[Code of Federal Regulations]
[Title 33, Volume 3]
[Revised as of July 1, 2001]
From the U.S. Government Printing Office via GPO Access
[CITE: 33CFR263.15]

[Page 340-343]
 
                TITLE 33--NAVIGATION AND NAVIGABLE WATERS
 
         CHAPTER II--CORPS OF ENGINEERS, DEPARTMENT OF THE ARMY
 
PART 263--CONTINUING AUTHORITIES PROGRAMS--Table of Contents
 
                           Subpart A--General
 
Sec. 263.15  Program policies.

    (a) Designation of authority. One of the referenced legislative 
authorities must be designated as the primary purpose of the project for 
allocation of Program funds and for determining legislative funding 
limitations. However, other authorized project purposes are not 
precluded to meet related needs as determined appropriate by the Chief 
of Engineers. The cost limitation of Corps participation for the 
designated authority will prevail regardless of the number of project 
purposes served. Normally, only one authority will be used for each 
study accomplished and each project recommended. Certain authorizations 
specify individual project allotment ceilings ``from the appropriations 
for any one fiscal year.'' It is the intent of Congress that such 
specified amount be the maximum limit for Corps of Engineers 
expenditures at each location or individual project undertaken, without 
regard to time.
    (b) Applicability of costs to Federal and non-Federal shares. Unless 
otherwise specified in a legislative authority (Sec. 263.13), cost 
sharing policies applicable to Congressionally authorized projects are 
applicable to projects recommended under this Program. Any

[[Page 341]]

legislative limitation on Corps participation in project costs, however, 
takes precedence over the apportionment of costs resulting from 
established cost sharing policies.
    (1) Project first costs. Project first costs include all Corps of 
Engineers costs for investigations, design, and construction (including 
costs of supervision and administration) incurred subsequent to the 
Division Engineer's transmittal of a Detailed Project Report or Recon 
Report to OCE for approval. These costs are normally those related to 
preparation of plans and specifications and project construction.
    (2) Federal cost limitation. All Corps of Engineers costs of 
investigations, planning, design and construction, to include those 
incurred prior to transmittal of the DPR or Recon Report to OCE for 
approval are to be included within the cost limitation established by 
Congress for a particular Program authority. Expenditures of other 
Federal agencies under their own authorities are not to be included 
within this cost limitation.
    (3) Costs for economic analysis. Costs to be considered as a part of 
the economic analysis (i.e., determination of a benefit-cost ratio), are 
the same as those considered in feasibility reports transmitted to 
Congress for authorization. In this regard, all costs incurred prior to 
the Division Engineer's transmittal of the Detailed Project or Recon 
Report to OCE for approval are considered ``preauthorization study 
costs'' and are excluded from the economic analysis.
    (4) Use of Federal funds to satisfy local cooperation requirements. 
Where the law requires that lands, easements and rights-of-way be 
furnished by local interests ``without cost to the United States'', 
direct contributions of other Federal agencies may not be accepted by 
local interests to satisfy such local cooperation requirements once 
local interests have furnished a letter of intent (see 
Sec. 263.17(e)(5)) to the reporting officer.
    (5) Non-Federal costs. Local interests must agree to assume 
responsibility for designated items of local cooperation and for all 
project costs in excess of the specified Corps cost limitation, or as 
otherwise apportioned, to insure that expenditure of Corps funds will 
result in a project that is integrally complete and fully effective. If 
the project cost exceeds the Corps cost limit, the difference is 
provided by local cash contributions. Local participation requirements 
will not be reduced, offset, or otherwise credited for local 
expenditures prior to the approval of a project by the Chief of 
Engineers. The scope of the project may be increased, including the 
addition of project purposes, if local interests are willing to pay the 
additional costs.
    (c) The planning process. Planning will be conducted generally in 
accordance with the 1105-2-200 series of planning regulations, adapted 
to this Program, as discussed in paragraphs (c)(1) through (c)(3) of 
this section and in Appendix B.
    (1) Stage 1--Reconnaissance. The reporting officer is delegated the 
authority to conduct a Reconnaissance (Recon) upon the request of a non-
Federal governmental entity or official, to determine if a detailed 
feasibility study is warranted. Charges not to exceed $5,000 may be made 
against the District revolving fund. The results of the Recon will be 
reported to the Division Engineer in a brief letter report; the Division 
Engineer will require of a reporting officer only information considered 
essential for approval of proceeding with the feasibility study, as 
provided in paragraph (e)(2) of this section.
    (2) Stage 2--Feasibility study (Plan formulation). The Division 
Engineer is delegated the authority to authorize the reporting officer 
to conduct a feasibility study, subject to availability of funds from 
OCE.
    (i) The criteria for Division Engineer approval for initiating a 
feasibility study are: there is a Federal interest in the problem 
identified in the Recon, there exists solutions for which Federal 
participation may be justified under one of the Program authorities, 
there are existing non-Federal entities which are legally and 
financially capable of satisfying the typical local cooperation 
requirements for such solutions, and a feasibility study can be 
accomplished at a reasonable cost compared to the prospective benefits 
from

