DEPARTMENT OF TRANSPORTATION

Federal Transit Administration


Intent To Prepare an Environmental Impact Statement for the Metro 
Gold Line Foothill Extension, Azusa to Montclair in Los Angeles and San 
Bernardino Counties, CA

AGENCY: Federal Transit Administration, DOT.

ACTION: Notice of Intent to Prepare an Environmental Impact Statement.

-----------------------------------------------------------------------

SUMMARY: The Federal Transit Administration (FTA), as the federal lead 
agency, and the Metro Gold Line Foothill Extension Construction 
Authority (Construction Authority) intend to prepare an Environmental 
Impact Statement (EIS) for proposed transit improvements in the 
Foothill Extension Transit Corridor. FTA is the lead Federal agency 
with the Construction Authority as a co-lead agency for the National 
Environmental Policy Act (NEPA) process because the Construction 
Authority is seeking Federal funding for the proposed project. The 
proposed project is an extension of the existing Metro Gold Line light 
rail transit line, from Azusa to Montclair, with proposed stations in 
Glendora, San Dimas, La Verne, Pomona, Claremont and Montclair. The 
proposed project will improve mobility in eastern Los Angeles County 
and western San Bernardino County by introducing high-frequency transit 
service options; enhance the regional transit network by 
interconnecting existing and planned rail and bus transit lines; 
provide an alternative mode of transportation for commuters who 
currently use the congested I-210 corridor; improve transit 
accessibility for residents and employees who live and/or work along 
the corridor; and encourage a mode shift to transit, reducing air 
pollution and greenhouse gas emissions.
    The EIS will be prepared in accordance with the requirements of 
NEPA and its implementing regulations. Prior to commencement of a Final 
EIS, a locally preferred alternative (LPA) will be identified and 
adopted by the Construction Authority Board and included in the Los 
Angeles County Metropolitan Transportation Authority (LACMTA) 
Constrained Long Range Transportation Plan (LRTP). LACMTA and the 
Construction Authority do not currently anticipate applying for 43 
U.S.C. 5309 New Starts funding.
    The Construction Authority will be preparing a joint EIS/EIR 
document to comply with NEPA and the California Environmental Quality 
Act (CEQA). The purpose of this notice is to alert interested parties 
regarding the intent to prepare the EIS, to provide information on the 
nature of the proposed project and possible alternatives, to invite 
public participation in the EIS process (including providing comments 
on the scope of the Draft EIS), to announce that public scoping 
meetings will be conducted, and to invite participating and cooperating 
agencies.

DATES: Written comments on the scope of the EIS, including the 
project's purpose and need, the alternatives to be considered, the 
impacts to be evaluated, and the methodologies to be used in the 
evaluations should be sent to the Construction Authority on or before 
February 2, 2011 at the address below. See ADDRESSES below for the 
address to which written public comments may be sent. Public scoping 
meetings to accept comments on the scope of the EIS/EIR will be held on 
the following dates:
     Wednesday, January 12, 2011; 6 to 8 p.m. at the Ganesha 
Community Center, 1575 North White Avenue, Pomona, CA.
     Thursday, January 13, 2011; 6 to 8 p.m. at the Glendora 
Teen and Family Center, 241 West Dawson Street, Glendora, CA.
     Wednesday, January 19, 2011; 6 to 8 p.m. at the Oakmont 
Elementary School, 120 West Green Street, Claremont, CA.
     Thursday, January 20, 2011; 6 to 8 p.m. at the Ekstrand 
Elementary School,

[[Page 81329]]

400 North Walnut Avenue, San Dimas, CA.
    The prior planning work, the project's purpose and need, and the 
description of alternatives will be presented at these meetings. The 
buildings used for the scoping meetings are accessible to persons with 
disabilities. Any individual who requires special assistance, such as a 
sign language interpreter, to participate in a scoping meeting should 
contact Ms. Lisa Levy Buch, Director of Public Affairs, Metro Gold Line 
Foothill Extension Construction Authority, at (626) 305-7004, or 
[email protected].
    Scoping materials will be available at the meetings and are 
available on the Construction Authority's Web site (http://www.foothillextension.org). Hard copies of the scoping materials may 
also be obtained from Ms. Sylvia Beltran, Community Outreach 
Coordinator, Metro Gold Line Foothill Extension Construction Authority, 
at (626) 305-7012, or [email protected].
    An interagency scoping meeting will be held on Thursday, January 
13, 2011, at 2 p.m. at the Glendora Teen and Family Center, 241 West 
Dawson Street, Glendora, CA. Representatives of Native American tribal 
governments and of all federal, state, regional and local agencies that 
may have an interest in any aspect of the project will be invited to be 
participating or cooperating agencies, as appropriate and participate 
in the National Historic Preservation Act Section 106 Process.

