[Code of Federal Regulations]
[Title 24, Volume 1]
[Revised as of April 1, 2002]
From the U.S. Government Printing Office via GPO Access
[CITE: 24CFR84.25]

[Page 460-462]
 
                 TITLE 24--HOUSING AND URBAN DEVELOPMENT
 
PART 84-- UNIFORM ADMINISTRATIVE REQUIREMENTS FOR GRANTS AND AGREEMENTS WITH INSTITUTIONS OF HIGHER EDUCATION, HOSPITALS, AND OTHER NON-PROFIT ORGANIZATIONS--Table of Contents
 
                   Subpart C--Post-Award Requirements
 
Sec. 84.25  Revision of budget and program plans.

    (a) The budget plan is the financial expression of the project or 
program as approved during the award process. It may include either the 
Federal and non-Federal share, or only the Federal share, depending upon 
HUD requirements. It shall be related to performance for program 
evaluation purposes whenever appropriate.
    (b) Recipients are required to report deviations from budget and 
program plans, and request prior approvals for budget and program plan 
revisions, in accordance with this section.
    (c) For nonconstruction awards, recipients shall request prior 
approvals from HUD for one or more of the following program or budget 
related reasons.
    (1) Change in the scope or the objective of the project or program 
(even if there is no associated budget revision requiring prior written 
approval).
    (2) Change in a key person specified in the application or award 
document.
    (3) The absence for more than three months, or a 25 percent 
reduction in time devoted to the project, by the approved project 
director or principal investigator.
    (4) The need for additional Federal funding.
    (5) The transfer of amounts budgeted for indirect costs to absorb 
increases in direct costs, or vice versa, if approval is required by 
HUD.
    (6) The inclusion, unless waived by HUD, of costs that require prior 
approval in accordance with OMB Circular A-21, ``Cost Principles for 
Institutions of Higher Education,'' OMB Circular A-122, ``Cost 
Principles for Non-Profit Organizations,'' or 45 CFR part 74 Appendix E, 
``Principles for Determining Costs Applicable to Research and 
Development under Grants and Contracts with Hospitals,'' or 48 CFR part 
31, ``Contract Cost Principles and Procedures,'' as applicable.
    (7) The transfer of funds allotted for training allowances (direct 
payment to trainees) to other categories of expense.
    (8) Unless described in the application and funded in the approved

[[Page 461]]

awards, the subaward, transfer or contracting out of any work under an 
award. This provision does not apply to the purchase of supplies, 
material, equipment or general support services.
    (d) No other prior approval requirements for specific items may be 
imposed unless a deviation has been approved by OMB.
    (e) Except for requirements listed in paragraphs (c)(1) and (c)(4) 
of this section, HUD is authorized, at its option, to waive cost-related 
and administrative prior written approvals required by Circular A-110 
and OMB Circulars A-21 and A-122. Such waivers may include authorizing 
recipients to do any one or more of the following.
    (1) Incur pre-award costs 90 calendar days prior to award or more 
than 90 calendar days with the prior approval of HUD. All pre-award 
costs are incurred at the recipient's risk (i.e., HUD is under no 
obligation to reimburse such costs if for any reason the recipient does 
not receive an award or if the award is less than anticipated and 
inadequate to cover such costs).
    (2) Initiate a one-time extension of the expiration date of the 
award of up to 12 months unless one or more of the following conditions 
apply. For one-time extensions, the recipient must notify HUD in writing 
with the supporting reasons and revised expiration date at least 10 days 
before the expiration date specified in the award. This one-time 
extension may not be exercised merely for the purpose of using 
unobligated balances.
    (i) The terms and conditions of award prohibit the extension.
    (ii) The extension requires additional Federal funds.
    (iii) The extension involves any change in the approved objectives 
or scope of the project.
    (3) Carry forward unobligated balances to subsequent funding 
periods.
    (4) For awards that support research, unless HUD provides otherwise 
in HUD's regulations, the prior approval requirements described in 
paragraph (e) of this section are automatically waived (i.e., recipients 
need not obtain such prior approvals) unless one of the conditions 
included in paragraph (e)(2) of this section applies.
    (f) HUD may, at its option, restrict the transfer of funds among 
direct cost categories or programs, functions and activities for awards 
in which the Federal share of the project exceeds $100,000 and the 
cumulative amount of such transfers exceeds or is expected to exceed 10 
percent of the total budget as last approved by HUD. HUD shall not 
permit a transfer that would cause any Federal appropriation or part 
thereof to be used for purposes other than those consistent with the 
original intent of the appropriation.
    (g) All other changes to nonconstruction budgets, except for the 
changes described in paragraph (j) of this section, do not require prior 
approval.
    (h) For construction awards, recipients shall request prior written 
approval promptly from HUD for budget revisions whenever paragraphs 
(h)(1), (h)(2) or (h)(3) of this section apply.
    (1) The revision results from changes in the scope or the objective 
of the project or program.
    (2) The need arises for additional Federal funds to complete the 
project.
    (3) A revision is desired which involves specific costs for which 
prior written approval requirements may be imposed consistent with 
applicable OMB cost principles listed in Sec. 84.27.
    (i) No other prior approval requirements for specific items may be 
imposed unless a deviation has been approved by OMB.
    (j) When HUD makes an award that provides support for both 
construction and nonconstruction work, HUD may require the recipient to 
request prior approval from HUD before making any fund or budget 
transfers between the two types of work supported.
    (k) For both construction and nonconstruction awards, HUD shall 
require recipients to notify HUD in writing promptly whenever the amount 
of Federal authorized funds is expected to exceed the needs of the 
recipient for the project period by more than $5000 or five percent of 
the Federal award, whichever is greater. This notification shall not be 
required if an application for additional funding is submitted for a 
continuation award.
    (l) When requesting approval for budget revisions, recipients shall 
use the budget forms that were used in the

[[Page 462]]

application unless HUD indicates a letter of request suffices.
    (m) Within 30 calendar days from the date of receipt of the request 
for budget revisions, HUD shall review the request and notify the 
recipient whether the budget revisions have been approved. If the 
revision is still under consideration at the end of 30 calendar days, 
HUD shall inform the recipient in writing of the date when the recipient 
may expect the decision.