[Code of Federal Regulations]
[Title 23, Volume 1]
[Revised as of April 1, 2002]
From the U.S. Government Printing Office via GPO Access
[CITE: 23CFR190.5]

[Page 27]
 
                           TITLE 23--HIGHWAYS
 
 CHAPTER I--FEDERAL HIGHWAY ADMINISTRATION, DEPARTMENT OF TRANSPORTATION
 
PART 190--INCENTIVE PAYMENTS FOR CONTROLLING OUTDOOR ADVERTISING ON THE INTERSTATE SYSTEM--Table of Contents
 
Sec. 190.5  Bonus project claims.

    (a) The State may claim payment by submitting a form PR-20 voucher, 
supported by strip maps which identify advertising control limits and 
areas excluded from the claim and form FHWA-1175, for the one-half 
percent bonus claim.
    (b) The bonus payment computation is based on projects or portions 
thereof for which (1) the section of highway on which the project is 
located has been opened to traffic, and (2) final payment has been made. 
A bonus project may cover an individual project, a part thereof, or a 
combination of projects, on a section of an Interstate route.
    (c) The eligible system mileage to be shown for a bonus project is 
that on which advertising controls are in effect. The eligible system 
mileage reported in subsequent projects on the same Interstate route 
section should cover only the additional system mileage not previously 
reported. Eligible project cost is the total participating cost (State 
and Federal share of approved preliminary engineering (PE), right-of-way 
(R-O-W), and construction) exclusive of any ineligible costs. The amount 
of the bonus payment is to be based on the eligible total costs of the 
supporting projects included in each claim.
    (d) Progress vouchers for route sections on which additional one-
half percent bonus payments are to be claimed are to be so identified, 
and the final claim for each route section is to be identified as the 
final voucher.