[Federal Register Volume 75, Number 87 (Thursday, May 6, 2010)]
[Notices]
[Pages 24938-24940]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2010-10641]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. PF10-7-000]


Questar Pipeline Company; Notice of Intent to Prepare an 
Environmental Assessment for the Planned Mainline 104 Expansion Project 
and Request for Comments on Environmental Issues

April 29, 2010.
    The staff of the Federal Energy Regulatory Commission (FERC or 
Commission) will prepare an environmental assessment (EA) that will 
discuss the environmental impacts of the Mainline 104 Expansion 
Project, involving construction and operation of facilities by Questar 
Pipeline Company (Questar) in Uintah County, Utah. This EA will be used 
by the Commission in its decision-making process to determine whether 
the project is in the public convenience and necessity.
    This notice announces the opening of the scoping process the 
Commission will use to gather input from the public and interested 
agencies on the project. Your input will help the Commission staff 
determine what issues need to be evaluated in the EA. Please note that 
the scoping period will close on May 29, 2010.
    This notice is being sent to the Commission's current environmental 
mailing list for this project. State and local government 
representatives are asked to notify their constituents of this planned 
project and encourage them to comment on their areas of concern.
    A fact sheet prepared by the FERC entitled ``An Interstate Natural 
Gas Facility On My Land? What Do I Need To Know?'' is available for 
viewing on the FERC Web site (http://www.ferc.gov). This fact sheet 
addresses a number of typically-asked questions, including the use of 
eminent domain and how to participate in the Commission's proceedings.

Summary of the Planned Project

    Questar plans to construct and operate about 23.3 miles of 24-inch-
diameter pipeline in Uintah County, Utah. The Mainline 104 Expansion 
Project would loop \1\ the western end of Questar's existing Mainline 
40 between its existing Green River Block Valve and its Fidlar 
Compressor Staiton. According to Questar, its project would allow 
existing shippers to amend the primary receipt-point capacity eastward 
to Fidlar.
---------------------------------------------------------------------------

    \1\ A pipeline loop is constructed parallel to an existing 
pipeline to increase capacity.
---------------------------------------------------------------------------

    The Mainline 104 Expansion Project would consist of the following 
facilities:
     23.5 miles of 24-inch-diameter looping pipeline;
     four mainline block valves;
     two pig launchers/receivers; \2\
---------------------------------------------------------------------------

    \2\ A ``pig'' is a tool that is inserted into and moves through 
the pipeline, and is used for cleaning the pipeline, internal 
inspections, or other purposes.
---------------------------------------------------------------------------

     six taps; and
     minor modifications at the existing Fidlar Compressor 
Station.
    The general location of the project facilities is shown in appendix 
1.\3\
---------------------------------------------------------------------------

    \3\ The appendices referenced in this notice are not being 
printed in the Federal Register. Copies of appendices were sent to 
all those receiving this notice in the mail and are available at 
http://www.ferc.gov using the link called ``eLibrary'' or from the 
Commission's Public Reference Room, 888 First Street, NE., 
Washington, DC 20426, or call (202) 502-8371. For instructions on 
connecting to eLibrary, refer to the last page of this notice.
---------------------------------------------------------------------------

Land Requirements for Construction

    Construction of the planned facilities would disturb about 336 
acres of land for the above ground facilities and the pipeline. 
Following construction, about 142 acres would be maintained for 
permanent operation of the project's facilities; the remaining acreage 
would be restored and allowed to revert to former uses. About 70 
percent of the planned pipeline route parallels existing pipeline, 
utility, or road rights-of-way.

