[Federal Register: September 1, 2009 (Volume 74, Number 168)]
[Notices]
[Page 45271-45273]
From the Federal Register Online via GPO Access [wais.access.gpo.gov]
[DOCID:fr01se09-117]
-----------------------------------------------------------------------
DEPARTMENT OF TRANSPORTATION
Federal Transit Administration
Intent to Prepare an Environmental Impact Statement for Proposed
Transit Improvements to the Orange Line, Cook County, IL
AGENCY: Federal Transit Administration (FTA), Department of
Transportation.
ACTION: Notice of Intent to Prepare an Environmental Impact Statement.
-----------------------------------------------------------------------
SUMMARY: The FTA, as the Federal lead agency, and the Chicago Transit
Authority (CTA) intend to prepare an Environmental Impact Statement
(EIS) for the Orange Line Extension Project in Cook County, Illinois.
CTA operates the rapid transit system in Chicago, Cook County,
Illinois. The proposed project, described more completely within, would
extend the Orange Line, a heavy rail transit line, to connect Midway
Station at the Midway International Airport to the Ford City shopping
center. The purpose of this Notice of Intent is to alert interested
parties regarding the intent to prepare the EIS and to provide
information on the nature of the proposed project and possible
alternatives to invite public participation in the EIS process.
DATES: Written comments on the scope of the EIS, including the
project's purpose and need, the alternatives to be considered, the
impacts to be evaluated, and the methodologies to be used in the
evaluations should be sent to CTA on or before October 27, 2009. See
ADDRESSES below for the address to which written public comments may be
sent. A public scoping meeting to accept comments on the scope of the
EIS will be held on the following date:
Monday, September 21, 2009; 6 p.m. to 8 p.m.; at the
Hancock College Preparatory High School, 4034 W. 56th St., Chicago, IL
60629.
The buildings used for the scoping meetings are accessible to
persons with disabilities. Any individual who requires special
assistance, such as a sign language interpreter, to participate in the
scoping meeting should contact Mr. Darud Akbar, Government and
Community Relations Officer, at 312-681-2708 or
dakbar@transitchicago.com, five days prior to the meeting.
Scoping materials describing the project purpose and need and the
alternatives proposed for analysis will be available at the meetings
and on the CTA Web site http://www.transitchicago.com/OrangeEIS. Paper
copies of the scoping materials may also be obtained from Mr. Darud
Akbar, Government and Community Relations Officer, at 312-681-2708 or
dakbar@transitchicago.com. An interagency scoping meeting will be held
on Thursday, September 24 at 1:30 p.m. at CTA Headquarters, in
Conference Room 2C, 567 W. Lake Street, Chicago, IL 60661.
Representatives of Native American tribal governments and of all
Federal, State, regional and local agencies that may have an interest
in any aspect of the project will be invited to be participating or
cooperating agencies, as appropriate.
ADDRESSES: Comments will be accepted at the public scoping meetings or
they may be sent to Mr. Jeffrey Busby, General Manager, Strategic
Planning, Chicago Transit Authority, P.O. Box 7602, Chicago, IL 60680-
7602, or via e-mail at OrangeExtension@transitchicago.com.
FOR FURTHER INFORMATION CONTACT: Mr. David Werner, Community Planner,
Federal Transit Administration, Region V, 200 West Adams Street, Suite
320, Chicago, IL 60606, phone 312-353-3879, e-mail
David.Werner@dot.gov.
SUPPLEMENTARY INFORMATION:
Scoping
The FTA and CTA invite all interested individuals and
organizations, public agencies, and Native American Tribes to comment
on the scope of the EIS, including the project's purpose and need, the
alternatives to be studied, the impacts to be evaluated, and the
evaluation methods to be used. Comments should address (1) alternatives
that may better achieve the project's need and purposes at less cost or
with fewer adverse impacts, and (2) any significant environmental
impacts relating to the alternatives.
National Environmental Policy Act (NEPA) ``scoping'' (40 CFR
1501.7) has specific and fairly limited objectives, one of which is to
identify the significant issues associated with alternatives that will
be examined in detail in the document, while simultaneously limiting
consideration and development of issues that are not truly significant.
It is in the NEPA scoping process that potentially significant
environmental impacts--those that give rise to the need to prepare an
environmental impact statement--should be identified; impacts that are
deemed not to be significant need not be developed extensively in the
context of the impact statement, thereby keeping the statement focused
on impacts of consequence. Transit projects may also generate
environmental benefits; these should be highlighted as well--the impact
statement process should draw attention to positive impacts, not just
negative impacts.
