                            TITLE 10--ENERGY
 
               CHAPTER II--DEPARTMENT OF ENERGY--CONTINUED
 
PART 600--FINANCIAL ASSISTANCE RULES--Table of Contents
 
     Subpart B--Uniform Administrative Requirements for Grants and 
Cooperative Agreements With Institutions of Higher Education, Hospitals, 
       Other Non-Profit Organizations and Commercial Organizations
 
Sec. 600.125  Revision of budget and program plans.

    (a) The budget plan is the financial expression of the project or 
program as approved during the award process. It includes the sum of the 
Federal and non-Federal share when there are cost sharing requirements. 
It shall be related to performance for program evaluation purposes 
whenever appropriate.
    (b) Recipients are required to report deviations from budget and 
program plans, and request prior approvals for budget and program plan 
revisions, in accordance with this section.
    (c) For nonconstruction awards, recipients shall request prior 
approvals from the DOE for one or more of the following program or 
budget related reasons.
    (1) Change in the scope or the objective of the project or program 
(even if there is no associated budget revision requiring prior written 
approval).
    (2) Change in a key person specified in the application or award 
document.
    (3) The absence for more than three months, or a 25 percent 
reduction in time devoted to the project, by the approved project 
director or principal investigator.
    (4) The need for additional Federal funding.
    (5) If required by program regulations, the transfer of amounts 
budgeted for indirect costs to absorb increases in direct costs, or vice 
versa.
    (6) The inclusion, unless waived by program regulations or the terms 
and conditions of award, of costs that require prior approval in 
accordance with OMB Circular A-21, ``Cost Principles for Institutions of 
Higher Education,'' OMB Circular A-122, ``Cost Principles for Non-Profit 
Organizations,'' or 45 CFR part 74 Appendix E, ``Principles for 
Determining Costs Applicable to Research and Development under Grants 
and Contracts with Hospitals,'' or 48 CFR part 31, ``Contract Cost 
Principles and Procedures,'' as applicable.
    (7) The transfer of funds allotted for training allowances (direct 
payment to trainees) to other categories of expense.
    (8) Unless described in the application and funded in the approved 
awards, the subaward, transfer or contracting out of any work under an

[[Page 110]]

award. This provision does not apply to the purchase of supplies, 
material, equipment or general support services.
    (d) No other prior approval requirements for specific items may be 
imposed unless a deviation has been approved in accordance with 
Sec. 600.4.
    (e) Except for requirements listed in paragraphs (c)(1) and (c)(4) 
of this section, program regulations may waive cost-related and 
administrative prior written approvals required by this subpart and its 
Appendices. Such waivers may include authorizing recipients to do any 
one or more of the following.
    (1) Incur pre-award costs 90 calendar days prior to award without 
prior approval or more than 90 calendar days with the prior approval of 
DOE. All pre-award costs are incurred at the recipient's risk (i.e., DOE 
is under no obligation to reimburse such costs if for any reason the 
recipient does not receive an award or if the award is less than 
anticipated and inadequate to cover such costs).
    (2) Initiate a one-time extension of the expiration date of the 
final budget period of the project of up to 12 months unless one or more 
of the following conditions apply.
    (i) The terms and conditions of award prohibit the extension.
    (ii) The extension requires additional Federal funds.
    (iii) The extension involves any change in the approved objectives 
or scope of the project.
    (iv) The extension is being exercised merely for the purpose of 
using unobligated balances. For one-time extensions, the recipient must 
notify the DOE in writing with the supporting reasons and revised 
expiration date at least 10 days before the expiration date specified in 
the award.
    (3) Carry forward unobligated balances to subsequent funding 
periods.
    (4) For awards that support research, unless the terms and 
conditions of award provide otherwise, the prior approval requirements 
described in paragraph (e) of this section are automatically waived 
(i.e., recipients need not obtain such prior approvals) unless one of 
the conditions included in Sec. 600.125(e)(2) applies.
    (5) For continuation awards within a multiple year project in 
support of research, prior to receipt of continuation funding, preaward 
expenditures by recipients are not subject to the limitation or approval 
requirements of Sec. 600.125(e)(1). Nevertheless, incurrence by the 
recipient does not impose any obligation on DOE if a continuation award 
is not subsequently made, or if an award is made for a lesser amount 
than the recipient expected.
    (f) Program regulations may restrict the transfer of funds among 
direct cost categories or programs, functions and activities for awards 
in which DOE's share of the project exceeds $100,000 and the cumulative 
amount of such transfers exceeds or is expected to exceed 10 percent of 
the total budget as last approved by DOE. However, no program regulation 
shall permit a transfer that would cause any Federal appropriation or 
part thereof to be used for purposes other than those consistent with 
the original intent of the appropriation.
    (g) All other changes to nonconstruction budgets, except for the 
changes described in paragraph (j) of this section, do not require prior 
approval.
    (h) For construction awards, recipients shall request prior written 
approval promptly from the Contracting Officer for budget revisions 
whenever paragraph (h) (1), (2) or (3) of this section apply.
    (1) The revision results from changes in the scope or the objective 
of the project or program.
    (2) The need arises for additional Federal funds to complete the 
project.
    (3) A revision is desired which involves specific costs for which 
prior written approval requirements may be imposed consistent with 
applicable OMB cost principles listed in Sec. 600.127.
    (i) Except in accordance with the deviation procedures in 600.4 or 
as may be provided for in program regulations, no other prior approval 
requirements for specific items will be imposed by DOE.
    (j) When DOE makes an award that provides support for both 
construction and nonconstruction work, DOE may require the recipient to 
request prior approval from DOE before making any fund or budget 
transfers between the two types of work supported.
    (k) For both construction and nonconstruction awards, recipients 
shall

[[Page 111]]

notify DOE in writing promptly whenever the amount of Federal authorized 
funds is expected to exceed the needs of the recipient for the project 
period by more than $5000 or five percent of the Federal award, 
whichever is greater. This notification shall not be required if an 
application for additional funding is submitted for a continuation 
award.
    (l) Requests for budget revisions may be made by letter.
    (m) Within 30 calendar days from the date of receipt of the request 
for budget revisions, DOE shall review the request and notify the 
recipient whether the budget revisions have been approved. If the 
revision is still under consideration at the end of 30 calendar days, 
DOE shall inform the recipient in writing of the date when the recipient 
may expect the decision.
    (n) DOE approval or disapproval of a request for a budget or project 
revision shall be in writing and signed by a DOE Contracting Officer.
    (o) A request by a subrecipient for prior approval shall be 
addressed in writing to the recipient. The recipient shall promptly 
review such request and shall approve or disapprove the request in 
writing within 30 days from the date of the recipient's request for the 
revision. A recipient shall not approve any budget or project revision 
which is inconsistent with the purpose or terms and conditions of the 
DOE award. If the revision requested by the subrecipient would result in 
a change to the recipient's approved budget or approved project which 
requires DOE prior approval, the recipient shall obtain DOE approval 
before approving such revision.