Sec. 230.409  Contract compliance review procedures.

    (a) General. A compliance review consists of the following elements:
    (1) Review Scheduling (Actions R-1 and R-2).
    (2) Contractor Notification (Action R-3).
    (3) Preliminary Analysis (Phase I) (Action R-4).
    (4) Onsite Verification and Interviews (Phase II) (Action R-5).
    (5) Exit Conference (Action R-6).
    (6) Compliance Determination and Formal Notification (Actions R-8, 
R-9, R-10, R-11, R-12).

The compliance review procedure, as described herein and in appendix D 
provides for continual monitoring of the employment process. Monitoring 
officials at all levels shall analyze submissions from field offices to 
ensure proper completion of procedural requirements and to ascertain the 
effectiveness of program implementation.
    (b) Review scheduling. (Actions R-1 and R-2). Because construction 
work forces are not constant, particular attention should be paid to the 
proper scheduling of equal opportunity compliance reviews. Priority in 
scheduling equal opportunity compliance reviews shall be given to 
reviewing those contractor's work forces:
    (1) Which hold the greatest potential for employment and promotion 
of minorities and women (particularly in higher skilled crafts or 
occupations);
    (2) Working in areas which have significant minority and female 
labor forces within a reasonable recruitment area;
    (3) Working on projects that include special training provisions; 
and
    (4) Where compliance with equal opportunity requirements is 
questionable. (Based on previous PR-1391's (23 CFR part 230, subpart A, 
appendix C) Review Reports and Hometown Plan Reports).

In addition, the following considerations shall apply:
    (5) Reviews specifically requested by the Washington Headquarters 
shall receive priority scheduling;
    (6) Compliance Reviews in geographical areas covered by areawide 
plans would normally be reviewed under the Consolidated Compliance 
Review Procedures set forth in Sec. 230.415.
    (7) Reviews shall be conducted prior to or during peak employment 
periods.
    (8) No compliance review shall be conducted that is based on a home 
office work force of less than 15 employees unless requested or approved 
by Washington Headquarters; and
    (9) For compliance reviews based on an area work force (outside of 
areawide plan coverage), the Compliance Specialist shall define the 
applicable geographical area by considering:
    (i) Union geographical boundaries;
    (ii) The geographical area from which the contractor recruits 
employees, i.e. reasonable recruitment area;
    (iii) Standard Metropolitan Statistical Area (SMSA) or census 
tracts; and
    (iv) The county in which the Federal or Federal-aid project(s) is 
located and adjacent counties.
    (c) Contractor notification (Action R-3). (1) The Compliance 
Specialist should usually provide written notification to the contractor 
of the pending compliance review at least 2 weeks prior to the onsite 
verification and interviews. This notification shall include the 
scheduled date(s), an outline of the mechanics and basis of the review, 
requisite interviews, and documents required.
    (2) The contractor shall be requested to provide a meeting place on 
the day

[[Page 64]]

of the visit either at the local office of the contractor or at the 
jobsite.
    (3) The contractor shall be requested to supply all of the following 
information to the Compliance Specialist prior to the onsite 
verification and interviews.
    (i) Current Form PR-1391 developed from the most recent payroll;
    (ii) Copies of all current bargaining agreements;
    (iii) Copies of purchase orders and subcontracts containing the EEO 
clause;
    (iv) A list of recruitment sources available and utilized;
    (v) A statement of the status of any action pertaining to employment 
practices taken by the Equal Employment Opportunity Commission (EEOC) or 
other Federal, State, or local agency regarding the contractor or any 
source of employees;
    (vi) A list of promotions made during the past 6 months, to include 
race, national origin, and sex of employee, previous job held, job 
promoted into; and corresponding wage rates;
    (vii) An annotated payroll to show job classification, race, 
national origin and sex;
    (viii) A list of minority- or female-owned companies contacted as 
possible subcontractors, vendors, material suppliers, etc.; and
    (ix) Any other necessary documents or statements requested by the 
Compliance Specialist for review prior to the actual onsite visit.
    (4) For a project review, the prime contractor shall be held 
responsible for ensuring that all active subcontractors are present at 
the meeting and have supplied the documentation listed in 
Sec. 230.409(c)(3).
    (d) Preliminary analysis (Phase I) (Action R-4). Before the onsite 
verification and interviews, the Compliance Specialist shall analyze the 
employment patterns, policies, practices, and programs of the contractor 
to determine whether or not problems exist by reviewing information 
relative to:
    (1) The contractor's current work force;
    (2) The contractor's relationship with referral sources, e.g., 
unions, employment agencies, community action agencies, minority and 
female organizations, etc.;
    (3) The minority and female representation of sources;
    (4) The availability of minorities and females with requisite skills 
in a reasonable recruitment area;
    (5) Any pending EEOC or Department of Justice cases or local or 
State Fair Employment Agency cases which are relevant to the contractor 
and/or the referral sources; and
    (6) The related projects (and/or contractor) files of FHWA regional 
or division and State Coordinator's offices to obtain current 
information relating to the status of the contractor's project(s), 
value, scheduled duration, written corrective action plans, PR-1391 or 
Manpower Utilization Reports, training requirements, previous compliance 
reviews, and other pertinent correspondence and/or reports.
    (e) Onsite verification and interviews (Phase II) (Action R-5). (1) 
Phase II of the review consists of the construction or home office site 
visit(s). During the initial meeting with the contractor, the following 
topics shall be discussed:
    (i) Objectives of the visit;
    (ii) The material submitted by the contractor, including the actual 
implementation of the employee referral source system and any 
discrepancies found in the material; and
    (iii) Arrangements for the site tour(s) and employee interviews.
    (2) The Compliance Specialist shall make a physical tour of the 
employment site(s) to determine that:
    (i) EEO posters are displayed in conspicuous places in a legible 
fashion;
    (ii) Facilities are provided on a nonsegregated basis (e.g. work 
areas, washroom, timeclocks, locker rooms, storage areas, parking lots, 
and drinking fountains);
    (iii) Supervisory personnel have been oriented to the contractor's 
EEO commitments;
    (iv) The employee referral source system is being implemented;
    (v) Reported employment data is accurate;
    (vi) Meetings have been held with employees to discuss EEO policy, 
particularly new employees; and