The EA Process

    The National Environmental Policy Act (NEPA) requires the 
Commission to take into account the environmental impacts that could 
result from an action whenever it considers the issuance of a 
Certificate of Public Convenience and Necessity. NEPA also requires us 
\4\ to discover and address concerns the public may have about 
proposals. This process is referred to as scoping. The main goal of the 
scoping process is to focus the analysis in the EA on the important 
environmental issues. By this notice, the Commission requests public 
comments on the scope of the issues to address in the EA. All comments 
received will be considered during the preparation of the EA.
---------------------------------------------------------------------------

    \4\ ``We'', ``us'', and ``our'' refer to the environmental staff 
of the Commission's Office of Energy Projects.
---------------------------------------------------------------------------

    In the EA, we will discuss impacts that could occur as a result of 
the construction and operation of the

[[Page 24939]]

planned project under these general headings:
     Geology and soils;
     land use;
     water resources, fisheries, and wetlands;
     cultural resources;
     vegetation and wildlife;
     air quality and noise;
     endangered and threatened species; and
     public safety.
    We will also evaluate possible alternatives to the planned project 
or portions of the project, and make recommendations on how to lessen 
or avoid impacts on the various resource areas.
    Although no formal application has been filed, we have already 
initiated our NEPA review under the Commission's pre-filing process. 
The purpose of the pre-filing process is to encourage early involvement 
of interested stakeholders and to identify and resolve issues before an 
application is filed with the FERC. As part of our pre-filing review, 
we have begun to contact some federal and state agencies to discuss 
their involvement in the scoping process and the preparation of the EA.
    Our independent analysis of the issues will be presented in the EA. 
The EA will be placed in the public record and, depending on the 
comments received during the scoping process, may be published and 
distributed to the public. A comment period will be allotted if the EA 
is published for review. We will consider all comments on the EA before 
we make our recommendations to the Commission. To ensure your comments 
are considered, please carefully follow the instructions in the Public 
Participation section beginning on page 4.
    With this notice, we are asking agencies with jurisdiction and/or 
special expertise with respect to environmental issues to formally 
cooperate with us in the preparation of the EA. These agencies may 
choose to participate once they have evaluated the proposal relative to 
their responsibilities. Agencies that would like to request cooperating 
agency status should follow the instructions for filing comments 
provided under the Public Participation section of this notice. 
Currently, the U.S. Department of Interior's Bureau of Indian Affairs, 
Bureau of Land Management (BLM), and U.S. Fish and Wildlife Service 
have expressed their intention to participate as cooperating agencies 
in the preparation of the EA to satisfy their NEPA responsibilities 
related to this project.

Consultations Under Section 106 of the National Historic Preservation 
Act

    In accordance with the Advisory Council on Historic Preservation's 
implementing regulations, we are using this notice to solicit the views 
of the public on the project's potential effects on historic 
properties.\5\ We will document our findings on the impacts on cultural 
resources and summarize the status of consultations under section 106 
of the National Historic Preservation Act in our EA.
---------------------------------------------------------------------------

    \5\ The Advisory Council on Historic Preservation's regulations 
are at Title 36 of the Code of Federal Regulations, Part 800. 
Historic properties are defined in those regulations as any 
prehistoric or historic district, site, building, structure, or 
object included in or eligible for inclusion in the National 
Register for Historic Places.
---------------------------------------------------------------------------

Currently Identified Environmental Issues

    We have already identified several issues that we think deserve 
attention based on a preliminary review of the planned facilities and 
the environmental information provided by Questar. This preliminary 
list of issues may be changed based on your comments and our analysis.
     Approach and crossing of the Green River;
     Crossing the Uintah and Ouray Reservation; and
     Crossing state and federal lands.

