DEPARTMENT OF DEFENSE
Department of the Army; Corps of Engineers
Intent To Prepare a Draft Environmental Impact Statement (DEIS)
for the Revised Great Salt Lake Minerals Corporation's Solar
Evaporation Pond Expansion Project Within the Great Salt Lake, Box
Elder County, UT
AGENCY: Department of the Army; U.S. Army Corps of Engineers, DoD.
ACTION: Notice of intent.
-----------------------------------------------------------------------
SUMMARY: In accordance with the National Environmental Policy Act
(NEPA), the U.S. Army Corps of Engineers--Sacramento District (Corps)
will prepare an Environmental Impact Statement (EIS) for Corps
authorization actions for the proposed Revised Great Salt Lake Minerals
Corporation Solar Evaporation Ponds Expansion project. The basic
project purpose is potassium sulfate extraction/mining. The overall
project purpose is to increase production/output of organically
certified potassium sulfate to help meet the increasing demand for this
type of fertilize. The applicant believes there is a need to increase
production of potassium sulfate in order to maintain its market share
over the next 50 years.
The proposed expansion would add approximately 91,000 acres of
solar evaporative ponds, impacting approximately 80,000 acres of waters
of the United States, including wetlands, and reduce the need to import
raw potassium from other sources. The EIS will address impacts such as
wildlife habitat, water quality, Great Salt Lake water elevations,
wetlands, hydrology, cultural resources, transportation, endangered
species and industry. The projected date for public release of the
Draft EIS is October 30, 2009.
DATES: Four public scoping meetings will be held. The first scoping
meeting will be held on June 4, 2009 from 5-8
[[Page 27508]]
p.m. at the Davis County Library, 725 South Main Street, Bountiful,
Utah. The second public meeting will be on June 9, 2009 from 5-8 p.m.
at the Comfort Suites Hotel, 2250 South 1200 West, Ogden, Utah. The
third meeting will be held on June 11, 2009, from 5-8 p.m. at West High
School, 241 North 300 West, Salt Lake City, Utah. The fourth meeting
will be held on June 24, 2009, from 5-8 p.m. also at West High School,
241 North 300 West, Salt Lake City, Utah.
ADDRESSES: Public comments will be accepted at the scoping meetings or
may be mailed to Mr. Jason Gipson, Nevada-Utah Regulatory Branch, 533
West 2600 South, Suite 150, Bountiful, Utah 84010, or e-mailed to:
jason.a.gipson@usace.army.mil. All comments must be received on or
before July 9, 2009.
FOR FURTHER INFORMATION CONTACT: Questions about the proposed action
and the DEIS should be directed to the Corps project manager, Mr. Jason
Gipson at 801-295-8380 x14, or e-mail at jason.a.gipson@usace.army.mil.
Please refer to identification number 200700121.
SUPPLEMENTARY INFORMATION: Great Salt Lake Minerals Corporation (GSL
Minerals) currently operates approximately 47,000 acres of evaporative
ponds located on the east and west shores of the Great Salt Lake. A
25,000-acre evaporation facility is located on the west shore of the
North Arm of the Great Salt Lake and a 22,000-acre evaporation facility
is located on the east shore of the Bear River Bay. The existing solar
evaporation pond facilities are located within the Great Salt Lake,
i.e., the ponds are located below 4205 feet mean sea level, which is
below the high water mark of the Great Salt Lake. The company draws
naturally occurring brine from the lake into shallow ponds and allows
solar evaporation to produce sulfate of potash, as well as salt and
magnesium chloride minerals. Sulfate of potash is a specialty
fertilizer that improves the yield and quality of high-value crops such
as fruits, vegetables, tea, tree nuts and turf grasses. The GSL
Minerals facility has operated on the lake for 40 years.
The applicant originally proposed in late 2007 to construct three
additional solar evaporation ponds totaling approximately 33,000 acres.
The 2007 proposed project included adding two new solar ponds to the
existing west side complex, an 18,000-acre Dolphin Island expansion
pond and a 7,000-acre pond at the southern end of Clyman Bay between
the Union Pacific Railway and several existing ponds. A new feed canal
into the lake and a new pump station would be constructed on the north
end of the proposed Dolphin Island pond. Diesel driven pumps, similar
to those currently in use, would pump brine from the new feed canal to
the new pond. Existing pumps would be used to pump brine from the new
pond to an existing pond. The total 25,000-acre pond expansion on the
west side would increase the concentration of brine transferred to an
existing gravity-flow trench for transport to the east ponds in the
Bear River Bay. Additionally under the 2007 proposal, an 8,000-acre
pond would be constructed on the east side of the Great Salt Lake in
the Bear River Bay. Brine would be pumped to and from the new pond with
existing pump stations; however, the capacity of these pump stations
would be increased proportional to the new pond acreage. Additional
feed brine for this new pond would come from the North Arm of the Great
Salt Lake (Gunnison Bay), flowing through existing east side ponds.
