[Code of Federal Regulations]
[Title 30, Volume 1]
[Revised as of July 1, 2002]
From the U.S. Government Printing Office via GPO Access
[CITE: 30CFR33.7]

[Page 154]
 
                       TITLE 30--MINERAL RESOURCES
 
  CHAPTER I--MINE SAFETY AND HEALTH ADMINISTRATION, DEPARTMENT OF LABOR
 
PART 33--DUST COLLECTORS FOR USE IN CONNECTION WITH ROCK DRILLING IN COAL MINES--Table of Contents
 
                      Subpart A--General Provisions
 
Sec. 33.7  Date for conducting tests.

    The date of acceptance of an application will determine the order of 
precedence for testing when more than one application is pending, and 
the applicant will be notified of the date on which tests will begin. If 
a unit or system fails to meet any of the requirements, it shall lose 
its order of precedence. If an application is submitted to resume 
testing after correction of the cause of failure, it will be treated as 
a new application and the order of precedence for testing will be so 
determined.