[[Page 65]]

    (vii) Employees are aware of their right to file complaints of 
discrimination.
    (3) The Compliance Specialist should interview at least one 
minority, one nonminority, and one woman in each trade, classification, 
or occupation. The contractor's superintendent or home office manager 
should also be interviewed.
    (4) The Compliance Specialist shall, on a sample basis, determine 
the union membership status of union employees on the site (e.g. whether 
they have permits, membership cards, or books, and in what category they 
are classified [e.g., A, B, or C]).
    (5) The Compliance Specialist shall also determine the method 
utilized to place employees on the job and whether equal opportunity 
requirements have been followed.
    (6) The Compliance Specialist shall determine, and the report shall 
indicate the following:
    (i) Is there reasonable representation and utilization of minorities 
and women in each craft, classification or occupation? If not, what has 
the contractor done to increase recruitment, hiring, upgrading, and 
training of minorities and women?
    (ii) What action is the contractor taking to meet the contractual 
requirement to provide equal employment opportunity?
    (iii) Are the actions taken by the contractor acceptable? Could they 
reasonably be expected to result in increased utilization of minorities 
and women?
    (iv) Is there impartiality in treatment of minorities and women?
    (v) Are affirmative action measures of an isolated nature or are 
they continuing?
    (vi) Have the contractor's efforts produced results?
    (f) Exit conference (Action R-6). (1) During the exit conference 
with the contractor, the following topics shall be discussed:
    (i) Any preliminary findings that, if not corrected immediately or 
not corrected by the adoption of an acceptable voluntary corrective 
action plan, would necessitate a determination of noncompliance;
    (ii) The process and time in which the contractor shall be informed 
of the final determination (15 days following the onsite verification 
and interviews); and
    (iii) Any other matters that would best be resolved before 
concluding the onsite portion of the review.
    (2) Voluntary corrective action plans may be negotiated at the exit 
conference, so that within 15 days following the exit portion of the 
review, the Compliance Specialist shall prepare the review report and 
make a determination of either:
    (i) Compliance, and so notify the contractor; or
    (ii) Noncompliance, and issue a 30-day show cause notice.

The acceptance of a voluntary corrective action plan at the exit 
conference does not preclude a determination of noncompliance, 
particularly if deficiencies not addressed by the plan are uncovered 
during the final analysis and report writing. (Action R-7) A voluntary 
corrective action plan should be accepted with the understanding that it 
only address those problems uncovered prior to the exit conference.
    (g) Compliance determinations (Action R-8). (1) The evidence 
obtained at the compliance review shall constitute a sufficient basis 
for an objective determination by the Compliance Specialist conducting 
the review of the contractor's compliance or noncompliance with 
contractual provisions pursuant to E.O. 11246, as amended, and FHWA EEO 
Special Provisions implementing the Federal-Aid Highway Act of 1968, 
where applicable.
    (2) Compliance determinations on contractors working in a Hometown 
Plan Area shall reflect the status of those crafts covered by part II of 
the plan bid conditions. Findings regarding part I crafts shall be 
transmitted through channels to the Washington Headquarters, Office of 
Civil Rights.
    (3) The compliance status of the contractor will usually be 
reflected by positive efforts in the following areas:
    (i) The contractor's equal employment opportunity (EEO) policy;
    (ii) Dissemination of the policy and education of supervisory 
employees concerning their responsibilities in implementing the EEO 
policy;