[[Page 342]]

solving the problems identified in the Recon.
    (ii) Where a significant question arises concerning the Federal 
interest in a problem, the applicability of one of the Program 
authorities, or other policy matters, the case should be referred to 
DAEN-CWP or DAEN-CWO prior to authorization of a feasibility study.
    (iii) The feasibility study should complete the plan formulation 
process, including the selection of a plan. The study should be 
terminated if any of the above criteria are not satisfied, if there is a 
lack of public support, or in the case of obtaining local assurances, 
that a reasonable length of time (as determined by the reporting 
officer) has passed without satisfactory assurances from local 
interests. (See also (Sec. 263.17(e)(5)).
    (3) Stage 3--Development of Recommended Plan. This stage corresponds 
to Phase II AE&D for projects specifically authorized by Congress. 
Authority to continue the planning process from plan formulation to 
development of a recommended plan is delegated to the reporting officer, 
unless otherwise provided by implementing instructions issued by the 
Division Engineer, in accordance with Division responsibilities for 
intensive management of the program (Sec. 263.16(b)).
    (d) Review of planning reports. The primary responsibility for 
review of all aspects of Recon reports and DPR's rests with the Division 
Engineer. Division Engineers (with the exception of New England and 
Pacific Ocean) are delegated the authority to approve the plan 
formulation aspects of the study and the engineering design of 
recommended plans, in order that the reporting officer may proceed with 
work on plans and specifications pending formal approval of the project 
by the Chief of Engineers. Review of DPRs and Recon reports by OCE will 
be limited to conformance of recommended plans to existing policy.
    (e) Public involvement. General policy and guidance on public 
involvement is contained in ER 1105-2-800. Requirements for public 
meetings are discussed further in Sec. 263.17(e)(1). There is 
essentially no difference in the Corps' objectives for involving and 
informing the public for studies and projects in this Program than for 
projects planned and constructed under specific Congressional authority. 
Since plans formulated under this Program are usually smaller in scope 
than those specifically authorized by Congress, planners should be able 
to more readily identify the affected and interested public early in the 
planning process and initiate a public involvement program that can be 
continued through plan implementation.
    (f) State and agency coordination. Reporting officers should 
generally follow the same procedures for agency coordination as in the 
case of a Congressionally authorized study. Coordination with A-95 
clearinghouses is discussed in ER 1105-2-811.
    (1) Section 205, 107, 103, 111 and 208 Authorities. The views of 
Governors of affected States, or their designated representatives, and 
regional offices of appropriate Federal agencies must accompany the DPR 
when submitted to OCE for approval. Division Engineers shall insure that 
coordination letters are current and have been adequately considered in 
the plan formulation and review process. Letters obtained by reporting 
officers from the coordination of draft or final reports are to be 
considered current only if the dates on such letters are no more than 
360 days prior to the date of submittal of the DPR to OCE, and if no 
significant changes have been made to the DPR which should be reviewed 
by the originators of such letters. Reporting officers will normally 
accomplish any required recoordination of reports to meet the above 
criteria. Division Engineers may elect, however, to obtain the views of 
States or Federal agencies, as deemed appropriate. The Chief of 
Engineers will not normally coordinate DPRs with Governors or Federal 
Department heads.
    (2) Section 14 and 3 Authorities. The provisions of paragraph (f)(1) 
of this section shall apply to the extent determined feasible by the 
Division Engineer. To be responsive to emergency conditions and to avoid 
undue delays, Division Engineers may permit coordination with States and 
regional offices

