DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 12745-002]
Modesto Irrigation District and Turlock Irrigation District;
Notice of Preliminary Permit Application Accepted for Filing and
Soliciting Comments, Motions to Intervene, and Competing Applications
June 16, 2010.
On February 1, 2010, Modesto Irrigation District and Turlock
Irrigation District filed an application for a preliminary permit,
pursuant to section 4(f) of the Federal Power Act, proposing to study
the feasibility of the Red Mountain Bar Pumped Storage Project located
on the Tuolomne River, Don Pedro reservoir, in Tuolomne County,
California. The sole purpose of a preliminary permit, if issued, is to
grant the permit holder priority to file a license application during
the permit term. A preliminary permit does not authorize the permit
holder to perform any land-disturbing activities or otherwise enter
upon lands or waters owned by others without the owners' express
permission.
The proposed pumped storage project would consist of the following
new and existing facilities:
Alternative A (Single Speed Unit)--(1) An upper reservoir with a
total active storage capacity of 34,000 acre-feet and a surface area of
244 acres at maximum normal water surface elevation of 1,570 feet above
mean sea level (msl); (2) a one-half-mile-long, 34-foot-diameter tunnel
to connect the upper reservoir with the existing Don Pedro reservoir;
(3) a powerhouse with pump/turbines having an installed capacity of
approximately 900 megawatts (MW); (4) an intake on the existing Don
Pedro reservoir, which would be used as the lower reservoir; and (5) a
47-mile-long, 230-kilovolt transmission line. Alternative A of the
proposed project would have an annual generation of 1,573,000 megawatt-
hours (MWh).
Alternative B (Variable Speed Unit)--(1) An upper reservoir with a
total active storage capacity of 34,000 acre-feet and a surface area of
244 acres at maximum normal water surface elevation of 1,570 feet msl;
(2) a 1.1-mile-long, 37-foot-diameter tunnel to connect the upper
reservoir with the existing Don Pedro reservoir; (3) a powerhouse with
pump/turbines having an installed capacity of approximately 1,000 MW;
(4) an intake on the existing Don Pedro reservoir, which would be used
as the lower reservoir; and (5) a 47-mile-long, 230-kilovolt
transmission line. Alternative B of the proposed project would have an
annual generation of 1,747,000 MWh.
Applicant Contact: Donald H. Clarke, Law Offices of GKRSE, 1500 K
Street, NW., Washington, DC 20005; phone: (202) 408-5400.
FERC Contact: Jim Hastreiter, 503-552-2760.
Deadline for filing comments, motions to intervene, competing
applications (without notices of intent), or notices of intent to file
competing applications: 60 days from the issuance of this notice.
Competing applications and notices of intent must meet the requirements
of 18 CFR 4.36. Comments, motions to intervene, notices of intent, and
competing applications may be filed electronically via the Internet.
See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission's
Web site (http://www.ferc.gov/docs-filing/ferconline.asp) under the
``eFiling'' link. For a simpler method of submitting text-only
comments, click on ``Quick Comment.'' For assistance, please contact
FERC Online Support at [email protected]; call toll-free at
(866) 208-3676; or, for TTY, contact (202) 502-8659. Although the
[[Page 35779]]
Commission strongly encourages electronic filing, documents may also be
paper-filed. To paper-file, mail an original and eight copies to:
Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888
First Street, NE., Washington, DC 20426.
More information about this project, including a copy of the
application, can be viewed or printed on the ``eLibrary'' link of the
Commission's Web site at http://www.ferc.gov/docs-filing/elibrary.asp.
Enter the docket number (P-12745) in the docket number field to access
the document. For assistance, contact FERC Online Support.
Kimberly D. Bose,
Secretary.
[FR Doc. 2010-15139 Filed 6-22-10; 8:45 am]
BILLING CODE 6717-01-P