronically should submit the
original and 14 copies of the protest or intervention to the Federal
Energy Regulatory Commission, 888 First Street, NE., Washington, DC
20426.
Comment Date: January 10, 2008.
Kimberly D. Bose,
Secretary.
[FR Doc. E7-25325 Filed 12-28-07; 8:45 am]
BILLING CODE 6717-01-P