Drawbridge Operation Regulations; Reynolds Channel, Lawrence, NY
AGENCY: Coast Guard, DHS.
ACTION: Notice of temporary deviation from regulations.
-----------------------------------------------------------------------
SUMMARY: The Commander, First Coast Guard District, has issued a
temporary deviation from the regulation governing the operation of the
Atlantic Beach Bridge across Reynolds Channel, mile 0.4, at Lawrence,
New York. Under this temporary deviation, an advance notice shall be
required for bridge openings from February 26, 2007 through March 2,
2007, from 7 a.m. to 5:30 p.m. This deviation is necessary to
facilitate scheduled bridge maintenance.
DATES: This deviation is effective from February 26, 2007 through March
2, 2007.
ADDRESSES: Materials referred to in this document are available for
inspection or copying at the First Coast Guard District, Bridge Branch
Office, One South Street, New York, New York 10004, between 7 a.m. and
3 p.m., Monday through Friday, except Federal holidays. The telephone
number is (212) 668-7165. The First Coast Guard District Bridge Branch
Office maintains the public docket for this temporary deviation.
FOR FURTHER INFORMATION CONTACT: Judy Leung-Yee, Project Officer, First
Coast Guard District, at (212) 668-7195.
SUPPLEMENTARY INFORMATION: The Atlantic Beach Bridge, across Reynolds
Channel at mile 0.4, at Lawrence, New York, has a vertical clearance in
the closed position of 25 feet at mean high water and 30 feet at mean
low water. The existing drawbridge operation regulations are listed at
33 CFR 117.5.
The owner of the bridge, Nassau County Bridge Authority, requested
a temporary deviation to facilitate scheduled bridge span lock
maintenance. The bridge will not be able to open while the bridge
maintenance is underway. An advance notice for openings is necessary in
order to have the bridge operational for vessel traffic.
Under this temporary deviation the bridge shall open on signal
after at least a 1-hour advance notice is given between 7 a.m. and 5:30
p.m. from February 26, 2007 through March 2, 2007.
The contact information for providing the advance notice for bridge
openings shall be via marine radio channel 13 or by calling (516) 239-
1821.
In accordance with 33 CFR 117.35(c), this work will be performed
with all due speed in order to return the bridge to normal operation as
soon as possible.
Should the bridge maintenance authorized by this temporary
deviation be completed before the end of the effective period published
in this notice, the Coast Guard will rescind the remainder of this
temporary deviation, and the bridge shall be returned to its normal
operating schedule. Notice of the above action shall be provided to the
public in the Local Notice to Mariners and the Federal Register, where
practicable.
This deviation from the operating regulations is authorized under
33 CFR 117.35.
Dated: January 16, 2007.
Gary Kassof,
Bridge Program Manager, First Coast Guard District.