Sec. 1260.11  Evaluation and selection.

    (a) Technical evaluation of proposals will be conducted by the 
cognizant NASA technical office and may be based on peer reviews.
    (b) Under NRA's, AO's, other BAA's, and CAN's, the selecting 
official will furnish documentation requested by the grant officer, 
(including a copy of the NRA, selection statement, and peer review 
evaluation if requested), to confirm that the award is being made as a 
result of a selection under a NRA, AO, other BAA, or CAN. The technical 
office will forward to the grant office a completed award package, 
including a funded procurement request, technical evaluation of the 
proposed budget, and other support documentation, at least 29 days prior 
to the requested award date, or before the expiration of the funded 
period in the case of the renewal of an existing effort.
    (c) If a proposal is not selected, the proposer will be notified by 
the selecting official in accordance with the procedures set forth in 
the NRA, AO, CAN, or BAA.
    (d) Unsolicited proposals will be evaluated in accordance with the 
following procedure:
    (1) Evaluations of unsolicited proposals to be awarded as grants or 
cooperative agreements will be conducted using the same criteria used 
for reviewing unsolicited proposals to be awarded as contracts, as set 
forth at FAR subpart 15.6 and (NFS) 48 CFR subpart 1815.6. Normally, 
unsolicited proposals are accepted to perform discrete projects with 
defined anticipated outcomes and completion dates. An unsolicited 
proposal that results in a grant or cooperative agreement with no 
defined end date, and which requires subsequent submission of follow-on 
unsolicited proposals to ensure continuation of the effort, should be 
closely reviewed to ensure that it meets the FAR definition for a valid 
unsolicited proposal.
    (2) An unsolicited proposal recommended for acceptance shall be 
supported by a Justification for Acceptance of an Unsolicited Proposal 
(JAUP) prepared by the cognizant technical office. The JAUP shall be 
submitted for the approval of the grant officer after review and 
concurrence at a level above the technical officer. However,

[[Page 273]]

this review and concurrence is not required for technical officers at a 
division chief or higher level. The grant officer's signature on the 
award document will indicate approval of the JAUP.
    (3) NASA will notify in writing organizations that submit 
unsolicited proposals that will not be funded. Method of notification is 
at the discretion of the grant officer. Proposals will be returned only 
when requested. Agency procedures for handling unsolicited proposals are 
specified at (NFS) 48 CFR 1815.606.
    (e) For awards made non-competitively, written justifications for 
equipment or travel will be submitted by the technical office for grant 
officer approval when more than half of the proposed budget is for 
equipment or travel and associated indirect cost. The justification 
shall describe the extent to which the equipment or travel is necessary. 
The grant officer's signature on the award will indicate approval of the 
justification.
    (f) The evaluation of the proposal budget will conform to the 
following procedure:
    (1) The technical officer will review the proposer's estimated cost 
for conformance to program requirements and fund availability. The 
results of this review shall be recorded in Column B of the proposed 
Budget Summary Form (Exhibit A to subpart A of this part 1260, available 
at the address given in Exhibit A). New budgets are not required when 
the program office recommended funding is within twenty percent (20 
percent) of the proposed amount, provided that, if requested by the 
proposer, a revised scope of work based on the recommended funding is 
submitted by the proposer for acceptance by the technical officer. 
However, when funding decreases in equipment and/or subcontracts are 
involved, the cognizant program office is required to identify the cost 
element(s) affected by the change in funding level.
    (2) The grant officer will review the budget, and any changes made 
by the technical officer, to identify any item which may be unallowable 
under the cost principles, or which appears unreasonable or unnecessary. 
The grant officer will complete Column C of the Budget Summary after 
discussing significant changes with the recipient and/or technical 
office. Requests for details from the recipient should be limited.
    (3) The grant officer will address requests for direct charge of 
equipment in the negotiation summary, and state whether the purchase is 
approved as a direct cost.
    (g) 42 U.S.C. 2459d prohibits NASA from funding any grant for longer 
than one year if the effect is to provide a guaranteed customer base for 
new commercial space hardware or services. The only exception would be 
if an Appropriations Act specifies the new commercial space hardware or 
services to be used.
    (h) NASA reserves the right to either fully fund or incrementally 
fund grants based on fiscal law and program considerations. Grants with 
anticipated annual funding exceeding $50,000 may be funded for less than 
the amount stated in the proposal.
    (1) The grant officer will determine the number of incremental 
funding actions that will be allowed.
    (2) The special condition at Sec. 1260.53, Incremental Funding, will 
be included in the grant.
    (i) Proposals for efforts that involve printing, binding, and 
duplicating in excess of 25,000 pages are subject to the Government 
Printing and Binding Regulations, No. 26, February 1990, S. Pub. 101-9, 
U.S. Government Printing Office, Washington, DC 20402, published by the 
Congressional Joint Committee on Printing. The technical office will 
refer such proposals to the Installation Central Printing Management 
Officer (ICPMO). The grant officer will be advised in writing of the 
results of the ICPMO review.
    (j) The provision at Sec. 1260.30, Rights in Data, is to be inserted 
as a standard provision into grants and cooperative agreements that 
don't require cost sharing. Additional language is required for cost 
sharing and/or matching efforts, and in cooperative agreements, as set 
forth in the provision.
    (k) By acceptance of a grant (containing the provision at 
Sec. 1260.34) the recipient agrees that it is in compliance with the 
Clean Air and Federal

[[Page 274]]

Water Pollution Control Acts. The Administrator may approve exemptions 
from this prohibition under certain circumstances under Executive Order 
11738. Requests for exemptions or renewals thereof shall be made to the 
Office of Procurement, NASA Headquarters, Program Operations Division 
(Code HS), Washington, DC 20546.
    (l) Requests for acquisition of property may be made by a recipient 
either as part of the original budget proposal or subsequent to award. 
Comprehensive guidance on evaluating requests for acquisition of 
property, vesting of title, and administration issues, is set forth at 
Sec. 1260.74.