ADDRESSES: Comments will be accepted at the public scoping meetings or 
they may be sent to Ms. Lisa Levy Buch, Director of Public Affairs, 
Metro Gold Line Foothill Extension Construction Authority, 406 E. 
Huntington Drive, Suite 202, Monrovia, CA 91016-3633, or via e-mail at 
[email protected]. The locations of the public scoping 
meetings are given above under DATES.

FOR FURTHER INFORMATION CONTACT: Mr. Ray Tellis, Team Leader, Los 
Angeles Metropolitan Office, Federal Transit Administration, 888 South 
Figueroa Street, Suite 1850, Los Angeles, CA 90017, phone (213) 202-
3950, e-mail [email protected].

SUPPLEMENTARY INFORMATION:

Background

    A Draft EIS/EIR for Gold Line Phase II Pasadena to Montclair 
Foothill Extension was issued in April 2004 (``2004 DEIS/EIR''). A 
Notice of Availability was published in the Federal Register on May 7, 
2004. Following the release of the 2004 DEIS/EIR, the public comment 
period, and input from the cities along the alignment, the Construction 
Authority Board approved a Locally Preferred Alternative (LPA) in 
August 2004 for the Pasadena to Azusa extension of the Gold Line Phase 
II Project. In March 2005, a Project Definition Report (PDR) was 
prepared to refine the station and parking lot locations, grade 
crossings, two rail grade separations, and traction power substation 
locations. Following the PDR, the Construction Authority Board approved 
a Revised LPA in June 2005. Between March and August 2005, station 
options in Claremont were added.
    Subsequent to circulation of the 2004 DEIS/DEIR the Construction 
Authority decided to fund the Pasadena to Azusa extension of the Gold 
Line Phase II Project without Federal funding and the environmental 
impact assessment for Phase II no longer proceeded as a joint NEPA/CEQA 
document but as a CEQA document. The Pasadena to Azusa Extension 
project of the Gold Line Phase II Pasadena to Montclair Extension was 
certified under CEQA by the Construction Authority and a FEIR was 
completed in February 2007. Because the Construction Authority decided 
to fund the Pasadena to Azusa extension of the Gold Line Phase II 
Project without Federal funding, the FTA subsequently withdrew the Gold 
Line Phase II DEIS on June 25, 2010.
    The Construction Authority will be seeking Federal funding for the 
Metro Gold Line Foothill Extension from Azusa to Montclair and an EIS 
will be prepared. To avoid confusion expressed about the terminology 
used in the 2004 DEIS/EIR (e.g. Phase I; Phase II, Segments 1 and 2), 
the proposed project described by this NOI, which was previously named 
Gold Line Phase II Segment 2, is now referred to as the Metro Gold Line 
Foothill Extension, Azusa to Montclair Project.
    The proposed Metro Gold Line Foothill Extension, Azusa to Montclair 
Project, is included in the strategic unfunded element of the LACMTA 
2009 LRTP. Various transit improvements were explored and opportunities 
identified in other studies such as the Gold Line Phase II Extension 
Pasadena to Claremont Alternatives Analysis, Final Draft Report 
(January 9, 2003), and the Gold Line Phase II Pasadena to Montclair 
Foothill Extension Final Environmental Impact Report (2007) which are 
available for review at the LACMTA Transportation Library, 15th Floor, 
One Gateway Plaza, Los Angeles, CA 90012, the Metro Gold Line Foothill 
Extension Construction Authority, 406 E. Huntington Drive, Suite 202, 
Monrovia, CA 91016-3633, and on the Construction Authority's Web site 
(http://www.foothillextension.org).