Once the scope of the environmental study, including significant
environmental issues to be addressed, is settled, an annotated outline
of the document will be prepared and shared with interested agencies
and the public. The outline serves at least three worthy purposes,
including (1) documenting the results of the scoping process; (2)
contributing to the transparency of the process; and (3) providing a
clear roadmap for concise development of the environmental document.
Purpose and Need for the Project
The purpose of the Orange Line Extension project is to improve
access to the existing Orange Line for southwest side and southwest
suburban residents and businesses, support the area's ongoing economic
development efforts, and strengthen the competiveness of transit in the
reverse commute market.
The need for the project is based on the following considerations:
access to the Orange Line is currently constrained by limited parking
availability; access to the Orange Line by bus or auto is unreliable
due to congestion approaching the existing terminal station; and few
uncongested roadways are available to access the current Orange Line
terminal because of wider than usual arterial street spacing, which
limits mobility for residents and businesses.
Project Location and Environmental Setting
The proposed heavy rail transit (HRT) project area lies about 10
miles southwest of the Chicago Central Area (commonly referred to as
the ``Loop''). The limits of the project area are 59th Street on the
north and 79th Street on the south. Midway International Airport is
located in the northwestern portion of the project area.
The project area includes parts of the community areas of Ashburn,
Clearing, and West Lawn within the City of Chicago, and is adjacent to
the Village of Bedford Park and the City of Burbank. The project area
is highly developed, with significant residential (primarily single
family), industrial, transportation
[[Page 45272]]
and commercial (retail and office) developments.
The locally preferred alternative (LPA) for the proposed Orange
Line Extension project was approved by the Chicago Transit Board for
further study in the EIS on August 12, 2009. The proposed Orange Line
Extension would extend the heavy rail transit line from Midway Station
at the Midway International Airport south along the Belt Railway
Company (BRC) right-of-way from 59th Street to Marquette Road, cross
the BRC Clearing Yard and terminate on Cicero Avenue. The extension
would include 2.3 new route miles of rapid transit to the existing
Orange Line and one additional station at approximately 7600 S. Cicero
Avenue, with new bus terminal and parking facilities.
Alternatives
The Orange Line Extension Final Alternatives Analysis Report (2009)
prepared by CTA identified three alternatives for further consideration
in the EIS. The three alternatives include: a No Build Alternative,
Transportation System Management (TSM) Alternative, and the Fixed
Guideway Alternative.
No-Build Alternative: The No Build Alternative is defined as the
existing transportation system, plus any committed transportation
improvements. Committed transportation improvements include projects
that are already in the Chicago Metropolitan Agency for Planning (CMAP)
financially constrained Transportation Improvement Program (TIP). The
Orange Line project area has one road improvement project included in
the FY 2007-2012 TIP; the Cicero Avenue Smart Corridor Project from
37th Street to 63rd Street scheduled for completion in 2009.
Bus transit service under the No Build Alternative would be focused
on the preservation of existing services and projects. The transit
network within the project area is projected to be substantially the
same as it is now. All elements of the No Build Alternative are
included in each of the other alternatives.
Transportation System Management (TSM) Alternative: A TSM
Alternative is proposed because it is required as part of the New
Starts evaluative process; in this case, it does not meet the purposes
of and need for the proposed project. The TSM Alternative is Bus Rapid
Transit (BRT) that would operate west on 59th Street from the 59th
Street Midway Station bus terminal to Cicero Avenue, and then south on
Cicero Avenue from 59th Street to approximately 76th Street. Proposed
BRT service would operate in mixed traffic with traffic signal priority
on the Cicero Avenue segment.
The TSM Alternative is 2.3 miles long and would not include any
intermediate stops. There would be no exclusive lanes along the Cicero
Avenue portion of the route. A new park and ride facility would be
constructed at the proposed terminal stop at approximately 7600 S.
Cicero. Bus route 67 67th/69th/71st would be re-routed to terminate at
the new Ford City Station.
Fixed Guideway Alternative/Locally Preferred Alternative (LPA): The
proposed LPA would operate partly in a trench and partly at-grade along
the BRC right-of-way between the existing Midway station and
approximately 6400 south, where it would transition to an elevated
structure above Marquette Road. The proposed route would travel under
59th Street and 63rd Street allowing those cross streets to remain open
to traffic. It then would veer to the southwest over the BRC Clearing
Yard and then continue south on an elevated structure in the median of
Cicero Avenue to a new Ford City terminal station located on Cicero
Avenue at approximately 76th Street.
