DEPARTMENT OF TRANSPORTATION
Pipeline and Hazardous Materials Safety Administration
Office of Hazardous Materials Safety; Notice of Delays in
Processing of Special Permits Applications
AGENCY: Pipeline and Hazardous Materials Safety Administration (PHMSA),
DOT.
ACTION: List of Applications Delayed more than 180 days.
-----------------------------------------------------------------------
SUMMARY: In accordance with the requirements of 49 U.S.C. 5117(c),
PHMSA is publishing the following list of special permit applications
that have been in process for 180 days or more. The reason(s) for delay
and the expected completion date for action on each application is
provided in association with each identified application.
FOR FURTHER INFORMATION CONTACT: Delmer F. Billings, Director, Office
of Hazardous Materials Special Permits and Approvals, Pipeline and
Hazardous Materials Safety Administration, U.S. Department of
Transportation, East Building, PHH-30, 1200 New Jersey Avenue, SE.,
Washington, DC 20590-0001, (202) 366-4535.
Key to ``Reason for Delay''
1. Awaiting additional information from applicant.
2. Extensive public comment under review.
3. Application is technically complex and is of significant impact
or precedent-setting and requires extensive analysis.
4. Staff review delayed by other priority issues or volume of
special permit applications.
Meaning of Application Number Suffixes
N--New application.
M--Modification request.
PM--Party to application with modification request.
Issued in Washington, DC, on October 22, 2008.
Delmer F. Billings,
Director, Office of Hazardous Materials, Special Permits and Approvals.
Modification to Special Permits
----------------------------------------------------------------------------------------------------------------
Reason for Estimated date
Application No. Applicant delay of completion
----------------------------------------------------------------------------------------------------------------
14167-M........................................ Trinityrail, Dallas, TX........... 4 10-31-2008
8723-M......................................... Alaska Pacific Powder Company, 1 10-31-2008
Anchorage, AK.
135 83-M....................................... Structural Composites Industries, 1 10-31-2008
Pomona, CA.
10950-M........................................ The Fertilizer Institute, 1 10-31-2008
Washington, DC.
----------------------------------------------------------------------------------------------------------------
[[Page 64397]]
New Special Permit Applications
----------------------------------------------------------------------------------------------------------------
Reason for Estimated date
Application No. Applicant delay of completion
----------------------------------------------------------------------------------------------------------------
14643-N........................................ World Airways, Inc., Peachtree 3 11-30-2008
City, GA.
14664-N........................................ Century Arms, Inc., Fairfax, VT... 4 10-31-2008
14689-N........................................ Trinity Industries, Inc., Dallas, 2, 3 11-30-2008
TX.
14668-N........................................ Lincoln Composites, Lincoln, NE... 1 02-28-2009
----------------------------------------------------------------------------------------------------------------
[FR Doc. E8-25742 Filed 10-28-08; 8:45 am]