Project Initiation and Scoping

    The FTA and the Construction Authority will prepare an EIS/EIR for 
the Metro Gold Line Foothill Extension Azusa to Montclair Project 
pursuant to 23 U.S.C. 139 and CEQA. The Construction Authority is 
serving as the local lead agency for purposes of CEQA. FTA is serving 
as the Federal lead agency and the Construction Authority as a co-lead 
agency for purposes of NEPA. FTA and the Construction Authority will 
invite interested Federal, State, Tribal, regional and local government 
agencies to be participating agencies under the provisions of Title 23 
CFR 771.111.
    Scoping is the process of determining the scope, focus, and content 
of an EIS. FTA and the Construction Authority invite all interested 
individuals and organizations, public agencies, and Native American 
Tribes to comment on the scope of the EIS, including the project's 
purpose and need, the alternatives to be studied, the impacts to be 
evaluated, and the evaluation methods to be used. Comments should focus 
on: (1) Feasible alternatives that may better achieve the project's 
need and purposes with fewer adverse impacts, and (2) any significant 
environmental impacts relating to the alternatives. NEPA ``scoping'' 
has specific and fairly limited objectives, one of which is to identify 
the significant issues associated with alternatives that will be 
examined in detail in the document, while simultaneously limiting 
consideration and development of issues that are not truly significant.

Purpose and Need for the Project

    The purpose of this project is to provide a high-capacity 
transportation improvement that responds to problems associated with 
the I-210, a freeway that is not able to accommodate current and 
forecasted peak-hour travel demands; respond to the limited bus routes 
and commuter rail service available in the study corridor; respond to 
problems associated with the corridor's congested arterial network; 
respond to issues associated with population and employment conditions 
and forecasts; respond to goals of the region and corridor to improve 
air quality and avoid or minimize impacts to natural and manmade 
environments.

[[Page 81330]]

Project Location and Environmental Setting

    The proposed project is located in Los Angeles and San Bernardino 
Counties encompassing six adjoining cities that are located along I-210 
and a railroad right-of-way, between the eastern boundary of Azusa on 
the west and Montclair on the east. The project area includes the 
cities of Glendora, San Dimas, La Verne, Pomona, and Claremont in Los 
Angeles County. In San Bernardino County, it includes the city of 
Montclair.
    The Build Alternative is a Light Rail Transit (LRT) system that 
would begin at the current terminus of the Metro Gold Line at the 
Azusa-Citrus Station continuing east to Montclair.

Alternatives

    The Gold Line Phase II Extension Pasadena to Claremont Alternatives 
Analysis, Final Draft Report (January 9, 2003), prepared for the 
Construction Authority, studied a number of alternatives within the 
study area. This analysis looked at a wide range of alignment and 
technology options aimed at serving the corridor transportation needs. 
These included a No-Build Alternative, a Transportation System 
Management (TSM) Alternative, as well as various modal alternatives. 
The initial analysis looked at enhanced bus service, bus rapid transit, 
LRT, commuter rail, diesel multiple units, high occupancy vehicle 
facilities, and fixed-guideway facilities. The alignment alternatives 
included the existing railroad right-of-way, the I-210 freeway, and 
local major arterials. Operations alternatives varied by mode starting 
with five-minute headways.
    The three alternatives being evaluated include the No Build 
Alternative, TSM, and the Build Alternative. The freight rail alignment 
identified in the Alternatives Analysis Report with the LRT technology 
is the Build Alternative that will be analyzed. In addition, pursuant 
to 40 CFR 1502.14, the EIS will analyze any reasonable alternatives 
identified during scoping.
    No-Build Alternative: The No-Build Alternative includes all highway 
and transit projects and operations that the region and LACMTA expect 
to be in place in 2035. The No-Build Alternative would not require 
construction of ancillary facilities other than those included in the 
projects comprising the alternative. The No-Build Alternative is 
LACMTA's 2009 LRTP adopted in October 2009. This 2009 LRTP includes a 
balance of vehicle and transit improvements, including an expanded bus 
and rail network. Projects within the 2009 LRTP that are relevant to 
the corridor are stated below.
     Transit projects include countywide (Los Angeles and San 
Bernardino Counties) bus service improvements; commuter rail 
(Metrolink) improvements; and light rail and heavy rail transit 
improvements.
     Freeway improvements include projects on freeways such as 
the extension of freeway Route 30/I-210 from Foothill Boulevard to I-15 
(now completed) and the continuing extension of I-15 to I-215 in the 
future.
     Smart street projects include improvements such as 
synchronized traffic signals, on-street parking removal, frontage road 
and grade separation construction, and key intersection improvements to 
improve traffic flow.
     Arterial improvement projects include improvements to 
existing roadways.
    Transportation System Management (TSM) Alternative: The EIS/EIR 
will evaluate transportation and environmental effects of modest 
improvements in the highway and transit systems beyond those in the No-
Build Alternative. The TSM Alternative would include low-cost 
improvements to the No-Build Alternative to reduce delay and enhance 
mobility. The TSM Alternative would emphasize transportation system 
upgrades, such as intersection improvements, minor road widening, 
traffic engineering actions, bus route restructuring, shortened bus 
headways, expanded use of articulated buses, reserved bus lanes, 
expanded park-and-ride facilities, express and limited-stop service, 
signalization improvements, and timed-transfer operations.
    Build Alternative: The Build Alternative utilizes the existing 
LACMTA/Construction Authority and San Bernardino Associated Governments 
rights of way through the San Gabriel Valley for LRT service. The Build 
Alternative would extend the Metro Gold Line LRT system from the 
eastern boundary of Azusa to the Montclair TransCenter (approximately 
11.4 miles) located in Montclair, bordering the city of Upland. The 
same LRT technology and the same types of system components would be 
used as the existing Metro Gold Line. The Build Alternative would 
include six new stations, with one in each of the cities along the 
corridor; Glendora, San Dimas, La Verne, Pomona, Claremont and 
Montclair. Potential station locations have been defined in 
consultation with the corridor cities. Parking facilities would be 
provided at each new station.
    Eight traction power substations (TPSSs) would be constructed along 
the route in order to provide electrical power to the line. Where 
possible, TPSS sites would be located near a station. TPSS sites would 
be located within existing rail right of way or within properties to be 
acquired for stations or parking. The Build Alternative would include 
two LRT tracks throughout, and one freight track between the eastern 
boundary of Azusa and Pomona. In Pomona, the single freight track would 
then join up with the double Metrolink tracks and continue through to 
Montclair and beyond.

