[Federal Register Volume 76, Number 48 (Friday, March 11, 2011)]
[Notices]
[Page 13344]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2011-5476]


-----------------------------------------------------------------------

DEPARTMENT OF AGRICULTURE

Forest Service


Beaver Creek Landscape Management Project, Ashland Ranger 
District, Custer National Forest; Powder River County, MT

AGENCY: Forest Service, USDA.

ACTION: Notice of change of responsible official.

-----------------------------------------------------------------------

SUMMARY: On April 2, 2010 the Forest Service announced its notice of 
intent (NOT) to prepare an Environmental Impact Statement for the 
Beaver Creek Landscape Management Project in the Federal Register (75 
FR 16728). The notice of availability (NOA) of the Draft Environmental 
Impact Statement for the Beaver Creek Landscape Management Project was 
published in the Federal Register on October 15, 2010 (75 FR 63470, EIS 
No. 20100405, Draft EIS, USFS, MT).

Responsible Official

    In the NOI the Forest Supervisor, Mary Erickson, was identified as 
the Responsible Official. Pursuant to Forest Service Manual (FSM) 
2404.13 the District Ranger has the authority to be the Responsible 
Official for this project. Therefore, this is notice that Ashland 
District Ranger, Walt Allen, is the Responsible Official for the Beaver 
Creek Landscape Management Project.

DATES: The Final Environmental Impact Statement is planned to be 
released in April 2011.

ADDRESSES: No comments are being sought at this time. However, Walt 
Allen can be contacted at the Ashland Ranger District, P.O. Box 168, 
Ashland, MT 59003 or by phone at 406-784-2344.

FOR FURTHER INFORMATION CONTACT: Amy Waring, Project Coordinator, at 
(406) 657-6205 extension 210.

    Dated: March 4, 2011.
Chris Worth,
Deputy Forest Supervisor.
[FR Doc. 2011-5476 Filed 3-10-11; 8:45 am]
BILLING CODE 3410-11-M