[Federal Register Volume 74, Number 167 (Monday, August 31, 2009)]
[Notices]
[Pages 44879-44880]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: E9-20915]


-----------------------------------------------------------------------

NUCLEAR REGULATORY COMMISSION

[NRC-2008-0252; Docket No. 052-00011]


Notice of Issuance of Early Site Permit and Limited Work 
Authorization for the Vogtle Electric Generating Plant ESP Site

AGENCY: Nuclear Regulatory Commission.

ACTION: Notice of Issuance of Early Site Permit and Limited Work 
Authorization.

-----------------------------------------------------------------------

FOR FURTHER INFORMATION CONTACT: Christian Araguas, Project Manager, 
AP1000 Projects Branch, Division of New Reactor Licensing, Office of 
New Reactors, U.S. Nuclear Regulatory Commission, Washington, DC 20555-
0001. Telephone: (301) 415-3637; e-mail: [email protected].

SUPPLEMENTARY INFORMATION: 

[[Page 44880]]

I. Introduction

    Pursuant to 10 CFR 2.106, the Nuclear Regulatory Commission (NRC) 
is providing notice of the issuance of Early Site Permit (ESP) ESP-004 
to Southern Nuclear Operating Company (SNC), Georgia Power Company, 
Oglethorpe Power Corporation, Municipal Electric Authority of Georgia, 
and the City of Dalton, Georgia, an incorporated municipality in the 
State of Georgia acting by and through its Board of Water, Light and 
Sinking Fund Commissioners, for approval of a site located in Burke 
County, Georgia, 26 miles southeast of Augusta, Georgia for two nuclear 
power reactors; this action is separate from the filing of an 
application for a construction permit or combined license for such a 
facility. The NRC has found that the application for an early site 
permit (ESP), and accompanying limited work authorization (LWA), filed 
by Southern Nuclear Operating Company (SNC), on behalf of itself and 
the other four entities named above, complies with the applicable 
requirements of the Atomic Energy Act of 1954, as amended, and the 
applicable rules and regulations of the Commission. All required 
notifications to other agencies or bodies have been duly made. There is 
reasonable assurance that the permit holders will comply with the 
regulations in 10 CFR Chapter I and the health and safety of the public 
will not be endangered. There is reasonable assurance that the site is 
in conformity with the provisions of the Act and the Commission's 
regulations. SNC is technically qualified to engage in the activities 
authorized. Issuance of the ESP will not be inimical to the common 
defense and security or to the health and safety of the public. 
Issuance of the LWA will provide reasonable assurance of adequate 
protection to public health and safety and will not be inimical to the 
common defense and security. The proposed complete and integrated 
emergency plans are in accordance with the applicable standards of 10 
CFR 50.47, and the requirements of Appendix E to 10 CFR Part 50, and 
provide reasonable assurance that adequate protective measures can and 
will be taken in the event of a radiological emergency. The proposed 
inspections, tests, analyses and acceptance criteria, including those 
on emergency planning, are necessary and sufficient, within the scope 
of the ESP and LWA, to provide reasonable assurance that the facility 
has been constructed and will be operated in conformity with the 
license, the provisions of the Act, and the Commission's regulations. 
The issuance of this ESP, subject to the Environmental Protection Plan 
(EPP) and the conditions for the protection of the environment set 
forth in the permit, is in accordance with the National Environmental 
Policy Act of 1969, as amended, and with the applicable sections of 10 
CFR Part 51, ``Environmental Protection Regulations for Domestic 
Licensing and Related Regulatory Functions,'' as referenced by Subpart 
A, ``Early Site Permits,'' of 10 CFR Part 52, ``Licenses, 
Certifications, and Approvals for Nuclear Power Plants,'' and all 
applicable requirements therein have been satisfied.
    Accordingly, this early site permit was issued on August 26, 2009, 
and is effective immediately.

II. Further Information

    The NRC has prepared a Safety Evaluation Report (SER) and Final 
Environmental Impact Statement (FEIS) that document the information 
that was reviewed and NRC's conclusion. In accordance with 10 CFR 2.390 
of the NRC's ``Rules of Practice,'' details with respect to this 
action, including the SER and accompanying documentation included in 
the early site permit package, are available electronically at the 
NRC's Electronic Reading Room at http://www.nrc.gov/reading-rm/adams.html. From this site, persons can access the NRC's Agencywide 
Document Access and Management System (ADAMS), which provides text and 
image files of NRC's public documents. The ADAMS accession numbers for 
the documents related to this notice are:

ML092260348 NUREG-1923, ``Safety Evaluation Report for an Early Site 
Permit (ESP) at the Vogtle Electric Generating Plant (VEGP) ESP Site''
ML082260190 NUREG-1872, ``Final Environmental Impact Statement for an 
Early Site Permit (ESP) at the Vogtle Electric Generating Plant Site.''
ML082550040 Errata to NUREG-1872, ``Final Environmental Impact 
Statement for an Early Site Permit (ESP) at the Vogtle Electric 
Generating Plant Site.'' (Errata)
ML091550858 VEGP Early Site Permit Application--Revision 5

    Persons who do not have access to ADAMS or who encounter problems 
in accessing the documents located in ADAMS should contact the NRC 
Public Document Room (PDR) Reference staff by telephone at 1-800-397-
4209, 301-415-4737, or by e-mail to [email protected].
    These documents may also be viewed electronically on the public 
computers located at the NRC's Public Document Room (PDR), O 1 F21, One 
White Flint North, 11555 Rockville Pike, Rockville, MD 20852. The PDR 
reproduction contractor will copy documents for a fee.

    Dated at Rockville, Maryland, this 26th day of August, 2009.

    For the Nuclear Regulatory Commission.
Eileen M. McKenna,
Acting Chief, AP1000 Projects Branch, Division of New Reactor 
Licensing, Office of New Reactors.
[FR Doc. E9-20915 Filed 8-28-09; 8:45 am]