Public Participation

    You can make a difference by providing us with your specific 
comments or concerns about the project. Your comments should focus on 
the potential environmental effects, reasonable alternatives, and 
measures to avoid or lessen environmental impacts. The more specific 
your comments, the more useful they will be. To ensure that your 
comments are timely and properly recorded, please send your comments so 
that they will be received in Washington, DC on or before May 29, 2010.
    For your convenience, there are three methods you can use to submit 
your comments to the Commission. In all instances, please reference the 
project docket number PF10-7-000 with your submission. The Commission 
encourages electronic filing of comments and has expert eFiling staff 
available to assist you at (202) 502-8258 or [email protected].
    (1) You may file your comments electronically by using the Quick 
Comment feature, which is located at http://www.ferc.gov under the link 
called ``Documents and Filings''. A Quick Comment is an easy method for 
interested persons to submit text-only comments on a project;
    (2) You may file your comments electronically by using the 
``eFiling'' feature that is listed under the ``Documents and Filings'' 
link. eFiling involves preparing your submission in the same manner as 
you would if filing on paper, and then saving the file on your 
computer's hard drive. You will attach that file to your submission. 
New eFiling users must first create an account by clicking on the links 
called ``Sign up'' or ``eRegister''. You will be asked to select the 
type of filing you are making. A comment on a particular project is 
considered a ``Comment on a Filing''; or
    (3) You may file a paper copy of your comments at the following 
address: Kimberly D. Bose, Secretary, Federal Energy Regulatory 
Commission, 888 First Street, NE., Room 1A, Washington, DC 20426.

Environmental Mailing List

    The environmental mailing list includes federal, state, and local 
government representatives and agencies; elected officials; 
environmental and public interest groups; Native American Tribes; and 
local libraries and newspapers. This list includes all affected 
landowners (as defined in the Commission's regulations) who are 
potential right-of-way grantors, whose property may be used temporarily 
for project purposes, or who own homes within certain distances of 
aboveground facilities, and anyone who submits comments on the project. 
We will update the environmental mailing list as the analysis proceeds 
to ensure that we send the information related to this environmental 
review to all individuals, organizations, and government entities 
interested in and/or potentially affected by the planned project.
    If the EA is published for distribution, copies will be sent to the 
environmental mailing list for public review and comment. If you would 
prefer to receive a paper copy of the document instead of the CD 
version or would like to remove your name from the mailing list, please 
return the attached Information Request (appendix 2).

Becoming an Intervenor

    Once Questar files its application with the Commission, you may 
want to become an ``intervenor'' which is an official party to the 
Commission's proceeding. Intervenors play a more formal role in the 
process and are able to file briefs, appear at hearings, and be heard 
by the courts if they choose to appeal the Commission's final ruling.

[[Page 24940]]

An intervenor formally participates in the proceeding by filing a 
request to intervene. Instructions for becoming an intervenor are 
included in the User's Guide under the ``e-filing'' link on the 
Commission's Web site. Please note that the Commission will not accept 
requests for intervenor status at this time. You must wait until a 
formal application for the project is filed with the Commission.

Additional Information

    Additional information about the project is available from the 
Commission's Office of External Affairs, at (866) 208-FERC, or on the 
FERC Web site (http://www.ferc.gov) using the eLibrary link. Click on 
the eLibrary link, click on ``General Search'' and enter the docket 
number, excluding the last three digits in the Docket Number field 
(i.e., PF10-7). Be sure you have selected an appropriate date range. 
For assistance, please contact FERC Online Support at 
[email protected] or toll free at (866) 208-3676, or for TTY, 
contact (202) 502-8659. The eLibrary link also provides access to the 
texts of formal documents issued by the Commission, such as orders, 
notices, and rulemakings.
    In addition, the Commission offers a free service called 
eSubscription which allows you to keep track of all formal issuances 
and submittals in specific dockets. This can reduce the amount of time 
you spend researching proceedings by automatically providing you with 
notification of these filings, document summaries, and direct links to 
the documents. Go to http://www.ferc.gov/esubscribenow.htm.
    Finally, public meetings or site visits will be posted on the 
Commission's calendar located at http://www.ferc.gov/EventCalendar/EventsList.aspx along with other related information.

Kimberly D. Bose,
Secretary.
[FR Doc. 2010-10641 Filed 5-5-10; 8:45 am]
BILLING CODE 6717-01-P