Under the 2007 proposal, dikes would be built to accommodate the
pond expansion and impound the waters of the respective areas. On the
east side of the lake, approximately 540,000 cubic yards of fill would
be discharged into Bear River Bay to create the dikes. On the west
side, approximately 900,000 cubic yards of fill would be discharged
into open water in the vicinity of Clyman Bay to create dikes.
The 2009 revised project proposes to: (1) Retain the proposed
construction of an 8,000-acre pond in Bear River Bay, (2) decrease the
previously proposed 8,000 acre pond on the west shore of the lake along
the north side of the railroad causeway to 6,000 acres, (3) increase
the 18,000-acre pond to 23,000 acres, (4) add an additional 2,000-acre
pond west of the above described 6,000-acre pond along the north side
of the railroad causeway, (5) add a 14,000-acre pond on the south side
of the railroad causeway, and (6) add an additional 38,000-acre pond in
the Dolphin Island area of the lake. On the east side of the lake,
approximately 540,000 cubic yards of fill would be discharged into Bear
River Bay to create the dikes. On the west side, approximately 4.7
million cubic yards of fill would be discharged into open water in the
vicinity of Clyman Bay to create dikes.
The total 83,000-acre West Pond Expansion (including Lakeside Lease
areas) would increase the concentration of brine transferred to an
existing gravity-flow trench (Behrens Trench) for transport to the GSL
Minerals east solar evaporation ponds in the Bear River Bay (Figures 1,
2 and 3). Ultimately as part of the proposed project the efficiency of
the Behrens Trench would be improved to reduce mixing of concentrated
brine with lake water surrounding the trench by either improving the
existing open Behrens Trench by excavating the trench wider and deeper
or by laying pipes in the existing trench.
In addition the project includes the purchasing and transporting
SOP from the U.S. Magnesium ponds located along the southwestern margin
of the lake to the existing processing facility. GSL Minerals will also
increase SOP production by constructing an SOP processing plant within
the U.S. Magnesium pond area (Figure 4).
The proposed project habitat areas include saline open water,
sporadically inundated playa lakebed, seasonally flooded playa, saline
wetlands, potential freshwater springs, rip-rapped dikes and sandy
upland habitats. These areas are located adjacent and to the north of
the existing evaporation pond facilities. The Corps verified a
jurisdictional wetland delineation for the 2007 proposed project on
October 10, 2007, which identified approximately 34,180.08 acres of
waters of the U.S., including 21.4 acres of saline wet meadow wetlands,
1,102.94 acres of seasonally inundated playa above the high water mark
of the western side of the Great Salt Lake and 33,055.74 acres of
seasonally or sporadically inundated playa lake bed below the high
water mark of the Lake. A delineation of waters of the U.S. has not
been completed or verified for the additional areas proposed under the
2009 revised application. However, it is estimated the additional
50,000 acres are all located within the ordinary high water mark of the
Great Salt Lake, resulting in the same acreage of additional impacts to
waters of the U.S. The proposed project would result in approximately
80,000 acres of permanent adverse impacts to waters.
The applicant has not proposed compensatory mitigation for project
impacts. The determination of appropriate compensatory mitigation will
be determined through public scoping and impact analysis of the EIS
process.
The proposed project will not affect any federally-listed
threatened or endangered species, however, it may affect state-listed
special status species. Once a habitat assessment of the areas has been
completed, the Corps will consult with state and Federal wildlife
agencies. The Corps will also consult with the State Historic
Preservation Officer under Section 106 of the National Historic
Preservation Act for properties listed or potentially eligible
[[Page 27509]]
for listing on the National Register of Historic Places, as
appropriate.
A number of on-site and off-site alternatives, including the no
action alternative, will be evaluated in the DEIS in accordance with
NEPA and the Section 404(b)(1) guidelines.
As part of the Corps 404 permitting process, pre-application
interagency meetings have been held to provide information and identify
issues and concerns. In addition, meetings have been held with local
environmental organizations for the same purposes. Preliminary issues
identified as part of this process include: Water quality, heavy
metals, nutrient loading, fresh water exchange, changes in salinity,
and brine shrimp habitat, economic issues and cultural resources.
Additionally, potential avian impacts were identified to waterfowl,
shorebirds, and raptors including the American white pelican, snowy
plover, Canada goose, and others.
The above determinations are based on information provided by the
applicant and upon the Corps' preliminary review. The Corps is
soliciting verbal and written comments from the public, Federal, state
and local agencies and officials, Native American tribes, and other
interested parties in order to consider and evaluate the impacts of
this proposed activity. The Corps' public involvement program includes
multiple opportunities for interested parties to provide written and
oral comments. Affected Federal, state, local agencies, Indian tribes,
and other interested private organizations and the general public are
invited to participate.
Brenda S. Bowen,
Army Federal Register Liaison Officer.
[FR Doc. E9-13437 Filed 6-9-09; 8:45 am]