DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 13952-000]


Claverack Creek, LLC; Notice of Preliminary Permit Application 
Accepted for Filing and Soliciting Comments, Motions To Intervene, and 
Competing Applications

    On December 31, 2010, Claverack Creek, LLC filed an application for 
a preliminary permit, pursuant to section 4(f) of the Federal Power Act 
(FPA), proposing to study the feasibility of the Claverack Creek 
Hydroelectric Project to be located on Claverack Creek, in Columbia 
County, New York. The sole purpose of a preliminary permit, if issued, 
is to grant the permit holder priority to file a license application 
during the permit term. A preliminary permit does not authorize the 
permit holder to perform any land-disturbing activities or otherwise 
enter upon lands or waters owned by others without the owners' express 
permission.
    The proposed project would consist of: (1) The existing 16-foot-
high, 170-foot-long Stottville Mill Dam; (2) an existing 11.4-acre 
impoundment with a normal water surface elevation of 106.0 feet mean 
sea level; (3) an existing turbine with a new generator and a new 
turbine-generator with a total capacity of 450 kilowatts; (4) an 
existing 10-foot-wide, 8-foot-deep intake canal; (5) new trash racks, 
head gates, and stop log structure; (6) an existing 6-foot-diameter, 
10-foot-long penstock and a new 10-foot-long penstock extension; (7) a 
new 40-foot-wide, 60-foot-long powerhouse; (8) an existing 10-foot-
wide, 20-foot-long tailrace; (9) a new approximately 200-foot-long, 
13.2-kilovolt transmission line from the powerhouse to a nearby 
distribution line; (10) a redeveloped 100-foot-long access road; (11) 
and appurtenant facilities. The project would have an estimated annual 
generation of 2,182 megawatt-hours.
    Applicant Contact: Mr. William D. B. Fay, Claverack Creek, LLC, 189 
River Road, Ware, MA 01082; phone: (413) 244-6445.
    FERC Contact: Timothy Looney; phone: (202) 502-6096.
    Deadline for filing comments, motions to intervene, competing 
applications (without notices of intent), or notices of intent to file 
competing applications: 60 days from the issuance of this notice. 
Competing applications and notices of intent must meet the requirements 
of 18 CFR 4.36. Comments, motions to intervene, notices of intent, and

[[Page 7839]]

competing applications may be filed electronically via the Internet. 
See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission's 
Web site http://www.ferc.gov/docs-filing/efiling.asp. Commenters can 
submit brief comments up to 6,000 characters, without prior 
registration, using the eComment system at http://www.ferc.gov/docs-filing/ecomment.asp. You must include your name and contact information 
at the end of your comments. For assistance, please contact FERC Online 
Support at [email protected] or toll free at 1-866-208-3676, 
or for TTY, (202) 502-8659. Although the Commission strongly encourages 
electronic filing, documents may also be paper-filed. To paper-file, 
mail an original and seven copies to: Kimberly D. Bose, Secretary, 
Federal Energy Regulatory Commission, 888 First Street, NE., 
Washington, DC 20426.
    More information about this project, including a copy of the 
application, can be viewed or printed on the ``eLibrary'' link of the 
Commission's Web site at http://www.ferc.gov/docs-filing/elibrary.asp. 
Enter the docket number (P-13952-000) in the docket number field to 
access the document. For assistance, contact FERC Online Support.

    Dated: February 4, 2011.
Kimberly D. Bose,
Secretary.