DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 2232-522]
Duke Energy Carolinas, LLC; Notice of Authorization for Continued
Project Operation
September 18, 2008.
On August 29, 2006, Duke Energy Carolinas, LLC, licensee for the
Catawba-Wateree Hydroelectric Project, filed an Application for a New
license pursuant to the Federal Power Act (FPA) and the Commission's
regulations thereunder. The Catawba-Wateree Hydroelectric Project is
located on Catawba River, in Alexander, Burke, Caldwell, Catawba,
Gaston, Iredell, Lincoln, McDowell, and Mecklenburg Counties, North
Carolina and on the Catawba and Wateree Rivers in the counties of
Chester, Fairfield, Kershaw, Lancaster, and York, South Carolina.
The license for Project No. 2232-522 was issued for a period ending
August 31, 2008. Section 15(a)(1) of the FPA, 16 U.S.C. 808(a)(1),
requires the Commission, at the expiration of a license term, to issue
from year-to-year an annual license to the then licensee under the
terms and conditions of the prior license until a new license is
issued, or the project is otherwise disposed of as provided in section
15 or any other applicable section of the FPA. If the project's prior
license waived the applicability of section 15 of the FPA, then, based
on section 9(b) of the Administrative Procedure Act, 5 U.S.C. 558(c),
and as set forth at 18 CFR. 16.21(a), if the licensee of such project
has filed an application for a subsequent license, the licensee may
continue to operate the project in accordance with the terms and
conditions of the license after the minor or minor part license
expires, until the Commission acts on its application. If the licensee
of such a project has not filed an application for a subsequent
license, then it may be required, pursuant to 18 CFR 16.21(b), to
continue project operations until the Commission issues someone else a
license for the project or otherwise orders disposition of the project.
If the project is subject to section 15 of the FPA, notice is
hereby given that an annual license for Project No. 2232-522 is issued
to the Duke Energy Carolinas, LLC., for a period effective September 1,
2008 through August 31, 2009, or until the issuance of a new license
for the project or other disposition under the FPA, whichever comes
first. If issuance of a new license (or other disposition) does not
take place on or before August 31, 2009, notice is hereby given that,
pursuant to 18 CFR 16.18(c), an annual license under section 15(a)(1)
of the FPA is renewed automatically without further order or notice by
the Commission, unless the Commission orders otherwise. If the project
is not subject to section 15 of the FPA, notice is hereby given that
the Duke Energy Carolinas, LLC., is authorized to continue operation of
the Catawba-Wateree Hydroelectric Project, until such time as the
Commission acts on its application for a subsequent license.