[Federal Register: March 17, 2009 (Volume 74, Number 50)]
[Notices]
[Page 11369-11370]
From the Federal Register Online via GPO Access [wais.access.gpo.gov]
[DOCID:fr17mr09-43]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP09-58-000]
Rockies Express Pipeline LLC; Notice of Intent To Prepare an
Environmental Assessment for the Proposed Meeker to Cheyenne Expansion
Project and Request for Comments on Environmental Issues
March 10, 2009.
The staff of the Federal Energy Regulatory Commission (FERC or
Commission) will prepare an environmental assessment (EA) that will
discuss the environmental impacts of the Meeker to Cheyenne Expansion
Project involving construction and operation of facilities by Rockies
Express Pipeline LLC (REX) in Moffat County, Colorado, and Carbon
County, Wyoming. This EA will be used by the Commission in its
decision-making process to determine whether the project is in the
public convenience and necessity.
This Notice of Intent (NOI) announces the opening of the scoping
process we will use to gather input from the public and interested
agencies on the project. Your input will help the Commission staff
determine which issues need to be evaluated in the EA. Please note that
the scoping period will close on April 9, 2009.
This notice is being sent to landowners of property within 2.5 mile
of the Big Hole and Arlington Compressor Stations; Federal, State, and
local government representatives and agencies; elected officials;
environmental and public interest groups; Native American Tribes; other
interested parties; and local libraries and newspapers. State and local
government representatives are asked to notify their constituents of
this planned project and encourage them to comment on their areas of
concern.
A fact sheet prepared by the FERC entitled ``An Interstate Natural
Gas Facility On My Land? What Do I Need To Know?'' is available for
viewing on the FERC Internet Web site (http://www.ferc.gov). This fact
sheet addresses a number of typically asked questions, including the
use of eminent domain and how to participate in the Commission's
proceedings.
Summary of the Proposed Project
REX proposes to design, construct, and maintain (a) a new 17,500-
horsepower (hp) electric-driven compressor unit at the existing
Arlington Compressor Station in Carbon County, Wyoming; and (b) a new
20,500-hp gas-fired compressor unit at the existing Big Hole Compressor
Station in Moffat County, Colorado.
Carbon Power and Light, Inc. (CP&L) would construct a 230-kilovolt
electric transmission line about three (3) miles long to serve the
electric compressor units at the Arlington Compressor Station. The
proposed transmission line would begin at the Foot Creek Substation and
follow a route to the southwest along Wyoming State Highway 13 to
CP&L's planned Arlington substation site adjacent to the Arlington
Compressor Station.\1\
---------------------------------------------------------------------------
\1\ This NOI is also being sent to affected landowners along the
planned CP&L non-jurisdictional transmission line.
---------------------------------------------------------------------------
The additional compression expansion would provide an additional
200,000 dekatherms per day (Dth/day) of natural gas from the Meeker Hub
northward to the Wamsutter Hub and continuing eastward to the Cheyenne
Hub as a result of a ``ramp-up'' contractual agreement with EnCana
Marketing USA. If approved, REX proposes to commence construction of
the proposed facilities in July 2010.
The general location map of REX's Meeker to Cheyenne Expansion
Project and CP&L's facilities are shown in Appendix 1.\2\
---------------------------------------------------------------------------
\2\ The appendices referenced in this notice are not being
printed in the Federal Register. Copies of all appendices, other
than appendix 1 (maps) are available on the Commissions Web site at
the ``eLibrary'' link or from the Commission's Public Reference
Room, 888 First Street, NE., Washington, DC 20426, or call (202)
502-8371. For instruction on connecting to eLibrary, refer to the
last page of this notice. Copies of the appendices were sent to all
those receiving this notice in the mail.
---------------------------------------------------------------------------
Land Requirements for Construction
Construction of the compressor station expansions would occur
completely within the fenced property boundaries of the existing 19.4-
acre Big Hole and 10.8-acre Arlington Compressor Stations. Land
required for operation of the new compressor units would be 0.7 acre
within the existing compressor station sites. Existing public roads
would be used to access the facilities.
CP&L's planned transmission line would be about 4.2 miles long with
a 150-foot wide right of way (ROW). Support structures would be
``H~Frame'' wooden poles which would be placed every 650 feet apart for
a total of about 34 structures. Land disturbance during construction
would be approximately 2800 square feet per structure. At each
structure there would be a 100-foot by 100-foot area that would be
permanently cleared of trees or shrubbery.
The EA Process
The National Environmental Policy Act (NEPA) requires the
Commission to take into account the environmental impacts that could
result from an action whenever it considers the issuance of a
Certificate of Public Convenience and Necessity. NEPA also requires us
to discover and address concerns the public may have about proposals.
This process is referred to as ``scoping.'' The main goal of the
scoping process is to focus the analysis in the EA on the important
environmental issues. By this NOI, the Commission staff requests public
comments on the scope of the issues to address in the EA. All comments
received are considered during the preparation of the EA. State and
local government representatives are encouraged to notify their
constituents of this proposed action and encourage them to comment on
their areas of concern.