[[Page 66]]

    (iii) The authority and responsibilities of the EEO officer;
    (iv) The contractor's recruitment activities, especially 
establishing minority and female recruitment and referral procedures;
    (v) The extent of participation and minority and female utilization 
in FHWA training programs;
    (vi) The contractor's review of personnel actions to ensure equal 
opportunities;
    (vii) The contractor's participation in apprenticeship or other 
training;
    (viii) The contractor's relationship (if any) with unions and 
minority and female union membership;
    (ix) Effective measures to assure nonsegregated facilities, as 
required by contract provisions;
    (x) The contractor's procedures for monitoring subcontractors and 
utilization of minority and female subcontractors and/or subcontractors 
with substantial minority and female employment; and
    (xi) The adequacy of the contractor's records and reports.
    (4) A contractor shall be considered to be in compliance (Action R-
9) when the equal opportunity requirements have been effectively 
implemented, or there is evidence that every good faith effort has been 
made toward achieving this end. Efforts to acheive this goal shall be 
result-oriented, initiated and maintained in good faith, and emphasized 
as any other vital management function.
    (5) A contractor shall be considered to be in noncompliance (Action 
R-10) when:
    (i) The contractor has discriminated against applicants or employees 
with respect to the conditions or privileges of employment; or
    (ii) The contractor fails to provide evidence of every good faith 
effort to provide equal opportunity.
    (h) Show cause procedures--(1) General. Once the onsite verification 
and exit conference (Action R-5) have been completed and a compliance 
determination made, (Action R-8), the contractor shall be notified in 
writing of the compliance determination. (Action R-11 or R-12) This 
written notification shall be sent to the contractor within 15 days 
following the completion of the onsite verification and exit conference. 
If a contractor is found in noncompliance (Action R-10), action efforts 
to bring the contractor into compliance shall be initiated through the 
issuance of a show cause notice (Action R-12). The notice shall advise 
the contractor to show cause within 30 days why sanctions should not be 
imposed.
    (2) When a show cause notice is required. A show cause notice shall 
be issued when a determination of noncompliance is made based upon:
    (i) The findings of a compliance review;
    (ii) The results of an investigation which verifies the existence of 
discrimination; or
    (iii) Areawide plan reports that show an underutilization of 
minorities (based on criteria of U.S. Department of Labor's Optional 
Form 66 ``Manpower Utilization Report'') throughout the contractor's 
work force covered by part II of the plan bid conditions.
    (3) Responsibility for issuance. (i) Show cause notices will 
normally be issued by SHA's to federally assisted contractors when the 
State has made a determination of noncompliance, or when FHWA has made 
such a determination and has requested the State to issue the notice.
    (ii) When circumstances warrant, the Regional Federal Highway 
Administrator or a designee may exercise primary compliance 
responsibility by issuing the notice directly to the contractor.
    (iii) The Regional Federal Highway Administrators in Regions 8, 10, 
and the Regional Engineer in Region 15, shall issue show cause notices 
to direct Federal contractors found in noncompliance.
    (4) Content of show cause notice. The show cause notice must: (See 
sample--appendix A of this subpart)
    (i) Notify the contractor of the determination of noncompliance;
    (ii) Provide the basis for the determination of noncompliance;
    (iii) Notify the contractor of the obligation to show cause within 
30 days why formal proceedings should not be instituted;

[[Page 67]]

