Sec. 140.605  Approval actions.

    (a) Authorization to proceed with preliminary engineering and 
acquisition of rights-of-way shall be issued in the same manner as for 
regularly financed Federal-aid projects.
    (b) Authorization of physical construction shall be given in the 
same manner as for regularly financed Federal-aid projects. The total 
cost and Federal funds required, including interest, shall be indicated 
in the plans, specifications, and estimates.
    (c) Projects subject to the reimbursable schedule shall be 
identified as an ``E'' project when the SHA is authorized to proceed 
with all or any phase of the work.
    (d) Concurrence in the award of contracts shall be given.