Florida Gas Transmission Company, LLC; Notice of Application
November 17, 2008.
Take notice that on October 31, 2008, Florida Gas Transmission
Company, LLC (FGT), 5444 Westheimer Road, Houston, Texas 77056-5306,
filed in the above referenced docket an application pursuant to section
7(c) of the Natural Gas Act (NGA) and parts 157 and 284 of the
Commission's regulations, for an order granting a certificate of public
convenience and necessity authorizing the construction and operation of
natural gas pipeline and compression facilities and to acquire pipeline
facilities, all as more fully set forth in the application which is on
file with the Commission and open to public inspection. The filing is
available for review at the Commission in the Public Reference Room or
may be viewed on the Commission's Web site at http://www.ferc.gov using
the ``eLibrary'' link. Enter the docket number excluding the last three
digits in the docket number field to access the document. For
assistance, contact FERC at FERCOnlineSupport@gerc.gov or call toll-
free, (886) 208-3676 or TYY, (202) 502-8659.
Specifically, FGT proposes in its Phase VIII Expansion Project to:
(i) Construct and operate 483.2 miles of pipeline loop, mainline, and
laterals; (ii) install 213,600 horsepower of compression at existing
and new compressor stations; (iii) acquire from Florida Power & Light
Company (FPL) a 22.7 mile pipeline; and (iv) construct and operate
various metering and regulating facilities. All of the facilities
comprising the Phase VIII Expansion Project will be located in the
states of Alabama and Florida. FGT estimates that the proposed
facilities will cost approximately $2.455 billion. The facilities will
be able to provide an annual average of 820,000 MMBtu/day of firm
transportation. FGT proposes a new firm rate schedule, Rate Schedule
FTS-3 for service on the expansion.
Any questions concerning this application may be directed to
Stephen T. Veatch, Sr. Director, Certificates and Tariffs, Florida Gas
Transmission Company, LLC, 5444 Westheimer Road, Houston, Texas 77056-
5306 or at 713-989-2024 or stephen.veatch@sug.com.
On March 18, 2008, the Commission staff granted FGT's request to
utilize the FERC Pre-Filing Process and assigned Docket No. PF08-14-000
to staff activities involved the Phase VIII Expansion Project. Now as
of the filing of FGT's application on October 31, 2008, the Pre-Filing
Process for this project has ended. From this time forward, this
proceeding will be conducted in Docket No. CP09-17-000, as noted in the
caption of this Notice.
Pursuant to section 157.9 of the Commission's rules, 18 CFR 157.9,
within 90 days of this Notice, the Commission staff will either:
complete the environmental assessment (EA) and place it into the
Commission's public record (eLibrary) for this proceeding; or issue a
Notice of Schedule for Environmental Review. If a Notice of Schedule
for Environmental Review is issued, it will indicate, among other
milestones, the anticipated date for the Commission staff's issuance of
the final environmental impact statement (FEIS) or EA for this
proposal. The filing of the EA in the Commission's public record for
this proceeding or the issuance of a Notice of Schedule for
Environmental Review will serve to notify federal and state agencies of
the timing for the completion of all necessary reviews, and the
subsequent need to complete all federal authorizations within 90 days
of the date of issuance of the Commission staff's FEIS or EA.
There are two ways to become involved in the Commission's review of
this project. First, any person wishing to obtain legal status by
becoming a party to the proceedings for this project should, on or
before the comment date stated below file with the Federal Energy
Regulatory Commission, 888 First Street, NE., Washington, DC 20426, a
motion to intervene in accordance with the requirements of the
Commission's Rules of Practice and Procedure (18 CFR 385.214 or
385.211) and the Regulations under the NGA (18 CFR 157.10). A person
obtaining party status will be placed on the service list maintained by
the Secretary of the Commission and will receive copies of all
documents filed by the applicant and by all other parties. A party must
submit 14 copies of filings made in the proceeding with the Commission
and must mail a copy to the applicant and to every other party. Only
parties to the proceeding can ask for court review of Commission orders
in the proceeding.
However, a person does not have to intervene in order to have
comments considered. The second way to participate is by filing with
the Secretary of the Commission, as soon as possible, an original and
two copies of comments in support of or in opposition to this project.
The Commission will consider these comments in determining the
appropriate action to be taken, but the filing of a comment alone will
not serve to make the filer a party to the proceeding. The Commission's
rules require that persons filing comments in opposition to the project
provide copies of their protests only to the party or parties directly
involved in the protest.
Persons who wish to comment only on the environmental review of
this project should submit an original and two copies of their comments
to the Secretary of the Commission. Environmental commentors will be
placed on the Commission's environmental mailing list, will receive
copies of the environmental documents, and will be notified of meetings
associated with the Commission's environmental review process.
Environmental commentors will not be required to serve copies of filed
documents on all other parties. However, the non-party commentors will
not receive copies of all documents filed by other parties or issued by
the Commission (except for the mailing of environmental documents
issued by the Commission) and will not have the right to seek court
review of the Commission's final order.
The Commission strongly encourages electronic filings of comments,
protests and interventions in lieu of paper using the ``eFiling'' link
at http://www.ferc.gov. Persons unable to file electronically should
submit an original and 14 copies of the protest or intervention to the
Federal Energy regulatory Commission, 888 First Street, NE.,
Washington, DC 20426.
This filing is accessible on-line at http://www.ferc.gov, using the
``eLibrary'' link and is available for review in the Commission's
Public Reference Room in Washington, DC. There is an ``eSubscription''
link on the Web site that enables subscribers to receive e-mail
notification when a document is added to a subscribed docket(s). For
assistance with any FERC Online service, please e-mail
FERCOnlineSupport@ferc.gov, or call (866) 208-3676 (toll free). For
TTY, call (202) 502-8659.
[[Page 70631]]
Comment Date: December 8, 2008.
Kimberly D. Bose,
Secretary.