[Federal Register Volume 75, Number 201 (Tuesday, October 19, 2010)]
[Notices]
[Pages 64243-64244]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2010-26223]


========================================================================
Notices
                                                Federal Register
________________________________________________________________________

This section of the FEDERAL REGISTER contains documents other than rules 
or proposed rules that are applicable to the public. Notices of hearings 
and investigations, committee meetings, agency decisions and rulings, 
delegations of authority, filing of petitions and applications and agency 
statements of organization and functions are examples of documents 
appearing in this section.

========================================================================


Federal Register / Vol. 75, No. 201 / Tuesday, October 19, 2010 / 
Notices

[[Page 64243]]



DEPARTMENT OF AGRICULTURE

Forest Service


Umatilla National Forest, Walla Walla Ranger District; Oregon 
Tollgate Fuels Reduction Project

AGENCY: Forest Service, USDA.

ACTION: Notice of Intent to prepare an environmental impact statement.

-----------------------------------------------------------------------

SUMMARY: The Forest Service proposes fuels reduction on approximately 
4,400 acres within the Upper 204/Tollgate Wildland Urban Interface 
(WUI) as set forth in the Umatilla County Community Wildfire Protection 
Plan (CWPP) as amended. This project was planned and will be 
implemented using Healthy Forest Restoration Act (HFRA) of 2004 
authorities.
    The Tollgate Fuels Reduction project is located in Umatilla and 
Union Counties, Oregon and the project planning area encompasses over 
46,000 acres. The project planning area is approximately 40 miles 
south/southwest of Walla Walla, Washington.
    The proposed fuels treatments will seek to reduce standing and down 
fuels, improve area evacuation routes, improve firefighter/public 
safety and protect local infrastructure. Fuel reduction efforts will be 
completed through commercial timber harvest (3,050 acres) and non-
commercial thinning (1,350 acres). Timber harvest would generally focus 
on the removal of small diameter trees; however, larger trees may be 
removed as necessary to meet project objectives. Activities within the 
Lookingglass Inventoried Roadless Area (IRA) would include ground and 
ladder fuel reduction through the removal of standing (live and dead) 
trees and dead and down material. These activities would occur adjacent 
to private property and FR 64. No activities will occur in the North 
Fork Umatilla Wilderness or the Walla Walla River Inventoried Roadless 
Area.
    Development and implementation of these actions will be conducted 
in accordance with the Healthy Forest Restoration Act (HFRA), National 
Forest Management Act (NFMA), National Environmental Policy Act (NEPA), 
the Umatilla National Forest Land and Resource Management Plan and all 
other applicable laws and regulations.

DATES: Comments concerning the scope of the analysis must be received 
by November 18, 2010. The Draft EIS is expected to be filed with the 
Environmental Protection Agency (EPA) and be available to the public 
for review by May 2011. The Final EIS is scheduled to be completed by 
October 2011.

ADDRESSES: Send written comments to Michael Rassbach, District Ranger, 
Walla Walla Ranger District, 1415 W. Rose, Walla Walla, WA. Comments 
may also be sent via e-mail to [email protected]., or via facsimile to 509-522-6000.
    It is important that reviewers provide their comments at such times 
and in such a way that they are useful to the Agency's preparation of 
the EIS. Therefore, comments should be provided prior to the close of 
the comment period and should clearly articulate the reviewer's 
concerns and contentions.
    Comments received in response to this solicitation, including names 
and addresses of those who comment, will become part of the public 
record for this proposed action. Comments submitted anonymously will be 
accepted and considered; however, anonymous comments will not provide 
the respondent with standing to participate in subsequent 
administrative objection process or judicial review.

FOR FURTHER INFORMATION CONTACT: Kimpton Cooper, Environmental 
Coordinator, Walla Walla Ranger District, 1415 W. Rose, Walla Walla, WA 
99362. He can be reached by phone at (509) 522-6290 or by e-mail at 
[email protected].
    Individuals who use telecommunication devices for the deaf (TDD) 
may call the Federal Information Relay Service (FIRS) at 1-800-877-8339 
between 8 a.m. and 8 p.m., Eastern Time, Monday through Friday.

SUPPLEMENTARY INFORMATION: 