In the EA we \3\ will discuss impacts that could occur as a result
of the construction and operation of the proposed project under these
general headings:
---------------------------------------------------------------------------
\3\ ``We,'' ``us,'' and ``our'' refer to the environmental staff
of the Office of Energy Projects (OEP).
---------------------------------------------------------------------------
Geology and soils.
Land use.
Water resources, fisheries, and wetlands.
Cultural resources.
Vegetation and wildlife.
Air quality and noise.
Endangered and threatened species.
Public safety.
We will also evaluate possible alternatives to the proposed project
or
[[Page 11370]]
portions of the project, and make recommendations on how to lessen or
avoid impacts on the various resource areas.
Our independent analysis of the issues will be in the EA. Depending
on the comments received during the scoping process, the EA may be
published and mailed to federal, state, and local agencies; public
interest groups; interested individuals; affected landowners;
newspapers; libraries; and the Commission's official service list for
this proceeding. A comment period will be allotted for review if the EA
is published. We will consider all comments on the EA before we make
our recommendations to the Commission. To ensure your comments are
considered, please carefully follow the instructions in the public
participation section below.
Public Participation
You can make a difference by providing us with your specific
comments or concerns about the Meeker to Cheyenne Expansion Project.
Your comments should focus on the potential environmental effects,
reasonable alternatives, and measures to avoid or lessen environmental
impacts. The more specific your comments, the more useful they will be.
To ensure that your comments are timely and properly recorded, please
send in your comments so that they will be received in Washington, DC
on or before April 9, 2009.
For your convenience, there are three methods in which you can use
to submit your comments to the Commission. In all instances please
reference the project docket number CP09-58-000 with your submission.
The docket number can be found on the front of this notice. The
Commission encourages electronic filing of comments and has dedicated
eFiling expert staff available to assist you at 202-502-8258 or
efiling@ferc.gov.
(1) You may file your comments electronically by using the Quick
Comment feature, which is located on the Commission's Internet Web site
at http://www.ferc.gov under the link to Documents and Filings. A Quick
Comment is an easy method for interested persons to submit text-only
comments on a project;
(2) You may file your comments electronically by using the eFiling
feature, which is located on the Commission's Internet website at
http://www.ferc.gov under the link to Documents and Filings. eFiling
involves preparing your submission in the same manner as you would if
filing on paper, and then saving the file on your computer's hard
drive. You will attach that file as your submission. New eFiling users
must first create an account by clicking on ``Sign up'' or
``eRegister.'' You will be asked to select the type of filing you are
making. A comment on a particular project is considered a ``Comment on
a Filing;'' or
(3) You may file your comments via mail to the Commission by
sending an original and two copies of your letter to: Kimberly D. Bose,
Secretary, Federal Energy Regulatory Commission, 888 First Street, NE.,
Room 1A, Washington, DC 20426.
Label one copy of the comments for the attention of Gas Branch 1,
PJ11.1.
Environmental Mailing List
An effort is being made to send this notice to all individuals,
organizations, and government entities interested in and/or potentially
affected by the proposed project. This includes all landowners who are
potential right-of-way grantors, whose property may be used temporarily
for project purposes, or who own homes within distances defined in the
Commission's regulations of certain aboveground facilities.
If you do not want to send comments at this time but still want to
remain on our mailing list, please return the Information Request
(Appendix 2). If you do not return the Information Request, you will be
taken off the mailing list.
Becoming an Intervenor
In addition to involvement in the EA scoping process, you may want
to become an ``intervenor,'' which is an official party to the
proceeding. Intervenors play a more formal role in the process and are
able to file briefs, appear at hearings, and be heard by the courts if
they choose to appeal the Commission's final ruling. An intervenor
formally participates in a Commission proceeding by filing a request to
intervene. Instructions for becoming an intervenor are included in the
User's Guide under the ``e-filing'' link on the Commission's Internet
Web site.
Additional Information
Additional information about the project is available from the
Commission's Office of External Affairs, at 1-866-208-FERC or on the
FERC Internet Web site (http://www.ferc.gov) using the eLibrary link.
Click on the eLibrary link, click on ``General Search'' and enter the
docket number excluding the last three digits in the Docket Number
field. Be sure you have selected an appropriate date range. For
assistance, please contact FERC Online Support at
FercOnlineSupport@ferc.gov or toll free at 1-866-208-3676, or for TTY,
contact (202)502-8659. The eLibrary link also provides access to the
texts of formal documents issued by the Commission, such as orders,
notices, and rulemakings.
In addition, the Commission now offers a free service called
eSubscription which allows you to keep track of all formal issuances
and submittals in specific dockets. This can reduce the amount of time
you spend researching proceedings by automatically providing you with
notification of these filings, document summaries and direct links to
the documents. Go to http://www.ferc.gov/esubscribenow.htm.
Finally, public meetings or site visits will be posted on the
Commission's calendar located at http://www.ferc.gov/EventCalendar/
EventsList.aspx along with other related information.
Kimberly D. Bose,
Secretary.
[FR Doc. E9-5679 Filed 3-16-09; 8:45 am]
BILLING CODE 6717-01-P