[[Page 343]]

of Federal agencies to be effected concurrently with the review of the 
DPR or Recon report by OCE.
    (g) Project approval. With the exception of projects requiring the 
personal attention of the Chief of Engineers, the Director of Civil 
Works is authorized to approve or disapprove projects under this 
Program, for the Chief of Engineers. Projects will be approved on the 
basis of a Detailed Project Report (DPR), except in the case of 
emergencies under Section 14 or 3 Authorities, for which a Recon report 
(developed for the recommended work) may be utilized, (see 
Sec. 263.17(b)(3)). Prior to approving a project for construction, 
requirements for filing an EIS with CEQ must be satisfied, if an EIS has 
been prepared (ER 1105-2-507), a letter of intent for local cooperation 
must be obtained from non-Federal interests in accordance with 
Sec. 263.17(e)(5), and views received from affected States and regional 
offices of Federal agencies must be considered.
    (h) Project construction. Division Engineers may authorize District 
Engineers to commence work on plans and specifications pending project 
approval; however, contracts for construction shall not be entered into, 
nor shall funds be allocated for construction, until the Chief of 
Engineers has approved the project. Procedures for constructing approved 
projects, including the preparation of plans and specifications are 
generally the same as employed for Congressionally authorized projects.
    (i) Hold and save provision. As provided by sec. 9, Pub. L. 93-251 
(88 Stat. 16), ``The requirement * * * that non-Federal interests hold 
and save the United States free from damages due to construction, 
operation, and maintenance of the project, does not include damages due 
to the fault or negligence of the United States or its contractors.'' 
This provision will be reflected in all ``hold and save'' requirements 
of local cooperation.
    (j) Withdrawal of project approval. The Chief of Engineers may 
withdraw approval of a project under the Continuing Authorities Program 
at any time prior to the signing of a written agreement under section 
221, Pub. L. 91-611 (Sec. 263.17(k)).
    (1) Reporting officers shall at least annually review approved 
projects on which construction has not been initiated and shall 
determine if such projects should remain on the backlog awaiting 
construction funds. A recommendation for withdrawal of project approval 
shall be based on the following criteria:
    (i) Local interests are unwilling or unable to provide the necessary 
local cooperation,
    (ii) The project is no longer considered the best solution to the 
problems of the area, considering economic, social, and environmental 
factors, or
    (iii) The project is no longer justified under applicable Federal 
planning criteria.
    (2) Findings which indicate that the project should remain in the 
backlog shall not be reported to OCE. Recommendations for withdrawal of 
project approval shall be transmitted to DAEN-CWP-E, C, or W, or DAEN-
CWO, depending on the project authority.
    (i) Recommendations shall be coordinated with local, State and 
Federal interests consistent with Corps public involvement objectives, 
prior to transmittal to OCE.
    (ii) Recommendations shall be accompanied by a brief Project 
Information Sheet, as required under procedures for recommending project 
deauthorization under section 12, Pub. L. 93-251.
    (3) Reporting officers shall notify appropriate local, State and 
Congressional interests of any final action taken by OCE on 
recommendations for withdrawal of project approval.
    (4) As in the case of project approval, withdrawal of approval may 
be accomplished by the Director of Civil Works, for the Chief of 
Engineers.