    (iv) Schedule (date, time, and place) a compliance conference to be 
held approximately 15 days from the contractor's receipt of the notice;
    (v) Advise the contractor that the conference will be held to 
receive and discuss the acceptability of any proposed corrective action 
plan and/or correction of deficiencies; and
    (vi) Advise the contractor of the availability and willingness of 
the Compliance Specialist to conciliate within the time limits of the 
show cause notice.
    (5) Preparing and processing the show cause notice. (i) The State or 
FHWA official who conducted the investigation or review shall develop 
complete background data for the issuance of the show cause notice and 
submit the recommendation to the head of the SHA or the Regional Federal 
Highway Administrator, as appropriate.
    (ii) The recommendation, background data, and final draft notice 
shall be reviewed by appropriate State or FHWA legal counsel.
    (iii) Show cause notices issued by the SHA shall be issued by the 
head of that agency or a designee.
    (iv) The notice shall be personally served to the contractor or 
delivered by certified mail, return receipt requested, with a 
certificate of service or the return receipt filed with the case record.
    (v) The date of the contractor's receipt of the show cause notice 
shall begin the 30-day show cause period. (Action R-13).
    (vi) The 30-day show cause notice shall be issued directly to the 
noncompliant contractor or subcontractor with an informational copy sent 
to any concerned prime contractors.
    (6) Conciliation efforts during show cause period. (i) The 
Compliance Specialist is required to attempt conciliation with the 
contractor throughout the show cause time period. Conciliation and 
negotiation efforts shall be directed toward correcting contractor 
program deficiencies and initiating corrective action which will 
maintain and assure equal opportunity. Records shall be maintained in 
the State, FHWA division, or FHWA regional office's case files, as 
appropriate, indicating actions and reactions of the contractor, a brief 
synopsis of any meetings with the contractor, notes on verbal 
communication and written correspondence, requests for assistance or 
interpretations, and other relevant matters.
    (ii) In instances where a contractor is determined to be in 
compliance after a show cause notice has been issued, the show cause 
notice will be recinded and the contractor formally notified (Action R-
17). The FHWA Washington Headquarters, Office of Civil Rights, shall 
immediately be notified of any change in status.
    (7) Corrective action plans. (i) When a contractor is required to 
show cause and the deficiencies cannot be corrected within the 30-day 
show cause period, a written corrective action plan may be accepted. The 
written corrective action plan shall specify clear unequivocal action by 
the contractor with time limits for completion. Token actions to correct 
cited deficiencies will not be accepted. (See Sample Corrective Action 
Plan--appendix B of this subpart)
    (ii) When a contractor submits an acceptable written corrective 
action plan, the contractor shall be considered in compliance during the 
plan's effective implementation and submission of required progress 
reports. (Action R-15 and R-17).
    (iii) When an acceptable corrective action plan is not agreed upon 
and the contractor does not otherwise show cause as required, the formal 
hearing process shall be recommended through appropriate channels by the 
compliance specialist immediately upon expiration of the 30-day show 
cause period. (Action R-16, R-18, R-19)
    (iv) When a contractor, after having submitted an acceptable 
corrective action plan and being determined in compliance is 
subsequently determined to be in noncompliance based upon the 
contractor's failure to implement the corrective action plan, the formal 
hearing process must be recommended immediately. There are no provisions 
for reinstituting a show cause notice.
    (v) When, however, a contractor operating under an acceptable 
corrective action plan carries out the provisions of the corrective 
action plan but the actions do not result in the necessary

[[Page 68]]

changes, the corrective action plan shall be immediately amended through 
negotiations. If, at this point, the contractor refuses to appropriately 
amend the corrective action plan, the formal hearing process shall be 
recommended immediately.
    (vi) A contractor operating under an approved voluntary corrective 
action plan (i.e. plan entered into prior to the issuance of a show 
cause) must be issued a 30-day show cause notice in the situations 
referred to in paragraphs (h) (7) (iv) and (v) of this section, i.e., 
failure to implement an approved corrective action plan or failure of 
corrective actions to result in necessary changes.
    (i) Followup reviews. (1) A followup review is an extension of the 
initial review process to verify the contractors performance of 
corrective action and to validate progress report information. 
Therefore, followup reviews shall only be conducted of those contractors 
where the initial review resulted in a finding of noncompliance and a 
show cause notice was issued.
    (2) Followup reviews shall be reported as a narrative summary 
referencing the initial review report.
    (j) Hearing process. (1) When such procedures as show cause issuance 
and conciliation conferences have been unsuccessful in bringing 
contractors into compliance within the prescribed 30 days, the reviewer 
(or other appropriate level) shall immediately recommend, through 
channels, that the Department of Transportation obtain approval from the 
Office of Federal Contract Compliance Programs for a formal hearing 
(Action R-19). The Contractor should be notified of this action.
    (2) Recommendations to the Federal Highway Administrator for hearing 
approval shall be accompanied by full reports of findings and case files 
containing any related correspondence. The following items shall be 
included with the recommendation:
    (i) Copies of all Federal and Federal-aid contracts and/or 
subcontracts to which the contractor is party;
    (ii) Copies of any contractor or subcontractor certifications;
    (iii) Copy of show cause notice;
    (iv) Copies of any corrective action plans; and
    (v) Copies of all pertinent Manpower Utilization Reports, if 
applicable.
    (3) SHA's through FHWA regional and division offices, will be 
advised of decisions and directions affecting contractors by the FHWA 
Washington Headquarters, Office of Civil Rights, for the Department of 
Transportation.
    (k) Responsibility determinations. (1) In instances where requests 
for formal hearings are pending OFCCP approval, the contractor may be 
declared a nonresponsible contractor for inability to comply with the 
equal opportunity requirements.
    (2) SHA's shall refrain from entering into any contract or contract 
modification subject to E.O. 11246, as amended, with a contractor who 
has not demonstrated eligibility for Government contracts and federally 
assisted construction contracts pursuant to E.O. 11246, as amended.