Sec. 250.150  How do I name facilities and wells in the Gulf of Mexico Region?

    (a) Assign each facility a letter designation except for those types 
of facilities identified in paragraph (c)(1) of this section. For 
example, A, B, CA, or CB.
    (1) After a facility is installed, rename each predrilled well that 
was assigned only a number and was suspended temporarily at the mudline 
or at the surface. Use a letter and number designation. The letter used 
must be the same as that of the production facility, and the number used 
must correspond to the order in which the well was completed, not 
necessarily the number assigned when it was drilled. For example, the 
first well completed for production on Facility A would be renamed Well 
A-1, the second would be Well A-2, and so on; and

[[Page 257]]

    (2) When you have more than one facility on a block, each facility 
installed, and not bridge-connected to another facility, must be named 
using a different letter in sequential order. For example, EC 222A, EC 
222B, EC 222C.
    (3) When you have more than one facility on multiple blocks in a 
local area being co-developed, each facility installed and not connected 
with a walkway to another facility should be named using a different 
letter in sequential order with the block number corresponding to the 
block on which the platform is located. For example, EC 221A, EC 222B 
and EC 223C.
    (b) In naming multiple well caissons, you must assign a letter 
designation.
    (c) In naming single well caissons, you must use certain criteria as 
follows:
    (1) For single well caissons not attached to a facility with a 
walkway, use the well designation. For example, Well No. 1;
    (2) For single well caissons attached to a facility with a walkway, 
use the same designation as the facility. For example, rename Well No.10 
as A-10; and
    (3) For single well caissons with production equipment, use a letter 
designation for the facility name and a letter plus number designation 
for the well. For example, the Well No. 1 caisson would be designated as 
Facility A, and the well would be Well A-1.