[Code of Federal Regulations] [Title 23, Volume 1] [Revised as of April 1, 2002] From the U.S. Government Printing Office via GPO Access [CITE: 23CFR630.705] [Page 150] TITLE 23--HIGHWAYS CHAPTER I--FEDERAL HIGHWAY ADMINISTRATION, DEPARTMENT OF TRANSPORTATION PART 630--PRECONSTRUCTION PROCEDURES--Table of Contents Subpart G--Advance Construction of Federal-Aid Projects Sec. 630.705 Procedures. (a) An advance construction project shall meet the same requirements and be processed in the same manner as a regular Federal-aid project, except, (1) The FHWA authorization does not constitute any commitment of Federal funds on the project, and (2) The FHWA shall not reimburse the State until the project is converted under Sec. 630.709. (b) Project numbers shall be identified by the letters ``AC'' preceding the regular project number prefix. (c) If the SHA plans to claim bond interest costs under Sec. 630.711, it shall include in its request for authorization the estimated federally participating bond interest cost. (d) The SHA shall submit a final voucher to the FHWA upon completion of the project even though the project has not been converted. If the SHA is claiming bond interest costs under Sec. 630.711, it shall certify on the final voucher that the bond proceeds were expended in the construction of the project and shall include a computation of the eligible interest costs.