Probable Effects

    The purpose of this EIS process is to study, in a public setting, 
the effects of the proposed project and its alternatives on the 
physical, human, and natural environment. The FTA and the Construction 
Authority will evaluate all significant environmental, social, and 
economic impacts of the construction and operation of the proposed 
project. The probable impacts will be determined as part of the project 
scoping. Unless further screening illuminates areas of possible impact, 
resource areas will be limited to those identified during scoping. 
Measures to avoid, minimize, and mitigate adverse impacts will also be 
identified and evaluated.

FTA Procedures

    The regulations implementing NEPA, as well as provisions of the 
Safe, Accountable, Flexible, Efficient Transportation Equity Act: A 
Legacy for Users (SAFETEA-LU), calls for public involvement in the EIS 
process. Section 6002 of SAFETEA-LU requires that FTA and the 
Construction Authority do the following: (1) Extend an invitation to 
other Federal and non-Federal agencies and Native American tribes that 
may have an interest in the proposed project to become ``participating 
agencies;'' (2) provide an opportunity for involvement by participating 
agencies and the public to help define the purpose and need for a 
proposed project, as well as the range of alternatives for 
consideration in the EIS; and (3) establish a plan for coordinating 
public and agency participation in, and comment on, the environmental 
review process. An invitation to become a participating or cooperating 
agency, with scoping materials appended, will be extended to other 
Federal and non-Federal agencies and Native American tribes that may 
have an interest in the proposed project. It is possible that FTA and 
the Construction Authority will not be able to identify all Federal and 
non-Federal

[[Page 81331]]

agencies and Native American tribes that may have such an interest. Any 
Federal or non-Federal agency or Native American tribe interested in 
the proposed project that does not receive an invitation to become a 
participating agency should notify at the earliest opportunity the 
Community Outreach Coordinator identified above under ADDRESSES.
    The EIS will be prepared in accordance with NEPA and its 
implementing regulations issued by the Council on Environmental Quality 
(40 CFR parts 1500-1508) and with the FTA/Federal Highway 
Administration regulations ``Environmental Impact and Related 
Procedures'' (23 CFR part 771). Related environmental procedures to be 
addressed during the NEPA process, include, but are not limited to the 
project-level air quality conformity regulation of the U.S. 
Environmental Protection Agency (EPA) (40 CFR part 93); the regulation 
implementing Section 106 of the National Historic Preservation Act (36 
CFR part 800); Section 4(f) of the Department of Transportation Act (23 
CFR part 774); and Executive Order 12898 on environmental justice.

    Issued on: December 17, 2010.
Leslie T. Rogers,
Regional Administrator, Region IX, Federal Transit Administration.
[FR Doc. 2010-32337 Filed 12-23-10; 8:45 am]
BILLING CODE 4910-57-P