The LPA is 2.3 miles long and would not include any intermediate
stops. The conceptual alignment design for the elevated structure at
Marquette Road would allow for a future station in that vicinity. The
Ford City terminal station would include a park-and-ride facility and
an improved bus terminal. The alternative assumes that Pace buses from
the south would continue to directly serve Midway Station. Route 67
67th/69th/71st would be re-routed to terminate at the new proposed Ford
City terminal station.
Two alignment options along Cicero Avenue to 76th Street will be
evaluated; an alignment above the median of Cicero Avenue and an
alignment located directly east of the Cicero Avenue right-of-way. The
alignment over the median of Cicero Avenue would have fewer property
acquisition costs and impacts to existing businesses; however, both
alignment options will be studied further in the EIS.
Possible Effects
The purpose of this EIS process is to study, in a public setting,
the effects of the proposed project and its alternatives on the quality
of the human environment. Areas of investigation for transit projects
generally include, but are not limited to: land use, development
potential, land acquisition and displacements, historic resources,
visual and aesthetic qualities, air quality, noise and vibration,
energy use, safety and security, and ecosystems, including threatened
and endangered species; investigation may reveal that the proposed
project will not affect or affect substantially many of those areas.
Measures to avoid, minimize, or mitigate any significant adverse
impacts will be identified.
FTA Procedures
The regulations implementing NEPA, as well as provisions of the
Safe, Accountable, Flexible, Efficient Transportation Equity Act: A
Legacy for Users (SAFETEA-LU), call for public involvement in the EIS
process. Section 6002 of SAFETEA-LU requires that FTA and CTA do the
following: (1) Extend an invitation to other Federal and non-Federal
agencies and Native American tribes that may have an interest in the
proposed project to become ``participating agencies;'' (2) provide an
opportunity for involvement by participating agencies and the public to
help define the purpose and need for a proposed project, as well as the
range of alternatives for consideration in the EIS; and (3) establish a
plan for coordinating public and agency participation in, and comment
on, the environmental review process. An invitation to become a
participating or cooperating agency, with scoping materials appended,
will be extended to other Federal and non-Federal agencies and Native
American tribes that may have an interest in the proposed project. It
is possible that FTA and CTA will not be able to identify all Federal
and non-Federal agencies and Native American tribes that may have such
an interest. Any Federal or non-Federal agency or Native American tribe
interested in the proposed project that does not receive an invitation
to become a participating agency should notify at the earliest
opportunity the Project Manager identified above under ADDRESSES.
A comprehensive public involvement program and a Coordination Plan
for public and interagency involvement will be developed for the
project and posted on CTA's Web site http://www.transitchicago.com/
OrangeEIS. The public involvement program includes a full range of
activities including maintaining the project Web page on the CTA Web
site and outreach to local officials, community and civic groups, and
the public. Specific activities or events for involvement will be
detailed in the project's public participation plan.
The Paperwork Reduction Act seeks, in part, to minimize the cost to
the taxpayer of the creation, collection, maintenance, use,
dissemination, and disposition of information. Consistent
[[Page 45273]]
with this goal and with principles of economy and efficiency in
government, it is FTA policy to limit insofar as possible distribution
of complete printed sets of environmental documents. Accordingly,
unless a specific request for a complete printed set of environmental
documents is received (preferably in advance of printing), FTA and its
grantees will distribute only the executive summary of the
environmental document together with a Compact Disc of the complete
environmental document. A complete printed set of the environmental
document is available for review at the grantee's offices and
elsewhere; an electronic copy of the complete environmental document is
also available on the grantee's Web page.
CTA may seek New Starts funding for the proposed project under 49
United States Code 5309 and will, therefore, be subject to New Starts
regulations (49 Code of Federal Regulations (CFR) Part 611). The New
Starts regulations also require the submission of certain project-
justification information to support a request to initiate preliminary
engineering. This information is normally developed in conjunction with
the NEPA process. Pertinent New Starts evaluation criteria will be
included in the EIS.
The EIS will be prepared in accordance with NEPA and its
implementing regulations issued by the Council on Environmental Quality
(40 CFR parts 1500-1508) and with the FTA/Federal Highway
Administration regulations ``Environmental Impact and Related
Procedures'' (23 CFR part 771).
Issued on: August 24, 2009.
Marisol R. Simon,
Regional Administrator, Federal Transit Administration, Region V.