[Federal Register Volume 75, Number 128 (Tuesday, July 6, 2010)]
[Notices]
[Pages 38799-38800]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2010-16282]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP10-459-000]


ETC Tiger Pipeline, LLC; Notice of Application

June 25, 2010.
    Take notice that on June 15, 2010, ETC Tiger Pipeline, LLC (ETC 
Tiger), 711 Louisiana Street, Suite 900, Houston, Texas 77002, filed an 
application in Docket No. CP10-459-000 pursuant to section 7(c) of the 
Natural Gas Act (NGA), and Part 157, Subpart A of the Commission's 
regulations requesting: (1) Authorization to construct, own, operate 
and maintain approximately 20.5 miles of 42-inch diameter natural gas 
pipeline and 30,565 horsepower of compression located in Louisiana 
capable of transporting up to 400,000 Mcf/day (Expansion Project); (2) 
a pre-determination of rolled-in rate treatment for the costs 
associated with the Expansion Project; and (3) approval of incremental 
fuel charges for transportation service provided by the proposed 
facilities, all as more fully set forth in the application which is on 
file with the Commission and open for public inspection.
    Any questions regarding the applications should be directed to Joey 
Mahmoud, Vice President, Energy Transfer Partners, L.P., 711 Louisiana 
Street, Suite 900, Houston, Texas 77002, 832-668-1242, 
[email protected] or Lisa M. Tonery, Fulbright & 
Jaworski L.L.P., 666 Fifth Avenue, New York, New York 10103, 212-318-
3009, [email protected].
    Pursuant to section 157.9 of the Commission's rules, 18 CFR 157.9, 
within 90 days of this Notice the Commission staff will either: 
complete its environmental assessment (EA) and place it into the 
Commission's public record (eLibrary) for this proceeding; or issue a 
Notice of Schedule for Environmental Review. If a Notice of Schedule 
for Environmental Review is issued, it will indicate, among other 
milestones, the anticipated date for the Commission staff's issuance of 
the final environmental impact statement (FEIS) or EA for this 
proposal. The filing of the EA in the Commission's public record for 
this proceeding or the issuance of a Notice of Schedule for 
Environmental Review will serve to notify federal and state agencies of 
the timing for the completion of all necessary reviews, and the 
subsequent need to complete all federal authorizations within 90 days 
of the date of issuance of the Commission staff's FEIS or EA.
    There are two ways to become involved in the Commission's review of 
this project. First, any person wishing to obtain legal status by 
becoming a party to the proceedings for this project should, on or 
before the comment date stated below, file with the Federal Energy 
Regulatory Commission, 888 First Street, NE., Washington, DC 20426, a 
motion to intervene in accordance with the requirements of the 
Commission's Rules of Practice and Procedure (18 CFR 385.214 or 
385.211) and the Regulations under the NGA (18 CFR 157.10). A person 
obtaining party status will be placed on the service list maintained by 
the Secretary of the Commission and will receive copies of all 
documents filed by the applicant and by all other parties. A party must 
submit

[[Page 38800]]

14 copies of filings made with the Commission and must mail a copy to 
the applicant and to every other party in the proceeding. Only parties 
to the proceeding can ask for court review of Commission orders in the 
proceeding.
    However, a person does not have to intervene in order to have 
comments considered. The second way to participate is by filing with 
the Secretary of the Commission, as soon as possible, an original and 
two copies of comments in support of or in opposition to this project. 
The Commission will consider these comments in determining the 
appropriate action to be taken, but the filing of a comment alone will 
not serve to make the filer a party to the proceeding. The Commission's 
rules require that persons filing comments in opposition to the project 
provide copies of their protests only to the party or parties directly 
involved in the protest.
    Persons who wish to comment only on the environmental review of 
this project should submit an original and two copies of their comments 
to the Secretary of the Commission. Environmental commentors will be 
placed on the Commission's environmental mailing list, will receive 
copies of the environmental documents, and will be notified of meetings 
associated with the Commission's environmental review process. 
Environmental commentors will not be required to serve copies of filed 
documents on all other parties. However, the non-party commentors will 
not receive copies of all documents filed by other parties or issued by 
the Commission (except for the mailing of environmental documents 
issued by the Commission) and will not have the right to seek court 
review of the Commission's final order.
    The Commission strongly encourages electronic filings of comments, 
protests and interventions in lieu of paper using the ``eFiling'' link 
at http://www.ferc.gov. Persons unable to file electronically should 
submit an original and 14 copies of the protest or intervention to the 
Federal Energy regulatory Commission, 888 First Street, NE., 
Washington, DC 20426.
    This filing is accessible on-line at http://www.ferc.gov, using the 
``eLibrary'' link and is available for review in the Commission's 
Public Reference Room in Washington, DC. There is an ``eSubscription'' 
link on the Web site that enables subscribers to receive e-mail 
notification when a document is added to a subscribed docket(s). For 
assistance with any FERC Online service, please e-mail 
[email protected], or call (866) 208-3676 (toll free). For 
TTY, call (202) 502-8659.
    Comment Date: July 16, 2010.

Kimberly D. Bose,
Secretary.
[FR Doc. 2010-16282 Filed 7-2-10; 8:45 am]
BILLING CODE 6717-01-P