Purpose and Need for Action

    The Tollgate planning area is situated on a high plateau between 
the North Fork Umatilla Wilderness and the South Fork Walla Walla 
River. The Tollgate plateau is surrounded on all sides by very steep 
and deep canyons. The plateau area falls primarily into fire regime 4, 
based on species composition, and suggests the occurrence of mixed to 
high severity fire events with long return intervals. Private lands and 
in-holdings are adjacent to, and interspersed with National Forest 
System lands.
    The Tollgate WUI is comprised of approximately 368 residences, 43 
privately owned cabins under NFS special use permit, 4 NFS campgrounds, 
6 trailheads, 1 ski area, 4 snowparks and other FS facilities. The area 
is one of the heaviest used recreation areas on the entire Umatilla NF. 
In addition, there are numerous non-recreation uses of the area. 
Important local and regional infrastructure (fiber optic lines, 
telephone lines, power transmission lines, and communication equipment) 
is interspersed throughout the WUI. Oregon State Highway 204 bisects 
the Tollgate community and provides a major transportation route, 
linking it to Elgin, OR in the south, and Milton-Freewater/Pendleton, 
OR in the north. Highway 204 also provides an important commercial 
shipping route that facilitates the flow of goods and services between 
Union and Umatilla counties.
    Tollgate's geographic positioning, relative to large tracts of 
remote and inaccessible roadless and wilderness areas, makes for a 
uniquely positioned community, and is an important contributing factor 
to the area's overall need for treatment. In many cases, wilderness and 
roadless areas occur at higher elevations and are well removed, from 
communities. Tollgate however sits above large tracts of both roadless 
and wilderness areas. Wildfires can initiate in these remote places, 
gain intensity, and ultimately emerge onto the plateau.
    An accounting of the condition of existing vegetation within the 
analysis area has shown that these stands are very receptive to the 
initiation of high severity crown fire. The stands are also likely to 
sustain high severity crown fire that may emerge from the surrounding 
wilderness and roadless areas. Field reconnaissance of each prospective 
unit

[[Page 64244]]

was performed, and showed that the structure, composition, arrangement, 
and dynamics of the present vegetation indicate an area highly 
susceptible to experiencing severe fire events.
    A strong need for treatment exists. A community, important 
infrastructure and a major transportation corridor represent values 
that are at risk. The area's infrastructure is located above, and in 
the path of major fire travel routes. The community is situated amongst 
vegetation that is poised to burn with severity.
    It is unlikely that high severity fire events can be stopped from 
occurring in fire regime 4; however, through the implementation of 
fuels reduction treatments property, infrastructure, and lives may be 
more effectively protected. Treatments resulting in modified fuel 
configurations in strategic locations can lessen the impacts of a major 
fire event to the people, infrastructure, and travel routes within 
Tollgate.
    The following project objectives were identified based on the 
intent of the 2004 Healthy Forest Restoration Act, the Umatilla County 
CWPP, and goals brought forth through public collaborative efforts:
     Lower fire hazard, by reducing overall fuel load and 
reducing the vertical and horizontal continuity of fuels within the 
project planning area.
     Improve protection to adjacent private lands and public/
private infrastructure from a wildfire event.
     Provide safe egress of local residents and safe ingress/
egress for firefighters during wildfire events.
     Effect immediate change in fire behavior within the 
Tollgate WUI by reducing fuels and creating strategic fuel breaks.

Proposed Action

    The Forest Service proposes to conduct fuels reduction activities 
on approximately 4,400 acres within the Tollgate project planning area. 
Fuel reduction efforts would be implemented through the use of 
commercial timber harvest (3,050 acres) and non-commercial thinning 
(1,350 acres). Fuel reduction prescriptions include crown reduction, 
dead and down material removal, and ladder fuel reduction.
    The project also includes fuel reduction activities in three (3) 
Riparian Habitat Conservation Areas (RHCAs) of strategic importance. 
There are treatments proposed along Oregon State Highway 204, designed 
to improve the defensibility of this important travel corridor. 
Treatments are also proposed within the Lookingglass Inventoried 
Roadless Area (IRA). The proposed treatments are targeted on the edge 
of IRA boundary where it coincides with private inholdings and Forest 
Road 6400. No actions are proposed within either the North Fork 
Umatilla Wilderness or Walla Walla River Inventoried Roadless Area.

Responsible Official

    Walla Walla District Ranger.

Nature of Decision To Be Made

    The responsible official will decide:
    (1) Whether fuels reduction activities should occur, and if so, how 
much, when and where.
    (2) What monitoring and mitigation measures should be taken or are 
needed.

Scoping Process

    This notice of intent initiates the scoping process, which guides 
the development of the environmental impact statement.
    It is important that reviewers provide their comments at such times 
and in such manner that they are useful to the agency's preparation of 
the environmental impact statement. Therefore, comments should be 
provided prior to the close of the comment period and should clearly 
articulate the reviewer's concerns and contentions.
    A public meeting will be held on Thursday, November 4, 2010 at 6 
pm. The meeting will be held at the Tollgate Trailfinders Clubhouse 
located off OR Hwy. 204. The clubhouse is adjacent to the Tollgate 
store and across from the Tamarack Inn. All interested members of the 
public are welcome to attend. For more information about this meeting, 
please contact Kimpton Cooper using the contact information listed 
above.
    It should be noted that HFRA set up a pre-decisional objection 
process. Individual wishing to have standing to participate in the 
objection process must submit written comments either at this time 
(public scoping) or during the comment period for the Draft EIS.

    Dated: October 12, 2010.
Michael Rassbach,
District Ranger.
[FR Doc. 2010-26223 Filed 10-18-10; 8:45 am]