Notice of Availability of Draft Environmental Impact Statement
for the Tonopah Solar Energy Crescent Dunes Solar Energy Project, Nye
County, NV
AGENCY: Bureau of Land Management, Interior.
ACTION: Notice of availability.
-----------------------------------------------------------------------
SUMMARY: In accordance with the National Environmental Policy Act of
1969, as amended (NEPA), the Bureau of Land Management (BLM) has
prepared a Draft Environmental Impact Statement (EIS) for the Crescent
Dunes Solar Energy Project, Nye County, Nevada, and by this Notice is
announcing the opening of the comment period.
DATES: To ensure comments will be considered, the BLM must receive
written comments on the Crescent Dunes Solar Energy Project Draft EIS
within 45 days following the date the Environmental Protection Agency
publishes its Notice of Availability in the Federal Register. The BLM
will announce future meetings or hearings and any other public
involvement activities at least 15 days in advance through public
notices, media news releases, and/or mailings.
ADDRESSES: You may submit comments on the Crescent Dunes Solar Energy
Project Draft EIS by any of the following methods:
E-mail: [email protected].
Fax: 775-482-7810.
Mail: Timothy Coward, Renewable Energy Project Manager,
BLM Tonopah Field Office, P.O. Box 911, Tonopah, Nevada 89049.
Copies of the Draft EIS for the Crescent Dunes Solar Energy Project
are available at the BLM Tonopah Field Office and at the Battle
Mountain District Office, 50 Bastian Road, Battle Mountain, Nevada, or
at the following Web site: http://www.blm.gov/nv/st/en/fo/battle_mountain_field.html.
FOR FURTHER INFORMATION CONTACT: Timothy Coward, (775) 482-7800, BLM
Tonopah Field Office, 1553 South Main Street, P.O. Box 911, Tonopah,
Nevada 89049; [email protected].
SUPPLEMENTARY INFORMATION: Tonopah Solar Energy, LLC applied to the BLM
for a 7,680-acre right-of-way (ROW) on public lands to construct a
concentrated solar thermal power plant facility approximately 13 miles
northwest of Tonopah, Nye County, Nevada. The proposed project is not
expected to use the total acres applied for in the ROW application. The
project is located within the southern portion of the Big Smoky Valley,
north of U.S. Highway 95/6 along the Gabbs Pole Line Road (State
Highway 89). The facility is expected to operate for approximately 30
years. The proposed solar power project would use concentrated solar
power technology, using heliostats or mirrors to focus sunlight on a
receiver erected in the center of the solar field (the power tower or
central receiver). A heat transfer fluid is heated as it passes through
the receiver and is then circulated through a series of heat exchangers
to generate high-pressure steam. The steam is used to power a
conventional Rankine cycle steam turbine, which produces electricity.
The exhaust steam from the turbine is condensed and returned via
feedwater pumps to the heat exchangers where steam is regenerated.
Hybrid cooling processes would be used for this project to minimize
water use while continuing to maintain efficient power generation. The
plant design would generate a nominal capacity of 100 megawatts.
The project's proposed facility design includes the heliostat
fields, a 653-foot central receiver tower, a power block, buildings, a
parking area, a laydown area, evaporating ponds, and an access road. A
single overhead 230-kilovolt transmission line would connect the plant
to the nearby Anaconda Moly substation.
The Draft EIS describes and analyzes the proposed project's site-
specific impacts on air quality, biological resources, cultural
resources, water resources, geological resources, hazardous materials
handling, land use, noise, paleontological resources, public health,
socioeconomics, soils, traffic and transportation, visual resources,
wilderness characteristics, waste management, worker safety, and fire
protection. The Draft EIS also describes facility design engineering,
efficiency, reliability, transmission system engineering, and
transmission line safety.
Three action alternatives were analyzed in addition to the No
Action alternative: the Proposed Action Alternative, Alternative 1, and
Alternative 2. Alternative 2 is the BLM preferred alternative.
Scoping of the project occurred from November 24, 2009 through
December 24, 2009. A total of 24 comments were received. Comments on
cumulative impacts identified the affects to air quality to include
criteria pollutant and ``Dark Sky'' attributes on the effects of the
viewshed, and the availability of water for current and future use.
Other comments were that the proposed project is located in an area of
pediment adjacent to 2 highly mineralized mountain ranges which have
identified molybdenum and lithium deposits.
Maps of the proposed project area and the alternatives being
analyzed in the Draft EIS are available at the BLM Tonopah Field
Office, the Battle Mountain District Office, and at: http://www.blm.gov/nv/st/en/fo/battle_mountain_field.html.
Please note that public comments and information submitted,
including names, street addresses, and e-mail addresses of persons who
submit comments, will be available for public review and disclosure at
the above address during regular business hours (8 a.m. to 4 p.m.),
Monday through Friday, except holidays. Before including your address,
phone number, e-mail address, or other personal identifying information
in your comment, you should be aware that your entire comment--
including your personal identifying information--may be made publicly
available at any time. While you can ask us in your comment to withhold
your personal identifying information from public review, we cannot
guarantee that we will be able to do so.
Authority: 40 CFR 1506.6 and 1506.10.
Thomas J. Seley,
Manager, Tonopah Field Office.
[FR Doc. 2010-21958 Filed 9-2-10; 8:45 am]
BILLING CODE 4310-HC-P