[Federal Register: January 20, 2010 (Volume 75, Number 12)]
[Rules and Regulations]
[Page 3178-3179]
From the Federal Register Online via GPO Access [wais.access.gpo.gov]
[DOCID:fr20ja10-17]
=======================================================================
-----------------------------------------------------------------------
DEPARTMENT OF DEFENSE
Defense Acquisition Regulations System
48 CFR Parts 209, 237 and 252
[DFARS Case 2006-D051]
RIN 0750-AF80
Defense Federal Acquisition Regulation Supplement; Lead System
Integrators
AGENCY: Department of Defense (DoD).
ACTION: Final rule.
-----------------------------------------------------------------------
SUMMARY: DoD has adopted as final, without change, an interim rule
amending the Defense Federal Acquisition Regulation Supplement (DFARS)
to implement Section 802 of the National Defense Authorization Act for
Fiscal Year 2008. Section 802 places limitations on the award of new
contracts for lead system integrator functions in the acquisition of
major DoD systems.
DATES: Effective Date: January 20, 2010.
FOR FURTHER INFORMATION CONTACT: Ms. Meredith Murphy, Defense
Acquisition Regulations System, OUSD(AT&L)DPAP(DARS), IMD 3D139, 3062
Defense Pentagon, Washington, DC 20301-3062. Telephone 703-602-1302;
facsimile 703-602-0350, Please cite DFARS Case 2006-D051.
SUPPLEMENTARY INFORMATION:
A. Background
DoD published an interim rule at 73 FR 1823 on January 10, 2008, to
implement Section 807 of the National
[[Page 3179]]
Defense Authorization Act for Fiscal Year 2007 (Pub. L. 109-364) with
regard to limitations on the performance of lead system integrator
functions by DoD contractors. On January 28, 2008, Section 802 of the
National Defense Authorization Act for Fiscal Year 2008 (Pub. L. 110-
181) placed additional limitations on DoD's use of lead system
integrators. A second interim rule was published on July 15, 2009,
amending the first interim rule. One comment was received after the
comment period closed. The comment concerned the definitions of lead
system integrator with system responsibility and lead system integrator
without system responsibility. The comment was addressed in the interim
rule published on July 15, 2009.
This rule was not subject to Office of Management and Budget review
under Executive Order 12866, dated September 30, 1993.
B. Regulatory Flexibility Act
DoD certifies that this final rule will not have a significant
economic impact on a substantial number of small entities within the
meaning of the Regulatory Flexibility Act, 5 U.S.C. 601, et seq.,
because application of the rule is limited to contractors performing
lead system integrator functions for major DoD systems.
C. Paperwork Reduction Act
The Paperwork Reduction Act does not apply because the proposed
changes do not impose information collection requirements that require
the approval of the Office of Management and Budget under 44 U.S.C.
3501, et seq.
List of Subjects in 48 CFR Parts 209, 237 and 252
Government procurement.
Amy G. Williams,
Editor, Defense Acquisition Regulations System.
0
Accordingly, the interim rule amending 48 CFR Parts 209, 237, and 252,
which was published at 74 FR 34268 on July 15, 2009, is adopted as a
final rule without change.
[FR Doc. 2010-888 Filed 1-19-10; 8:45 am]