                           TITLE 23--HIGHWAYS
 
 CHAPTER I--FEDERAL HIGHWAY ADMINISTRATION, DEPARTMENT OF TRANSPORTATION
 
PART 635--CONSTRUCTION AND MAINTENANCE--Table of Contents
 
                Subpart D--General Material Requirements
 
Sec. 635.411  Material or product selection.

    (a) Federal funds shall not participate, directly or indirectly, in 
payment for any premium or royalty on any patented or proprietary 
material, specification, or process specifically set forth in the plans 
and specifications for a project, unless:
    (1) Such patented or proprietary item is purchased or obtained 
through competitive bidding with equally suitable unpatented items; or

[[Page 191]]

    (2) The State highway agency certifies either that such patented or 
proprietary item is essential for synchronization with existing highway 
facilities, or that no equally suitable alternate exists; or
    (3) Such patented or proprietary item is used for research or for a 
distinctive type of construction on relatively short sections of road 
for experimental purposes.
    (b) When there is available for purchase more than one nonpatented, 
nonproprietary material, semifinished or finished article or product 
that will fulfill the requirements for an item of work of a project and 
these available materials or products are judged to be of satisfactory 
quality and equally acceptable on the basis of engineering analysis and 
the anticipated prices for the related item(s) of work are estimated to 
be approximately the same, the PS&E for the project shall either contain 
or include by reference the specifications for each such material or 
product that is considered acceptable for incorporation in the work. If 
the State highway agency wishes to substitute some other acceptable 
material or product for the material or product designated by the 
successful bidder or bid as the lowest alternate, and such substitution 
results in an increase in costs, there will not be Federal-aid 
participation in any increase in costs.
    (c) A State highway agency may require a specific material or 
product when there are other acceptable materials and products, when 
such specific choice is approved by the Division Administrator as being 
in the public interest. When the Division Administrator's approval is 
not obtained, the item will be nonparticipating unless bidding 
procedures are used that establish the unit price of each acceptable 
alternative. In this case Federal-aid participation will be based on the 
lowest price so established.
    (d) Appendix A sets forth the FHWA requirements regarding (1) the 
specification of alternative types of culvert pipes, and (2) the number 
and types of such alternatives which must be set forth in the 
specifications for various types of drainage installations.
    (e) Reference in specifications and on plans to single trade name 
materials will not be approved on Federal-aid contracts.